Thursday: Painting IN PROGRESS

Greetings and welcome to the official project blog for your painting project at Cobblestone Lake in Apple Valley! We are looking forward to being onsite with you!

 

Cobblestone Lake Route Map

Route Map 

LCL 1013

Projected Finishing Schedule @ Cobblestone Lake - Updated 10/13

 

Legacy at Cobblestone Lake - Welcome Video

Before Video- Drone footage of the association

 

 

Thursday, October 19th: The NBA tipped off their regular season games on Tuesday and the Timberwolves had their first game in San Antonio last night. Though they couldn't pull off a win, they're hopeful to show off at the Target Center for their home-opener on Friday against the Utah Jazz. 

With this continued sunny and clear weather, the crews are cruising on the last 4 buildings. Buildng #18 & #19 are hopeful to wrap up on Monday, followed by #16 & #17 on Tuesday. Then, all crews will be completing touch ups on all of the buildings. 

LCL tape off addresses

Taping and covering in progress before spraying the siding color. 

LCL covering to spray siding

Taping off the windows before spraying the siding. 

LCL up to the peaks

Sitting on top of the world. 

LCL spray entry way

Spraying the entry way ceilings. 

Wednesday, October 18th: Good morning and Happy Hump Day! 

The crews are carrying on with prepping and finishing the last 4 buildings. We're in the home stretch folks!

We will also be posting red notices on doors that remain to be painted. We ask that you please contact Jesse to schedule a date/time to do so. He can be reached at 612-363-4586. Thanks! 

LCL touch ups on the post

Touch ups on the pillars. 

LCL how many ladders does it take

How many ladders does it take?!

LCL elevation almsot complete

This side of the building is nearing completion and we love its colors!

LCL Spraying trim

Continuing to spray the trim and soffits. 

Monday, October 16th: Good morning residents of Cobblestone Lake. We hope you all had a great weekend! And how about that Viking win?! 

It looks like a beautiful week of weather ahead. We're hoping with the clear and dry weather that we have about a week remaining to complete Buildings 16, 17, 18 & 19.

weather 10 16

Temperatures in the 70s- Woo Minnesota! 

LCL prep work to cover the railings

Covering the railings before spraying the siding. 

LCL prep work covering windows 5

Did we mention how important thorough prep is?

LCL ready to paint trim color

Uncoving and painting the trim. 

LCL Prep for siding spray work

Here comes the sun! 

Friday, October 13th: TGIF and Happy Friday the 13th! 

The border battle showdown is this Sunday at U.S. Bank Stadium. The Packers are in town to take on our Purple People Eaters. Skol Vikes! 

Buildings #10 and #15 are complete and the crews have moved on to start Buildings #16 and #17. They're also continuing with #18 and #19. We anticipate about 8 more working days to get the project complete! 

LCL Spraying window trim 4

Making way across the building to spray the trim. 

LCL Taping before spraying garage doors

Putting down plastic before spraying the the garage doors/frames.

LCL soffits and trim 4

First things first, spraying the trim to really make those siding colors pop!

Thursday, October 12th: It's official, the Timberwolves agreed to a multi-year contract extension with Andrew Wiggins. We can't wait to see what Wiggins will continue to do for the Timberwolves over the next few seasons. Preseason is underway and the regular season will commence on 10/18 in San Antonio against The Spurs. 

Here's a progress update: #10- done today, #15- should be done today with a few hours of touch ups in the morning tomorrow, #16- start tomorrow, #17- potential to start tomorrow, #18- halfway complete, #19- will be halfway complete tomorrow. 

LCL taping before spraying the primer

Taping off sections prior to spraying. 

LCL priming after trim is painted

Starting to spray the new siding color. 

LCLteamwork

Elmer and Rodrigo prove team work is the best kind of work. 

Wednesday, October 11th: Good afternoon residents of Cobblestone Lake! We hope you're all having a good week so far. 

Update on progress: #10- wrap up today, #11- a few doors remain, #14- wrapping up today/tomorrow then move to #15, #16- starting later this week, #18- in progress, and #19- in progress. 

LCL taping before spraying siding

Taping off the sections before spraying the top coat. 

LCL taping the sections before spraying

The crew works to cover sections prior to painting the new colors. 

Tuesday, October 10th: Though the Vikings game wasn't anything to write home about, they did come out with a field goal to win the game. Moving on to the next task-- Green Bay on Sunday at US Bank Stadium. Let's hope for a productive week of practice!

Building #10 will wrap up today and painting continues for Buildings 11, 14, 18, and 19. Thanks! 

LCL trim spraying 4

Covering trim to continue painting the siding colors. 

LCL uncover after spraying trim

Covering trim and railings to spray the siding. 

LCL rolling on the siding color

Using a brush and roller to paint the lower siding. 

Monday, October 9th: Good morning residents of Cobblestone Lake. We hope you all had a great weekend! We're gearing up to watch Monday Night Football as the Vikings take on the Bears in Chicago! Go Vikes!

Here's an update on progress by Building: #10- completed on Tuesday, #11- only door painting remains, #14- a few days left and then this crew will begin on Building #15, #16- projected to start later this week, #18- painting trim & #19- painting trim. We'll post pictures soon. Thanks!

LCL covering and taping windows

Prep work on Building #18.

LCL spraying trim and soffits

Spraying the window trim and soffits. 

LCL taping windows 3

Taping off and covering windows before spraying the trim. 

Friday, October 6th: TGIF! 

Looks like there's some rain in the forecast for this afternoon and then also tomorrow in the earlier part of the day. The crew is working to get as much completed before the rain rolls in this afternoon. 

They're continuing on 10, 11, and 15. Buildings 13 and 15 were completed yesterday and both 18 and 19 were started. Thanks and have a great weekend! 

Thursday, October 5th: The MN Lynx have done it again! They've won the WNBA Championship and this is their 4th title win in the last 7 years. The parade and celebrations are being held outside of Williams Area on the UMN campus in Minneapolis at 6:30pm tonight. 

The crews continue their efforts on Buildings 10, 11, 13, 14, & 15. They've also started prep on #18 & #19. 

LCL ladders up and paint window trim

Removing the tape on one of the buildings. 

LCL spray soffits cool angle

Quite the angle to spray the soffits. 

Wednesday, October 4th: Hello and Happy Wednesday! 

If we may borrow a line from Johnny Nash's hit song, "I can see clearly now the rain is gone." Quite literally, the clouds have cleared and we have a sunshiney day!

The crews are back and in full force. They are continuing to paint on Buildings 10,13, 14, and 15. They'll be starting on #18 and #19 tomorrow as well.

LCL painting trim first spray

Prep and then spraying the trim. 

LCL taping and prepping 4

Taping off edges and covering surfaces before getting the painting started. 

Tuesday, October 3rd: Hello residents of Cobblestone Lake. We were hoping the surfaces would be able to dry out a bit to paint, however, we got quite a bit of rain. The crew will be back onsite tomorrow!

Monday, October 2nd: Good morning and Happy October! We hope you all had a great weekend. 

With all of the rain last night and today, the crew will not be onsite today. We are hopeful that the forecasted rain for tomorrow is brief and that the crew can potentially work in the afternoon. Stay tuned on the blog for specific details. Thanks! 

weather 10 2

Weather week of 10/2. 

Friday, September 29th: TGIF! Lots happening around the Twin Cities this weekend and a major road closure as well- 35W will be closed from Friday at 10pm to Monday at 5am from Crosstown 62 to Downtown. Check into alternate routes if you're headed into downtown this weekend for the Twins, Gopher, Wild or Vikings games or to watch the Marathon on Sunday. Along with lots of sporting events there are plenty of Fall-themed activities- the Renaissance Fair, Sever's Corn Maze, or Valley Scare to name a few. The Parade of Homes is also running this weekend as well. 

We are still on track from our progress update yesterday. We hope you all have a great weekend!

Thursday, September 28th: It's a great day to be a Twins fan!! The MN Twins clinched the second wild-card spot last night when the Chicago White Sox beat the Los Angeles Angels. The players had quite an evening of celebrating in their club house complete with champagne showers and lots of smiles. The team will travel to play either the Yankees or the Red Sox on Tuesday! 

The crew is continuing their painting on Buildings #10-#15. The last two buildings (#18, #19) are also being pressure washed today. 

Quick progress update per building: #10- Continuing to paint and has about a week left, #11- Should be complete Friday or Saturday, #12- Complete on Friday, #13 and #14- Complete Monday or Tuesday, and #15- Complete next week Wednesday or Thursday. The last four buildings will be completed out of order, with #19 being next in line for completion. Thanks! 

LCL pressure washing 18

Pressure washing @ Building 18. 

LCL paint trim onside of building

Prepping and painting the window trim and soffits. 

Wednesday, September 27thGood afternoon! Clear and sunny skies and our painters couldn't be happier for a full day's work @ Legacy at Cobblestone Lake!  

 The crew is continuing with prepping and painting on Buildings #12- #15. They are also pressure washing Buildings 16 & 17 today as well as 18 & 19 tomorrow. They'll then begin on those buildings next week. 

LCL ever pressure wash

Ever pressure washes entry area. 

LCL spray around gargae

Spraying the siding above the garage frame. 

LCL brush and roll on siding color

Brush & Roll. 

LCLspray shutters and trim

Spraying on the new siding color. 

Monday, September 25th: Good morning and Happy Monday! We hope you all enjoyed the hot and sunny weekend weather! With all the rain today, the crew will not be onsite and will return when the substrates have had ample time to dry out- we'll keep you posted as to when this will be! 

As a heads up - the crew will be pressure washing Buildings 16 & 17 on Wednesday, 9/27 and then Buildings 18 & 19 on Thursday, 9/28. We anticipate prep and painting will then begin next week Wednesday, 10/3 for these remaining four buildings. 

weather 9 25

More 'fall-like' temperatures this week!

Friday, September 22nd: TGIF and Happy First Day of Fall, although with the 90 degree heat wave, Minnesota clearly did not get the memo. Regardless, we can all enjoy the warmer weather today and this weekend! 'Tis the season of The Renaissance Festival, Sever's Corn Maze and various apple orchards and pumpkin patches throughout the metro area if you're searching for weekend activities.

The crew is holding steady and current with the updates from yesterday. Looks like rain on Monday, so we'll keep you updated on any weather delays. Have a great weekend! 

Thursday, September 21st: We don't know about you, but we're channeling some Earth, Wind, and Fire on this '21st (night) of September!' 

Video Update for Thursday, 9/21

We are about 70% done with the entire project. The crew is continuing on 4 of the larger buildings (12-15), which will take us into the next 7-10 working days and then only 4 buildings on the East side of the association remain (16-19). We want to thank you for your patience and grace as you've had your window's covered for several days while we spray the siding and paint the trim. It's the best way to prevent overspray, but it does lend a 'caged bird' feel. So we appreciate your understanding and cooperation!  

Wednesday, September 20th: Good afternoon and Happy Hump Day!

The progress update from yesterday still stands for today-  the crews are continuing to paint at Buildings #10- #15.

LCL paint door frame trim

 Window frames and door frames get a fresh coat of white paint. 

LCL paint trim om sides

Building #13 continues with trim painting. 

LCL bldg 15 prep work

Prep work: covering windows and taping are in progress on Building #15. 

Tuesday, September 19th: Good afternoon! We sure like today's weather better than yesterday's rain! 

Here's a quick update: Building #1-#9 are complete aside from a few front doors, #10- the crew is painting the trim, #11- the crew is painting the siding on the front elevation, #12- The crew is painting the siding and trim on the front elevation, #13, the crew is painting trim on 2 sides of the building and they'll start the siding tomorrow, #14 and #15 both started prep and painting today. 

LCL prepping and covering door

Prepping and taping off entry doors. 

LCL trim is sprayed on front

The trim is sprayed and now we'll prep for siding painting.

LCL prep and taping windows

3 ladders up to tape and cover the windows. 

Monday, September 18th: Good morning residents of Cobblestone Lake. We hope you all had a great weekend! 

With the forecasted rain for today, the crews will not be onsite today. With the rest of the week's weather being variable with the potential for more rain, we'll keep you posted as to when they'll be back onsite. Thanks! 

Friday, September 15th: TGIF! We've had such a gorgeous weather week and also a productive painting week at Cobblestone Lake! 

Here's a quick status update: #6- Finishing today, #10, #11, #12- are all working on trim painting, #13 and #14- Pressure washing today and will begin prep/painting next week. Thanks so much and we hope you all have a great weekend! 

LCL PW 13 14

Action shot: spraying the lower edges of the siding. 

LCL pressure wash garage door

Ever sprays the garage door. 

LCL lift to paint peaks

Safety first: hard hats & strapped in!

LCL lift onsite for peaks

Utilizing the lift to reach the peaks.

Thursday, September 14th: It's quite the heat wave Minnesota! Though we can't really complain about the gorgeous weather while it's still here and before Mother Nature throws fall and...winter at us.

The crew is sticking to the schedule and progress posted from Monday. As a reminder, they'll be pressure washing building #14 & #15 tomorrow. Thanks! 

LCL its gutter time

It's gutter time!

LCL taping off front door overhangs front of 6

The front of Building #6 gets taped off and covered.

Tuesday, September 12th: The Vikings got their first win last night, with a 29-19 victory over the New Orleans Saints. Next up, they'll travel to Pittsburgh - bring it on!

Here's an update on buidling status at Cobblestone Lake: #5- Finish today/tomorrow, #6- Side and back are complete, working on front now, #7- Complete, #8- Painting on back and should finish Thursday/Friday, #9- Will finish Wednesday, #10- Start Wednesday, #11- Prepping on front of building and painting front soffits, #12- Start Wednesday, #13- Start prep work tomorrow, #14 & #15 will pressure wash on Friday, 9/15. 

LCL caulk door frames

Caulking and prep work on the front door frame and sidelights. 

LCL cover windows prep

Taping off and covering the shutters. 

LCL paint trim areas

Painting the trim on the front elevation. 

Monday, September 11th: We wanted to take a moment to reflect and remember the victims who lost their lives and also honor all of the heros from September 11th 2001. 

It's an exciting day in MN sports as the Vikings kick off the regular season at U.S. Bank Stadium as they take on the New Orleans Saints at 6pm. The Vikings will honor Randy Moss as he's inducted into the Viking's Ring of Honor during the pre-game. Also, Adrian Peterson will make his appearance as a Saint's RB and face off against his previous team. SKOL VIKINGS!

After pressure washing Buildings 10-13, the crew is now beginning their prep work on Building 10 and 11. They're also continuing on Buildings 6, 8, and 9. 

Friday, September 8th: TGIF! Though the weather has turned a bit cooler, we are not short on outdoor weekend activities. Here are some suggestions for getting out and about and soaking up the weekend weather: Greek Fest near Calhoun, James J. Hill Days in Wayzata, and the NE Food Truck Rally at Able Seedhouse and Brewery. We hope you all have a great weekend! 

The crew is pressure washing Buildings 10 & 11 today and then 12 & 13 tomorrow. They're continuing to paint on Buildings 5, 6, 8 & 9. Building 5 is set to be done on Monday.

LCL bldg 8

Painting the peaks on Building 8.

LCL paint peaks

Painting the peaks and then the trim color. 

Thursday, September 7th: Good morning! With the imminent threat of hurricane Irma to the U.S. and Florida, we are wishing the people of Florida quick and safe evacuations as well as safety to those already affected in Dominican Republic, Haiti, Turks and Caicos, Bahamas, and Cuba. 

The crew is keepin' on at Cobblestone Lake with painting being completed on Buildings 5-9. We'll be pressure washing Buildings 10 and 11 tomorrow as well 12 and 13 on Saturday. We ask you to kindly close your windows and remove any small personal belongings from the outside of your home. Thanks!

LCL tape cover job

Thorough prep is crucial in preventing overspray and producing a crisp and clean finish. 

LCL remove tape off of garage door

Obed takes off the paper after the garage door is sprayed. 

LCL painting accent color on front posts

The accent color on the entry columns get a pop of navy blue.

Wednesday, September 6th: Greetings residents of Cobblestone Lake!

Albeit a few doors and touch ups, the crews are finished with Buildings 1-4. They're starting and also continuing on Buildings 5-9 per our update from yesterday and we are staying on schedule. 

LCL long ladder up

Looking up the ladder, we are tackling the 2nd story siding. 

LCL paint peaks 1

We're starting at the top with the peaks. 

Tuesday, September 5th: Hello and Happy Tuesday! We hope you all had a great, long holiday weekend! The weather looks like a cooler week, but also a dry week, which is perfect for painting! 

weather 9 5

Cooler but dry weather ahead this week!

Here's a run down of progress on Building 1-9: #1- Complete, aside a few doors, #2- Complete, aside 1 door, #3- Painting one peak and a few doors and will finish today, #4- Painting trim and will finish today, #5- Painting the trim on three sides of buildings and will finish on Friday, #6- Start on Thursday, #7- Painting on various parts of building and will finish tomorrow, #8- Prep and painting started today, and #9- Prep and painting started today. 

LCL prepping and taping the trim

Taping off and covering windows prior to spraying. 

LCL spraying siding color

Spraying on the new siding color. 

Friday, September 1st: Happy September!

The crew continues to paint on Building 2, 3, 4, 5, and 7. They'll also be pressure washing Building 9 today. 

We hope you all have a safe and fun holiday weekend! 

Thursday, August 31st: And just like that we're closing out August and moving into September! 

It's a big day for Minnesota sports- Twins vs. White Sox @ 1:10pm, Gophers vs. Buffalo Buffs @ 6pm, and the Vikings vs. Dophins @ 7pm. Lots of cheering and hopefully celebrating ahead!

A few updates on the in-progress buildings: #1 - they are finishing up the peaks and will be done today, #2- complete, but need to redo 1 peak, #3- the peaks need to be painted as well as touch ups and will finish tomorrow, #4- will be completed on Saturday, #5- the trim is complete on 3 sides and they'll begin spraying the siding, #6- will start next week Wednesday, 9/6, #7- the front is almost complete and then they'll move to the sides, #8- we anticipate to start Tuesday, 9/5, #9- Pressure washing will take place tomorrow 9/1. 

LCL 15622 bldg

Trim is next on this building; out with the red and in with the white. 

LCL Jose paints door frame on 7

Jose Paints the door trim on Building 7.

LCL ladders up on 7

Up, up, and away on Building 7. 

Wednesday, August 30th: Good Morning! 

The crews are wrapping up on Building 1-3 today as well as painting on Building 5, 7, and 8. We'll be pressure washing Building 9 on Friday, 9/1. Please close your windows and remove any small items from the exterior of your home. They'll then begin prep and painting on Building 9 next week, Wednesday, 9/6. 

LCL cover windows prep

What goes up, must come down. Off comes the tape. 

LCL roll on color 1

Rolling on the one of the new colors! 

LCL tape and prep 1

Prep work is underway for the next set of buildings. 

LCL taping covering 2

Covering windows in preparation for painting. 

Tuesday, August 29th: Good afternoon residents of Cobblestone Lake!

The crew on building 1 is painting the peaks and will finshing tomorrow, aside from a few front doors. The crew painting on building 2 is also painting the peaks and will finish today. They'll begin building 5 today as well. The crew on building 3 is continuing to paint and will finish tomorrow afternoon. That crew will then move to building 8. Building 4, the largest of the 4 will continue for a few more days. 

Progress video - 8/29

Monday, August 28th: Good afternoon. We hope you all had a great weekend! 

After a rainy few days, the crew is resuming to finishing up the first set of buildings. They'll be starting to prep #7 today and then start #5 either on Tuesday or Wednesday. Pictures coming soon!

Thursday, August 24th: Hello and happy first day of the MN Fair! Al Roker from the Today show helped to kick off this year's MN Fair. Check out the video of him, Andrew Zimmern, and Governer Al Franken showing off some of the fair's fan-favorites and some featured new foods at this year's event.

The crews are continuing on Buildings 1-4. Building 7 is almost complete and then the crew will start on Building 7 on Friday or Saturday, weather permitting. Building 5 could potentially start Saturday as well, again weather permitting. We'll continue to update the schedule above as needed. Also, the reason we're moving out of order is due to the varying building sizes. Thanks!  

Wednesday, August 23rd: Good afternoon and happy hump day! Feeling lucky? Today the Powerball jackpot has reached an estimated $700 million! The odds of winning are still slim - one in more than 292 million, but why not take a chance?!

The crew at building 1 is working on the rear elevation and touch ups elsewhere. The crew at building 2 in painting the white trim on the front elevation and starting to paint the rear elevation. The crew at building 3 is painting on the front and will begin on the back as well. The crew at building 4 is painting on the front elevation. We're anticipating, with continued good weather, that we'll begin prep on building 6 tomorrow and on building 5 on Saturday. 

LCL brush on siding color

Painting the new color at the very top and working our way down. 

LCL garage doorframe

The garage door anad frame get a fresh coat of white paint. 

LCL pillar trim color

The entry way pillar trim is painted white. 

LCL go go gadget

Go-Go-Gadget arms to reach the very top!

Tuesday, August 22nd: Good afternoon and we couldn't be happier to see the sun because it means there's no rain and we have a full painting day!

The crews are resuming painting on Building 1-4. They're painting trim and siding colors. 

LCl spray siding

Spraying the new siding color. 

LCL tape of front overhang trim is painted

Taping off the front overhangs and entryways. 

LCL ladders up and away

Ladders up and the crews are tackling the front elevations. 

LCL team work ladders

Team work to get the 'Big Guy' up and safely on the building. 

Monday, August 21st: Happy Monday and Happy Total Solar Eclipse Day! Here's a link with all things related to the eclipse and safe viewing in MN. Anyone else have Bonnie Tyler's 'Total Eclipse of the Heart' playing on repeat in their head?! 

With some rain over night and forecasted for this afternoon, we have a few of the crews onsite completing some prep work. We'll be back in full force tomorrow with drier and sunnier weather. 

Friday, August 18th: It seems we're having a bit of déjà vu- rain and more rain, though tomorrow looks more promising! Lots of happenings around the Twin Cities ~ free movies in the park, numerous farmer's markets, and the St. Paul food truck festival. We're crossing our fingers for drier weekend weather!

Our carpenters are onsite completing some misc. repairs as well as a crew pressure washing building #8. 

LCL carpentry in progress

Chris completed some carpentry repairs. 

Thursday, August 17th: Hello!

It seems we're having a bit of déjà vu. Mother Nature is continuing to be uncooperative, but we do have a crew onsite pressing on with the pressure washing of Building #7. Stay tuned if we'll be back onsite tomorrow if things can dry out a bit. Thanks! 

Wednesday, August 16th: Good morning! 

The crew is taking note from Starship's "Nothing's Gonna Stop Us Now" and powering through the rain to pressure wash Building #6. It looks like there might be more rain in the forecast for tomorrow so we'll keep you posted when the crews will resume painting. Thanks!

LCL PW 6 1

Ever sprays the front entrance. 

LCL PW 6 take 2

Rain, no problem! The crew washed Building #6 despite wet conditions. 

Tuesday, August 15th: Hello Legacy at Cobblestone Lake! We're less than 10 days out from the start of the MN Fair and Today's Al Roker has announced he'll be onsite to live broadcast on opening day, August 24th. There's a chance also to win tickets to the live broadcast. We can already smell the fried goodness. 

The crews are continuing their prep work and painting on Buildings 1-4. They're also pressure washing Building 5 and will wash 6, 7, and 8 on Wednesday, Thursday, and Friday one a day respectively. 

LCL caulk trim

Step 1: Caulk seams

LCL spraying trim color

Step 2: Spray on the trim color

LCL siding spraying in progress

Step 3: Trim is partially sprayed

LCL prep soffits

Prepping and taping the soffits. 

LCL prep and tape front doors

Taping the front door trim and sidelights. 

LCL trim sprayed bldg1

The trim color is sprayed. 

Monday, August 14th: Good afternoon! We hope you all had a great weekend!

The crew will be getting a later start this afternoon due to all the rain we got over night. They'll be back onsite after lunch time. Thanks!

Prep work is underway on the first 4 buildings. They'll be spraying the soffits first and then working on the siding. 

LCL prep 15620

Caulking seems on the entrances. 

LCL prep tape off bottom

Prepping in progress on the bottom edges. 

LCL teamwork prep steps

The 'handoff.' 

Friday, August 11th: TGIF! The crew is back onsite, in much more welcomed weather! It looks like we're going to have some beautiful weather today and tomorrow!

They're pressure washing the 2nd two buildings #3 and #4 on the site map above. We'll then let the buildings dry over the weekend and be back on Monday to begin the prepping and painting of Buildings 1-4. 

Have a great weekend! 

LCL PW 2nd set

Pressure washing in progress!

LCL PW ever service door

Making sure every surface is washed!

LCL PW ever garage doorJPG

Ever sprays the garage door. 

LCL up and away we go

Straight to the top!

Thursday, August 10th: And they're off!! Your painting project is officially underway and the crew is pressure washing Building 1&2 today and then 3&4 tomorrow. We'll then be back onsite on Monday, 8/14 to begin prepping and painting on Buildings 1-4. 

We are so excited to be onsite and begin your project!

LCL PW 7

Ladders up, up, and away!

LCL PW 4

Marvin utilizes a ladder boost to reach all siding surfaces. 

LCL PW 3

The first step is pressure washing the surfaces so we have a clean slate to work with. 

LCL PW 6

Team Roell is getting the job done!

Thursday, August 3rd: Welcome to the project blog for this summer's painting project at Cobblestone Lake! After much anticipation and thorough deliberation over color schemes, we are ready to roll! We are excited to be a part of the color transformation of your back-to-back style homes as well as the row style homes. We'll be painting all 18 buildings, which includes 138 residences. 

The painting will include prep and finishing of: lap siding, shake siding, fascia, pillars, deck fascia, shutters, select window trim, front doors & frames, garage doors & frames, service doors 7 frames, patio door frames, and decorative corbels. 

We'll begin your project next week Thursday, 8/10 with pressure washing of the 1st and 2nd buildings. Please continue to check the finishing schedule, posted above as it will have the most current information regarding when we'll be at your building/unit. The route map will soon be updated with the designated buildings #s. 

For Pressure Washing: please remove all small belongings/personal items from the exterior of your home to allow for safe and unobstructed access for pressure washing and painting. 

You can find all pertinent project information here on the blog as we'll be updating your page several times a week with progress, pictures, and any changes to the schedule if they come up. 

Thank you again for having us and we'll see you next week! 

 

Jesse Maki

Onsite Job Supervisor

Phone: 612-363-4586

  • This email address is being protected from spambots. You need JavaScript enabled to view it.

Nick Roell

Project Manager

Ph: 763-559-5296

  • This email address is being protected from spambots. You need JavaScript enabled to view it.

Comments (2)

  • Krystal Leitner

    25 September 2017 at 23:03 | #

    Hello, I live at Cobblestone Lake (building 16) and our building will be worked on starting this Wednesday. I haven't seen more specific instructions, so I wanted to ask some questions:

    * Are we able to use our garage at all during painting? We have two cars (one car typically stays in the garage, and the other car in the driveway). If we can't use the garage, we'll make sure both cars are parked in visitor spots.

    * We don't have anything on our deck, so is there anything else we're required to do? Any additional information or assistance would be greatly appreciated.

    Thank you for all your hard work with this project! Take care,

    Krystal Leitner

    reply

    • Dana

      26 September 2017 at 14:32 | #

      Hi Krystal- Thanks for the inquiry. During prep and painting you'll have access to your garage, however, we ask that you please remove cars from the driveway. We'll begin on your building tomorrow with pressure washing - please close windows and remove any small items from the outside of your home. We'll then begin prepping and painting next week, 10/4, which is when we ask that you do not park in the driveway. Please let us know if you have any additional questions. Thanks!

      reply

Leave a comment

You are commenting as guest.

Request Your Free Estimate Today! Get A Free Estimate

facebook btn
linkedin btn
twitter btn
Reoll Painting

facebook btnlinkedin btntwitter btn