Greetings and welcome to your project blog for the painting project at Grove Street Flats in Minneapolis. We are looking forward to being onsite with you!

 

 

Friday, August 31st: Greetings and TGIF! 

The crew is continuing to paint your entry areas, posts, and other misc. touch ups. There are a few remaining items and they hope to wrap things up early next week. Thanks! 

Thursday, August 30th: Hello and good morning! 

The crew is continuing to paint the entry way areas as well as the light posts. They are anticipating to wrap up tomorrow. 

Grove Street lamp posts

Say watt?! Our crew is tackling your light posts today. 

Wednesday, August 29th: Good afternoon! We can hardly believe it's the end of August and September is right around the corner - these cooler mornings have us hoping for a long fall as we're wrapping up our outdoor painting projects. 

The crew at Grove Street has 1-2 more days as yesterday's rain day set them back a little bit. 

Grove Street nestor paint front of building

Nestor paints the door frame in one of your entry ways.

Tuesday, August 28th: Rain Delay

Monday, August 27th: Good morning residents of Grove Street Flats. We hope you all had a great weekend!

The crew is continuing to paint the your entry area posts, railings, awning, etc and they anticipate about 2 more working days. Thanks!

Grove street nestor paint green on front

Nestor is workig on one of the decorative portions of an entry way. 

Grove street azael paint green fence

Azael brushes on the green to the fence. 

Friday, August 24th: Hello and TGIF! 

We've got ourselves a rain day folks. The crew will return once the weather permits. Thanks and have a great weekend! 

Thursday, August 23rd: Good afternoon and happy start of the MN State Fair! The twelve days of fried goodness has begun and it couldn't have been a more perfect day to kick it all off! Be sure to check out the list of new foods, band lineups, and other attractions before heading over to St. Paul! 

Stretchy pants, empty stomachs, can't lose! 

The crew is continuing to prep and paint your fron entry railings, posts, and sidelights.

Grove street hermes paint railings

Hermes, your crew lead is rolling on the paint. 

Grove street saul prep railings

Saul is painting on one of your entry landings. 

Grove street prep on the front 2

Two by two we are taking care of this entry area - posts, awnings, and railings. 

Tuesday, August 21st: Good afternoon!

The crew is prepping and painting your entry railings at the fron of your building. We anticipate the remainder of the project to take 4-5 more working days, with weather being the biggest deterent from our schedule. Thanks!

Grove street paint railings

Hermes and Daisy paint the front area railings. 

Monday, August 20th: Good morning! 

The crew is off and running at Grove Street Flats this morning. They are making their way around the building and pressure washing the areas designated for painting. 

Grove street pressure wash

Pressure washing the divider wall caps. 

Friday, August 17th: Hello and welcome to your project blog! We'll be getting started at your building on Monday, 8/20. We'll begin with pressure washing the awnings as well as prepping and painting on your front railings and lamps posts. 

Welcome to your painting project at Grove Street Flats in Minneapolis!

Isaac Vogel

Project Manager

Ph: 612-578- 2438

  • This email address is being protected from spambots. You need JavaScript enabled to view it.

Leave a comment

You are commenting as guest.

Request Your Free Estimate Today! Get A Free Estimate

facebook btn
linkedin btn
twitter btn
Reoll Painting

facebook btnlinkedin btntwitter btn