Project Complete: Touch ups completed Tuesday/Wednesday

Greetings and welcome to the official blog for your painting project at Lohman's Amhurt in St. Louis Park. We are looking forward to being onsite with you! 

 Lohmans Amhurst Site map

Designated Building Numbers 

Lohmans 8 10

Projected finishing schedule at Lohman's Amhurst- Updated 8/10 

 

Tuesday, August 15th: Hello Old Farm! We're less than 10 days out from the start of the MN Fair and Today's Al Roker has announced he'll be onsite to live broadcast on opening day, August 24th. There's a chance also to win tickets to the live broadcast. We can already smell the fried goodness. 

The crews will be completing touch ups today and tomorrow, weather permitting on buildings #23-36. The final walk through will also be happening Thursday, 8/17.

Monday, August 14th: Good afternoon residents of Lohman's Amhurst! 

The crew finished up on the last few buildings on Satuday. They'll be back onsite Tuesday/Wednesday to complete touch ups on the last 13 buildings (#23-36). 

Thank you so much for all of your cooperation and patience as this was a large undertaking for our crews to complete 36 buildings. But it has been our pleasure being onsite and working with and for you! 

Friday, August 11th: TGIF! After 2 rain days, the crews are back onsite and it's safe to say this gorgeous weather is approved! Looks like we'll have another great day tomorrow!

The crew are painting on the remaining couple buildings today and tomorrow. We'll see how far they get, but they may finish up tomorrow or Monday. 

Have a great weekend! 

Wednesday, August 9th: Good morning! It seems as though Mother Nature has other plans than to continue painting your buildings today. Rain for the rest of today and potentially into tomorrow. We'll keep you updated as to when the crew will return once the rain subsides and the substrates have had time to dry. Thanks! 

Rain Delay @ Lohman's Amhurst

Tuesday, August 8th: Hello and good afternoon!  As we continue into August, the reality of back to school and the 'end of summer' is creeping closer. If you haven't had a chance to go to a movie in the park, this week there are several options from the Minneapolis Park and Recreation: Ghostbusters, Drop Dead Gorgeous, and Moana. Movies begin 15 minutes after sunset. 

Lohmans ever prime siding

Ever spot primes the siding. 

Lohmans scrape prep 5

Scraping and prepping the siding. 

Lohmans tape wndows and caulk shutters

The windows get covered and the shutters are caulked. 

Monday, August 8/7: Good afternoon and happy Monday! We hope you all had a great weekend!

The crews are working on Buildings #24-27 today and will continue their prep/painting of 4 buildings/day. Depending on weather, they should warp up by week's end!

Lohmans roll on siding color

Brushing on the siding paint. 

Lohmans tape roof soffits

Tape work on the roof soffits. 

Lohmans prep and scrape siding

Scraping and prep work IN PROGRESS

Lohmans caulk shutters

Caulking the shutters. 

Isaac and our office mascot Willy were onsite today 8/2.

Friday, August 4th: Hello and TGIF! It's a beautiful day and we've made it to the weekend! There's a lot happening around the cities this weekend. The Uptown and Powderhorn Art Festivals are happening throughout the weekend, various farmer's markets, and if you're up for traveling a bit, Wefest is taking Detroit Lakes by storm with their stellar line up of country starts! Have a great weekend!

The crews are back onsite and prepping and painting on the next set of buildings (#16-19). They'll begin the next grouping tomorrow as well (#20-23). 

Wednesday, August 2nd: Good afternoon and happy hump day! We hope you had an enjoyable National Night Out last night. 

The crews are making their way around to Buildings #16-36 today. They are anticipated to get through all 20 Buildings today and then depending on weather will be back to begin prep on Buildings #16-19 on Friday. 

Lohmans pressure washing phase 2

Phase II of pressure washing is underway.

Lohmans noe pressure wash

Noe sprays the siding on higher ground. 

Lohmans phase 2 pressure wash

First we'll clean the siding, then prep, then paint. 

Tuesday, August 1st: Good morning! Tonight is National Night Out. It is an annual community-building campaign that promotes police-community partnerships and strengthening neighborhood camaraderie. This is all done in an effort to promote safer and more caring places to live. So check out what your neighborhood has planned and join in National Night Out!

The crew is starting buildings #11-15 today. It seems as though they'll be working through 4 buildings a day and we'll do our best to keep you fully updated on the schedule. 

Lohmans caulk shutters

The shutters get prepped and caulked. 

lohmans spot prime 1

The siding gets spot primed. 

Lohmans aerial view

An aerial view of prepping the roof lines. 

Lohmans caulk and prep work

Did we mention how important thorough prep is?!

Monday, July 31st: Good morning Lohman's Amhurst. We hope you all had a great weekend! And just like that we're closing out July and coming into August. 

The crew is finished with Building #1-4 and will start with prep and painting on Buildings #5-10 today.

As a head's up for later this week, the crew will be pressure washing buildings #16-36 on Wednesday, 8/2 and Thursday, 8/3 this week. We'll also be posting notices to alert residents of the pressure washing. For the pressure washing we ask that you please move any small and/or personal items from the outside of your home/deck to allow for safe and unobstructed access for washing and painting. It's not necessary to clear your deck completely. 

We plan to post subsequent notices regarding the specific time we'll be onsite prepping and painting your building. We will also be updating the finishing schedule posted above as we know how quickly the crew are painting each building. 

Lohmans scrape and prep

Prepping the window frame for painting. 

Lohmans spraying siding

Quick reach to spray the siding. 

Friday, July 28th: Good morning and happy Friday!! 

The crew will be prepping and finishing buildings #1-4 today. 

Have a great weekend!

Thursday, July 27th: Good morning! We hope you've all had a great week thus far. 

The crew will be onsite about noon today to begin their prep and painting of the first several buildings. Thanks!

Building #1-4 are underway with prep work: scrape, tape, and covering windows. Prepping and painting will continue on these building tomorrow as well. 

lohmans tape windows

There is never enough tape or plastic when prepping for painting. 

lohmans scrape prep

Thorough prep work is crucial for allowing paint to adhere correctly. 

Lohmans prep

Priming in action. 

Monday, July 24th: Good afternoon residents of Lohman's Amhurst! We hope you all had a great weekend and enjoyed the gorgeous weather! 

The crews are underway and pressure washing the first set of buildings (#1-15). They'll likely be back onsite tomorrow to finish up the pressure washing and then they'll begin the prep and painting on Thursday, 7/27. 

Lohmans pressure wash 1

The first step is spraying and cleaning the surfaces. 

Lohmans pressure wash 3

Our crew is thorough to get all surfaces. 

Lohmans pressure wash

Once the substrates have dried, the crew will be back to begin prepping and painting.

Lohmans pressure wash 4

No spot left un-sprayed! 

Thursday, July 20th: Hello and welcome to your official blog! We are thrilled to be working with and for you this summer! For this year's project we'll be painting select wood substrates on the exterior of your home including: lap siding and window bump outs. 

We'll begin on Monday, 7/24 and Tuesday, 7/25 with pressure washing Buildings #1-15. Please see the site map above as we've designated building numbers starting at the north end of the association and then working our way down Independence Ave., and then counter clockwise onto Gettysburg Ave. 

For pressure washing, we kindly ask that you move any small and/or personal items from the outside of your home/deck to allow for safe and unobstructed access for washing and painting. Note- it is not necessary to completely clear the contents of your deck or patio. 

Once the substrates have had adequate time to dry, the crew will return to begin prepping and finishing of the included surfaces. We anticipate this to begin on Thursday, 7/27. 

We have also posted an anticipated finishing schedule so you can be apprised of when we'll pressure wash, prep, and then paint your building. The blog will also be updated several times a week with progress update, pictures, and any changes to the schedule or weather delays that may come up. 

Thanks so much and we looking forward to being onsite next week! 

Nick Roell

Project Manager

Ph: 763-559-5296

  • This email address is being protected from spambots. You need JavaScript enabled to view it.

Comments (9)

  • susan spannaus

    12 August 2017 at 17:43 | #

    Wow a great job....I put plastic over my patio that really helped but the painters were thorough and helped me clean up...Thanks and happy with the results.

    reply

  • susan spannaus

    12 August 2017 at 01:04 | #

    Hi, I wanted to let you know that you guys did a great job. You cleaned up the mess. I put plastic over everything because I am picky but I was around alot of the today and could not believe they finished our building - Cliffton Court. Again they worked hard and did a great job.
    Thanks to all of you..
    Susan Spannaus

    reply

    • Dana

      13 August 2017 at 17:16 | #

      Hi Susan- Thank you for the kind words! We do have hardworking crews and we're so happy you're thrilled with their workmanship. We'll be sure to pass along the message!

      reply

  • Deborah

    04 August 2017 at 13:48 | #

    Will the windows(glass) be cleaned or are they going to be left with dried water spots from the pressure washing?

    reply

    • Dana

      04 August 2017 at 14:14 | #

      Morning Deborah- With the amount of surface area being cleaned via pressure washing, despite our best efforts, water spots on windows are pretty much an inevitability. While we do not perform the window cleaning, we certainly can recommend a vendor that specializes in this. Let us know if you’d like their contact information. Thanks for the message!

      reply

  • susan spannaus

    01 August 2017 at 20:11 | #

    Hi, I live in Amhurst - Cliffton Court - should I cover my air conditioner and what is your anticipated date 8 /2 or 8/3.
    Thank you.

    reply

    • Dana

      01 August 2017 at 20:25 | #

      Hi Susan- Thank you for the message. There is no need to cover your air conditioner and unfortunately I don't know which day they'll get to your unit. They're going to try and get through as many as they can and with there being different sized buildings, we can't predict how quickly they'll move. Thanks!

      reply

  • Patti Koskovich

    24 July 2017 at 12:20 | #

    Are you washing/painting fences, or only portions of the building that are wood? In my case I have one window on my patio area that has "shutters". I'm assuming you aren't washing brick, only washing/prepping what will be painted?

    reply

    • Dana

      24 July 2017 at 14:46 | #

      Morning Patti- We'll be hand cleaning frames and shutters, but the majority of the project is siding and window bump outs which will be pressure washed. Thanks! Please reach out with any further questions you might have!

      reply

Leave a comment

You are commenting as guest.

Request Your Free Estimate Today! Get A Free Estimate

facebook btn
linkedin btn
twitter btn
Reoll Painting

facebook btnlinkedin btntwitter btn