Maplebrook  Estates - Brooklyn Park

Maplebrook Estates - Brooklyn Park

Quadrant II: Staining IN PROGRESS

Greetings and welcome to the project blog for the upcoming painting project at Maplebrook Estates. We are looking forward to being onsite with you!

Maplebrook map

Site Map - Quadrants labeled

 

Welcome Video

 

 

Tuesday, August 14th: Hello residents of Maplebrook Estates! 

The crew is cruising thorugh the decks, steps, skirts, and posts. We'll let you know when they'll be moving onto the next quadrant for pressure washing - at the earliest, late this week, but likely the early part of next week. Thanks!

Maplebrook stairs complete q2

There is pep in our step with these newly painted stairs. 

Maplebrook q2 complete 2

One of the completed decks in Quadrant II.

Thursday, August 9th: Good afternoon!

The crew has completed their staining in Quadrant I and is currently The crew pressure washing the decks in Quadrant II. They'll finish them today and then resume their staining on Monday, 8/13. Thanks! 

Wednesday, August 8th: Hello residents of Maplebrook Estates! 

Can you believe we're just about a week out from the Great Minnesota Get- Together?! We look forward to the 11 days of food on a stick, live music, animal barns, games, and rides all year and it's right around the corner. If you haven't had a chance to check out the 'new foods' list - here it is. 

The crew is wrapping up the decks in Quadrant I and will begin pressure washing the areas in Quadrant II tomorrow. 

Maplebrook railings done

Up close and personal with your deck boards and railings. 

Maplebrook deck complete 4

Another deck completed at Maplebrook.

Monday, August 6th: Good afternoon! We hope you all had a great weekend!

The crew is continuing to prep and stain the decks in Phase I at Maplebrook. As an FYI, they'll be pressure washing in Phase II on Thursday, 8/9. We'll post some pictures tomorrow!

Friday, August 3rd: Hello and TGIF! 

The crew is holding steady in Quadrant I, but unfortunately the rain has halted their progress for today. They'll resume tomorrow and will need 1-2 more working days to complete the decks in the first quadrant.

Maplebrook completed deck floor

One the finished deck floors - looking great!

Maplebrook completed railings

Floors, railings, posts - check, check, check!

Thursday, August 2nd: Hello and good afternoon!

Brief update: the crew is continuing to stain decks in the first quadrant. We'll be posting some progress pictures soon! 

Tuesday, July 31st: Good afternoon! 

The crew has finished pressure washing the decks in quadrant I and is completing some prep work today in advanace of the staining. They'll begin the staining tomorrow. Thanks!

Friday, July 27th: Good morning and TGIF! 

Maplebrook deck washed

The crew is continuing with their painting of the garage door frames and front door kickplates. We'll begin pressure washing the decks in quadrant 1 on Monday, 7/30. We'll then be back onsite to begin the staining in quadrant 1 on Wednesday, 8/1- weather permitting. When your area is scheduled for pressure washing please remove the contents of your deck for unobstructed access to wash as well as for the staining. Thanks and have a great weekend!

Maplebrook trim scrape and prime

The frame is scraped and primed and ready for painting. 

Maplebrook trim

The garage door frames are looking fresh with a new coat of paint. 

Maplebrook trim 3

One of the completed garage door frames. 

Wednesday, July 25th: Good afternoon! 

Your project is officially underway with the painting of your garage door frames and front door kick plates. Stay tuned for further blue notices for information regarding the pressure washing and staining of your decks. Thanks!

Tuesday, July 24th: Greetings and welcome to your project blog! 

We'll be getting your project underway tomorrow, July 24th with the prep and painting of your garage door frames and front door kick plates. This should have little to no impact on your daily happenings- we just ask you to be mindful of newly painted areas. We anticipate our crew to take about 4 days to complete this portion of the project. 

During your project we'll also be pressure washing and staining your decks. We will divide your association into 4 quadrants to complete the pressure washing and staining to minimize the time needed to have your deck items cleared. Before we begin on your deck/quadrant, we'll post a subsquent notice, alerting you of the date of pressure washing as well as anticipated start date for staining - with weather being the main deterent from this schedule. This Friday, 7/27 we'll be performing an inspection of the decks to identify areas needing repairs. 

Stay tuned here on the blog for further details- route and projected schedule. Thanks and we'll see you tomorrow! 

 

Isaac Vogel

Project Manager

Ph: 612-578- 2438

  • This email address is being protected from spambots. You need JavaScript enabled to view it.

Comments (1)

  • Kris Kuhn

    26 July 2018 at 13:34 | #

    Hi!
    Our deck is definitely in need of some repair but we are going out of town. Can you contact me with what we should do?
    Thanks :)

    reply

Leave a comment