Reoll Painting
MacLaren Hill- St. Paul

MacLaren Hill- St. Paul

1410/1412 Building - Prep & Painting IN PROGRESS

Greetings and welcome to your project blog for the painting project at MacLaren Hill in St. Paul. We are excited to be working with and for you this summer! 

 

MacLaren St. Paul MAP

Site Map @ MacClaren Hill

Welcome Video with Isaac 

 

 

Wednesday, August 15th: Good morning residents of MacClaren. We've posted a progress update video below. Isaac was onsite in the afternoon and we didn't get a chance to post it until today. Thanks! 

Progress update - 8/14 

Tuesday, August 14th: Hello and good morning residents of MacClaren in St. Paul. 

The crew is continuing their prep and painting on the 1410/1412 Building. 

macclaren victor rolls on the siding

Victor rolls on the paint. 

Macclaren caulk and prep spray

Santiago is prepping and caulking on the upper areas. 

Thursday, August 9th:

Progress Update with Isaac

Wednesday, August 8th: Hello!

The crew is continuing with their prep work at MacClaren. They are taping, scraping, and priming. They'll begin their spraying tomorrow. 

MacClaren prep and scrape 1

An aerial view - you can see areas that have been primed and prepped for painting. 

Monday, August 6th: Good afternoon residents of MacClaren Hill in St. Paul! We hope you all had a great weekend!

The crew is off and running at your project in St. Paul. The crew is beginning with prep: scraping and priming areas in advance of painting. 

MacClarensantiago scrape

Santiago scrapes one of the posts. 

MacClaren scrape

Victor scraped the siding- we want to make sure the siding is prepped for painting. 

MacClaren scraped and primed

Did we mention how important thorough prep is?!

Friday, August 3rd: Hello and TGIF!

The crew has completed the pressure washing of the 1410/1412 Building and will return on Monday to begin their prepping and painting. 

Thanks and have a great weekend! 

Wednesday, August 1st: We can't believe it's already August. Where has the time gone?!

The crew is continuing to pressure wash the 1410/1412 Building and will wrap up by later today or tomorrow morning. Then after some dry time, we'll be back to begin prepping and painting. 

McClaren PW up top

Up to the top we go!

Monday, July 30th: Greetings and welcome to your project specific blog for the painting project at MacLaren Hill in St. Paul. We are eager to get the project started!

The crew is beginning today with pressure washing the 1410/1412 Building. Our carpenters are also completing some work on the other 2 buildings. 

Once the pressure washing is complete and the substrates have had time time to dry, we'll resume onsite  with prepping and painting. Thanks!

Maclaren pressure wash 2

Pressure washing on the second level. 

Maclaren pressire wash in progress

Pressure washing the exterior surfaces at MacLaren Hill. 

Isaac Vogel

Project Manager

Ph: 612-578- 2438

  • This email address is being protected from spambots. You need JavaScript enabled to view it.

Leave a comment

You are commenting as guest.

Request Your Free Estimate Today! Get A Free Estimate

facebook btn
linkedin btn
twitter btn
Reoll Painting

facebook btnlinkedin btntwitter btn