Thursday, June 11th - Painting Completed - Walk - Through and Touch-Ups Remain

Greetings and welcome to the official project blog for the painting project at Lakes Citihomes in Minneapolis. We are excited to be working with/for you!

6 1 LCH Schedule

As of 7:55 on Monday, June 1st, this is the latest schedule update for Lakes Citihomes. Buildings #8-#12 should be completed by Thursday if the weather cooperates! 

Wednesday, June 10th: We are thrilled to report that outside of performing our walk-through to put together the project punch list, we are DONE at Lakes Citihomes! Wilmer the gang rallied the last couple of days and took full advantage of the terrific weather, which is lucky because it sounds like Thursday is going to be the storm of the summer! We want to once again thank everybody for their incredible cooperation and patience. Now go enjoy your decks!!!! 

LCH Aerial

LCH Metal Railings Done

Tuesday, June 9th: If you have acrophobia, then the aerial lift at Lakes Citihomes is not the place for you! Thankfully, Wilmer does not fall into that category and consequently, great progress is being made on the 3rd story bumpout decks. As of 10:45 on Tuesday morning, we are on pace to complete these areas by day's end. Wednesday then, will be reserved for completion of the common area metal railings and touch-ups throughout the property. We are soooo grateful for the folks that have reached out with kind words regarding the team at Lakes Citihomes...

"Your guys are so great...thanks for all the good work!"

"Everything looks really great. Your crew does a perfect job and are all lovely and so considerate."

LCH Aerial View

The view from the top at Lakes Citihomes

Monday, June 8th: The lift arrived today at around 11 and the crew has wasted no time getting things underway on the 3rd story bumpout decks. We ask that residents please exercise caution onsite as the lift will be traversing the areas and accessing those decks. We will have a better idea of how many decks the guys are completing per day and we will update you first thing in the morning with the projected scheduling/completion date. Right now, it's looking like it will be Wednesday/Thursday if the weather holds. 

LCH Boom

Up, up and away go the fellas on the 40' aerial lift at Lakes Citihomes

Saturday, June 6th: Now that the bulk of the painting is completed throughout the decking areas, the guys got an early start today and continue tackling the second phase of garage door painting, as well touching up some of the areas where the paint peeled away on the garage doors that have already been painted. With rain in the forecast for the latter part of the day today, the plan is to complete the garage doors by around lunch time. The boom arrives Monday! 

Friday, June 5th: Happy Friday residents of Lakes Citihomes. Your decks are finally dry enough to resume painting and we are excited to report that we are nearing completion on Building #8. We can't thank all the residents enough for all their cooperation! Upon completion of Building #8, we still have common area metal railings to complete, garage doors,  as well as the 3rd story decks which include the following addresses: 3019, 3016, 3015, 3013, 3011, 3010, 3009, 3007, 3005, 3006, 3068, 3066, 3058, 3054, 3052, 3046, 3044, 3042, 3040, 3030, 3024, 3022, 3033, 3035, 3037, 3041, and 3057. The aerial boom will arrive on Monday and they should take about 2-3 days to complete. For all of the above homeowners, please ensure your decks are clear through Wedensday of next week. Thanks! 

Thursday, June 4th: Upon arriving onsite today our job supervisor Wilmer determined that the included areas were still too wet to paint. If we get another full day w/o rain, we will arrive back onsite Friday to hopefully complete all the included areas inaccessible without ladders. If things going according to plan, the aerial lift will be onsite next week to access the 3rd story/rooftop decks. As per usual, thank you to everyone for your patience and understanding as we wrestle with Mother Nature. 

"I'm hoping soon you're gonna find Your way back to me Cause if you say you'll stay The rainy days will go away"

Wednesday, June 3rd: After a slight mixup on the painting route, we're all back on the same page and the guys took advantage of a beautiful day yesterday. They were able to get about 50% of Building #9 (3048-3054) completed, and as soon as the weather cooperates, they will begin work on Building #8 and hopefully complete it by the end of the week. Upon completion of those areas, we will need to spray the remaining garage doors and tackle the decks that will require the use of an aerial lift. However, to minimimze the cost impact of the lift to the association, we need to ensure that the weather will lend itself favorably to painting otherwise you are paying for the lift to sit idle. Please continue to check in for daily updates. Thanks! 

UPDATE - ROUTE CHANGE

After the crew completed building #7, they elected to shift to what is designated as Building #12 and make their way across the last row, with the last building designated for paitning as Building #8. We apologize for any inconvenience and/or confusion this has posed. Thanks for your understanding! 

Tuesday, June 2nd: As the saying goes, make hay while the sun shines! With the probability of rain @ 60% for Wednesday, our plan is to get as much done as we can beforehand. We expect the guys to be onsite until about 8 PM tonight, and if it rains tommorow, obviously we will be shut down outside. As of 10 AM on Tuesday morning, the guys are just wrapping up on Building #11, and the prep on Building #10 is underway. We are forecasting that the crew will complete Building #10 by the end of the day today. 

SalvadorLCPosts

Salvador rolls out one of the posts on Building #11 this morning

Monday, June 1st: Just like American Pharaos upcoming bid for the triple crown, down the stretch they come! The painters, that is! The crew took advantage of a glorious day this past Saturday and have managed to turn the corner towards the last stretch of buildings, starting with Building #8 today. While rain seems to pose a threat this coming Wednesday, the crew should make great headway today and tomorrow and will be nearing completion on the areas accessible without the use of a lift. Depending on what happens with the weather, the plan is to deploy the lift by the weekend, at which point we will be looking to complete all the 3rd story decks. Which reminds us, Wilmer would like to personally thank all the homeowners for their incredible cooperation getting their decks cleared. Because of you, we've been able to work efficiently, despite all the inclement weather. Thank you!!!! 

 Salvador Kenny LCH

Salvador and Kenny say hello from one of the Building #7 decks.

Saturday, May 30th: The guys arrived just after lunch today to resume work on the decks. We had to give the decks adequate time to dry and with the beautiful breezy weather, we did manage to get almost all of Building #7 completed. Have a wonderful Sunday everybody! 

Friday, May 29th: Rains have halted progress at Lakes Citihomes again today but with sun on tap for Saturday, we are planning to put in a long day on Saturday, as more rain is in the forecast for the better part of next week. WORK WILL BEGIN ON BUILDING #7 TOMORROW, AND THE GUYS WILL PROBABLY GET TO BUILDING #8 SO PLEASE PLAN ACCORDINLY SO THE GUYS CAN PAINT IN YOUR AREAS. Thanks for all of your cooperation. 

Wednesday, May 27th: We could hardly believe our eyes when we awoke this morning to....wait for it....SUNSHINE!!!! While the decks are still too damp to resume working on, we are improvising a little bit and beginning work on the garage doors and frames on buildings #1-4. Obviously, vertical surfaces dry more quickly than do horizontal surfaces, so in the interest of moving the project along, we have shifted focus to the doors. After we spray the garage doors at the buildings above, hopefully the decks will be dry enough to begin working on them mid-late afternoon. Thanks! 

 

Our "Top Gun" Wilmer sprays the garage doors on Buildings #1-4

Tuesday, May 26th: Rain has brought the project at Lakes Citihomes to a screeching halt and we will have to monitor the moisture levels on the decks before proceeding. With the amount of rain, it will likely be a couple of days before they are dry to resume finishing. We will post an updated schedule when we return onsite, but right now, we are at least a day behind, with the crew just getting underway on Building #5. While the decks will certainly be too wet to complete, the plan right now is to begin the garage doors on Building #1 and follow the same route as we have been for the decks. Please note that this will have very little impact on your day-to-day routines. If you see evidence of painting obviously happening, it should only take about 1.5 to 2 hours to totally dry. Otherwise, outside of that window, you are free to come and go as you like. 

As always, thanks for your patience and understanding. Fingers crossed for more cooperative weather in the coming days. 

Saturday, May 23rd: Good morning Lakes Citihomes and Happy Memorial Day Weekend. Looks like it is going to be another beautiful day to be outside and that means that work will continue to chug along! The crew is starting on Builiding #4 (3001-3011) and it sounds like there's a decent chance it gets completed today. Enjoy the day! 

LCH Jairo

Jairo scales a ladder on to access a 2nd story deck on Building #3

Friday, May 22nd: Happy Friday everyone...we hope your Memorial Day weekend is off to a great start! If you've been monitoring the project progress on the blog, you've probably deduced that we are finishing about 1 building per day and this should give you a decent idea of when we will be getting to your building. Again, we want to reiterate that we are doing MOST OF THE DECKS ON EACH BUILDING with the exception of the 3rd story bumpout decks, which will be done with the use of an aerial lift near the end of the project. Because the color we've applied is a slightly whiter shade of white, it should be pretty evident which decks have been completed, so you can also use this as your guide for whether or not your deck has been completed. We can say with certainty that buildings #1 and #2 have been completed and as of Friday morning, work is underway on Building #3. 

Thursday, May 21st: After a solid day of work yesterday (it's amazing what gets done when the weather cooperates!) the guys are just getting underway on Building 2 at Lakes Citihomes. Please not that MOST decks on each building are being completed in sequence with the exception of 3rd story "bump-out" decks. Those will be all done near the end of the project when we deploy the aerial lift to safely access those areas. Another noteworthy project detail is that the rooftop decks WILL be completed in the same sequence as the other decks, as those are accessible through the duplex breezeway entrances. You might see painters making their way up to those decks. Thanks for your cooperation to allow them safe access. 

Lakes Citihomes2

Kenny and Salvador get rolling on Building 2. With his orange hat, Salvador should be safe if there are any Deer Hunters onsite. 

UPDATE - 5-20-15

I know that a few residents have expressed concerns that there decks have been only "partially painted." Fear not, residents! The areas that you see areas that have been scraped and "spot primed" with a specialty adhesion primer to lock down the ridges where coating failure is present. As noted below, we wound up getting the scraping/priming completed on about 6 buildings yesterday, and now that the paint has arrived, the fellas have circled back to 3020 to begin painting. They will be following the route specified below and we will do our very best to provide residents with daily updates as to the project progress. We know for certain that residents of Building 1 should exercise caution today, as your decks are being painted. We may make it to Building 2, or Unit 3010, depending on how things go. With weather being a little on the cool side, I would give the paint about 4 hours to dry so in theory, all units we get to today will be dry for certain tomorrow, at which point in time, residents can return items to their decks. Thank you everybody, and special thanks to Chad for reaching out and discussing the project details. 

LCPaintStart

Full painting started this morning! For those areas not in building 1, the areas you see where work has been performed is "spot priming" after the areas have been scraped. We have yet to get to those areas for full re-painting. 

Wednesday, May 20th: In the immortal words of Jerry Garcia, the sun is shining, birds are winging, no rain is falling from a heavy sky. This can only mean one thing...painting is underway finally at Lakes Citihomes! 35 gallons will arrive onsite at about 9:30 and the guys will get going. Yesterday, we wound up scraping and priming on approximately 6 buildins, and we'll be circling back to begin painting those areas. The painting will follow the same route, so for those folks residing in Building 1, and possibly Building 2 (see map below) be advised that we will be working on your decks. As the day progresses we'll have a better idea of how far we'll be getting. 

Thanks! 

Tuesday, May 19th: With temperatures on the rise, the fellas are back in action at Lakes Citihomes. We are scraping and priming, and performing miscellaneous carpentry repairs, and that will continue throughout the day. The paint arrives tomorrow morning and as indicated on the map below, we will be starting at 3020 (Building 1) and following the route as indicated. To see when we will be getting to your address, please check the blog regularly. As you drive in, you can see the Roell Painting yard sign, which will direct you to our website. Upon arrival, click on the "blog" link, then navigate to the Lakes Citihomes project. Any questions, feel free to comment on the blog or reach out to us directly. Thanks! 

LakesCitihomesYardSign

Follow the yard sign to the website, the website to the blog, and the blog to the Lakes Citihomes project. Easy Peasy! 

Monday, May 18th: Happy Monday Lakes Citihomes residents. Wet and cold conditions have once again stopped project progress dead in its tracks, so now we just have to continue to monitor the weather and get back onsite when we can. 57 with sunshine tomorrow, so the guys will be back onsite to begin scraping. We will be following the same route as pressure washing and we will let you know here on the blog when we get to your building and how long we expect your building will take. If you see the below map, we've assigned numbers to each building and from now on, we will be referring to the buildings in this manner as a reference point for painting (i.e. 3020 is Building 1). So, prep and painting will begin tomorrow on Building 1 and as things get underway, we will let you know when building 1 will be completed, and when Building 2 will get started. Make sense?

The only caveat may be that to access the top story decks, we will likely have to utilize an aeril lift. Because we have a limited window of time to rent the lift, we will be doing all those areas at the same time. So, if you have a 3rd story deck, please monitor the schedule on the blog to know when we will be tacklling those specific areas. Thanks! 

LakesCitiHomesNumbers

We've assigned numbers to the buildings as scheduling guideline.

Thursday, May 14th: With rain all day, we thought we'd make good use of our time indoors today! Now you don't have to READ blog updates, you can WATCH them! And eat ice cream simulataneously. 

 

Wednesday, May 13th: Good evening residents of Lakes Citihomes. In amongst the dreary days as of late, today was a beautiful spring day in Minnesota. Although with temperatures being a bit on the cool side, we have to give the substrates adequate time to dry before painting. With the probability of rain currently at a staggering 100%, we are now postponing our return until Friday. 

Weather Forecast May 13th

There are apparently three things that are certain in life. Death. Taxes. And rain on Thursday. 

Monday, May 11th: Now that the pressure washing has been completed at Lakes Citihomes, we need to allow the substrates to dry. THANK YOU, THANK YOU, THANK YOU to all the residents who cleared their decks to allow the crew to wash unencumbered. In advance of Wednesday, we will be getting colors confirmed and crossing our fingers that the rain stays away. You can monitor and schedule updates right here on the blog. Thanks! 

Friday May 8th: After a cloudy first half the day, the sun finally decided to come out and the fellas logged a full day of pressure washing. Special thanks to all the residents, especially Jennifer, Alannah (sp?) and Colleen, for reaching out with questions about the project. We will be back on site Saturday to complete the pressure washing and we want to thank everybody again for clearing off their decks. For those folks who didn't get a chance to clear their decks, we will do our very best to wash around your things. 

IMG_1879.JPG

Project Manager Isaac and Job Supervisor Wilmer get the project underway on Friday morning! 

IMG 1878

Kenny gets the pressure washing started in the NW Corner at Unit 2016B.

Thursday, May 6th: Perhaps you've found your way to the blog as the result of the blue notices posted throughout the property, OR as the result of an email blast sent out by Jared. Having worked with Jared on several projects before, we agree that COMMUNICATION IS THE KEY when it comes to executing a great project. We are excited to get things rolling tomorrow and we want to both notify you (and thank you in advance) for clearing your decking areas in advance of pressure washing, which we are projecting will take 2 full days on both Saturday and Sunday. 

As you can see from the map below, we will be starting at the NW corner of the association at  3020 (including the perimeter wall on Lake St)  and we are hoping to get as far as 3023 by day's end. We will then resume pressure washing on Saturday at 3025 and will continue to make our way until we wrap up at 3022. PLEASE NOTE that this is a projected route and is subject to change depending on various factors (i.e. how easily debris comes off, etc...) so we ask that residents have some wiggle room as to the exact time we get to your unit. With that being said, we do anticipate completing the pressure washing across the entire property by day's end on Saturday so by the end of the day, you will be able to return items to your deck until we return midweek to begin the painting process.  

Lakes Citihomes Pressure Washing

Lastly, the best place to monitor the project progress and know exaclty when you will need items off your deck and when you can return items to your deck will be right here on the blog. We will be providing DAILY STATUS UPDATES which will help prevent you from having to have your charcoal grill as a roommate for the next month! 

Cheers Lakes Citihomes and thank you in advance! We'll see you tomorrow!

Tuesday, May 5th: Good morning Lakes Citihomes! We hope this message finds you well. We are excited to get work underway starting this Friday, May 8th. We will be finishing the decking areas (including undersides), common area metal railings and sign posts, and your garage doors and frames. The first step of the project is pressure washing the included areas, which will begin this coming Friday. We ask that residents remove items from their decking areas to enable the crew to pressure wash them thoroughly. We anticipate the pressure washing will take a minimum of 2-3 days and we will keep you posted of the progress as the project gets underway. For many residents, there will also be a lapse of time between pressure washing and re-finishing the decks, so it won't be necessary to have items off your deck for the entire duration of time. Again, the best resource for staying apprised of the project progress is right here on the blog. We will be posting physical notices onsite as well notifying homeowners of schedule and its impact on your daily routines. Thanks in advance for your cooperation! 

Isaac Vogel

Project Manager

Ph: 612-518-0272

  • This email address is being protected from spambots. You need JavaScript enabled to view it.

Comments (14)

  • Kerri

    02 June 2015 at 15:38 | #

    It sounds like you are finished with building #8 - but you haven't painted 3064 yet? Is that happening today?

    reply

    • Isaac

      02 June 2015 at 16:06 | #

      Kerri,

      Thanks for your message. You are correct...our mistake. The crew elected to transition from Building #7 to Building #12 (shorter ladder moves, etc...) and they are making their way along the back row towards Building #8. We apologize for any confusion/inconvenience this has posed.
      Please feel free to reach out to Isaac with any questions/concerns.

      reply

  • Craig Swygman

    25 May 2015 at 18:30 | #

    Hi Isaac,
    I live in one of the duplex units. The front decks are done, including the stoop coming in from the sidewalk! Good job! Are you going to paint the rooftop decks as well? If so, I don't seem to see it on the blog. I am in unit 3010 B and have a deck on the roof.
    Thanks!
    Craig

    reply

    • Isaac

      25 May 2015 at 20:36 | #

      Hey Craig-thanks for the message. We are doing the rooftop decks and that should have been completed when building #2 was completed. I will connect with Wilmer and follow up to ensure it gets completed at the first opportunity when the weather cooperates. Thanks!

      reply

  • Harry

    22 May 2015 at 14:00 | #

    Hi, it looks like they are working on building # 3 and # 7 Friday morning, does that mean that they will continue to paint both sides of the center courtyard today, and that my unit # 3043 may be done Friday/Saturday?

    Let me know if that is the case and I will remove all of my deck stuff.

    Harry

    reply

    • Isaac

      22 May 2015 at 14:15 | #

      Harry-Good morning and thank you for monitoring the project on the blog! We've just uploaded an updated site map with projected dates per building. This is based on the rate at which we are painting and is subject to slight variations based on building size and/or weather delays. Our projected day for completing your building is Tuesday, 5/26.

      reply

      • Isaac

        22 May 2015 at 14:22 | #

        To clarify, I've spoken to my job supervisor Wilmer regarding Monday (with it being a holiday) and as of right now, he and the crew have expressed a desire to work. That could change between now and Monday, but as of right now, that's the plan. If the residents of Lakes Citihomes would prefer we not work on a holiday, we can certainly accommodate that request as well.

        reply

  • Kerri

    15 May 2015 at 14:40 | #

    I have the same question as Harry - but would like to know when the painting will start for unit 3064 :)

    reply

    • Isaac

      16 May 2015 at 03:22 | #

      Kerri,

      Good evening. Sorry for slight delay in getting back to you. Obviously with rains all week, we've been shut down outside but we are hopeful we will be back onsite Monday to begin the painting. We anticipate the project taking about 3 weeks and we will begin in the NW corner (@ 3020) and we will go building by building, following generally the same route as the pressure washing. All this to say , I think 3064 is at least 1 week away. As we get things underway, we will have a better handle of the progress we are making and we can give you a more precise time frame. Thanks for reaching out!

      reply

      • Isaac

        22 May 2015 at 17:01 | #

        Kerri-See the route map at the top of the blog. Current projection for 3064 is 5/28. Thanks!

        reply

  • Harry

    15 May 2015 at 14:02 | #

    Hi, will the painting follow the same unit sequence as the pressure washing, how many units per day do you plan on completing, and assuming the weather cooperates, what is the target date for painting my unit # 3043?
    Just trying to get a general idea of the time frame.

    reply

    • Isaac

      16 May 2015 at 03:26 | #

      Harry,

      Good evening to you as well sir. As I had mentioned in my response to Kerri, rains have shut us down pretty much all week but we hope to be back onsite Monday to begin painting (weather permitting, fingers crossed!). I would say 3043 is at least a week away and please stay tuned right here with more precise time frames as we get things underway. Once we get a few decks completed, we should have a better idea of time frames and when we will be at your deck. The plan is to go building by building, and we will be providing daily status updates right here on the blog.
      Thanks for reaching out...stay tuned!!!!!

      reply

  • Isaac

    11 May 2015 at 23:15 | #

    Kaitlin-
    Thanks for your message. With the rain throughout the day, our painting start date has been pushed back until Thursday. Thanks for reaching out to confirm.

    reply

  • Kaitlin

    11 May 2015 at 23:11 | #

    Hi there - just want to confirm if you're planning on painting Wednesday or Thursday? The update headline says Thursday, while the body indicates Wednesday. If you could please clarify it'd be greatly appreciated!

    Thanks!

    reply

Leave a comment

You are commenting as guest.

Request Your Free Estimate Today! Get A Free Estimate

facebook btn
linkedin btn
twitter btn
Reoll Painting

facebook btnlinkedin btntwitter btn