Project IN PROGRESS

Greetings and welcome to your project blog for the upcoming painting project at MacClaren Hill in St. Paul. We are excited to be back and painting for your this summer!

 

 

Thursday, June 20th: Good morning! 

The crew is prepping and painting in the 1410 Building. We're anticipating to complete the Building in about 2 weeks from the start, then we'll  move over to the 1412 Building to complete the wall painting in that building. Thanks! 

Maclaren 1410 ceiling

Quite the lift we've got there!

Maclaren 1410

Photos from the ceiling painting.

Wednesday, June 19th: Greetings!

Project Check-In with Isaac 

Tuesday, June 18th: Good afternoon! 

The crew has prepped and painted the ceiling in the 1410 Building today and will move to the 1412 Building first thing tomorrow to prep and paint the tall ceiling only. Then they'll resume their prep and painting of the walls on the 1st, 2nd, and 3rd floors in the 1410 Building. 

Maclaren cover wood trim enamel

 Tackling the taller ceilings first in the 1410 Building.

Maclaren prep in 1410

 Prep, prep , and more prep.

Friday, June 14th: Greetings and TGIF! 

Lots happening around the Twin Cities this weekend to check out --- looks like a beautiful weather weekend as well! The Stone Arch Festival is this weekend, Fri-Sun in Minneapolis along Main St. in Minneapolis and not far from there, Boom Island Festival is Sat-Sun. If you're looking to cheer on the Twinkies, they've got a home- game stretch through next Wednesday and they are crushing it!

The crew is wrapping on the 1370 Building and will begin the 1410 Building on Monday --- starting with ceilings. They'll prep and paint the ceilings only in the 1410 and then in the 1412 Building. We're utilizing a lift to reach the upper areas and want to maximize the efficiency of the lift. Thanks and have a great weekend!

Thursday, June 13th: Greetings! 

It's another beautiful day and the crew has about two and a half floors complete and will wrap up here shortly. The 1410 Building is on deck and will begin next.

MacLaren paint walls 1370bldg

Cutting in around the edges first. 

MacLaren wall painting

Ladders up to apply the wall paint. 

Monday, June 10th: Good afternoon! 

The crew is cruising along and have moved to the 2nd floor of the 1370 Building. They'll be prepping and painting on this floor through tomorrow and will move up to the 3rd floor on Wednesday and they hope to be wrapping up by the end of the week! 

Maclaren plastic cover carpets

Laying plastic to cover the carpets before spraying the ceilings. 

Maclaren prep and cover beams

 Lots of prep involved before spraying the ceilings. 

Maclaren prep and cover for ceiling spraying

Angel and Mathilda prep the floor --- plastic, paper, and tape OH MY!

Maclaren ceilings in action spray

 Up up and away to spray the ceilings. 

Maclaren using ladders and beams to assist in height

Who knew spraying ceilings was an extreme sport? 

Wednesday, June 6th: Good morning! 

The crews are starting with the ceilings on the 1st floor and will also continue to the walls, railings, and enamel. 

Maclaren 1st ceiling

 Go go gadget arms to spray the ceiling at MacLaren.

Maclaren 1st floor

 Brushing and rolling through the entry way. 

Maclaren paint railings

Prepping and painting down the hallway railings.  

Monday, June 3rd: Good morning residents of MacLaren! 

MacLaren crew

Your Crew: Angel, Mathilda, and Jaime

Maclaren interior hallways

The famed 'Before' photo.

MacLaren interior looking up

Things are looking up with Roell Painting onsite at MacLaren!

We are thrilled to be back onsite with you this year! For your 2019 project, we'll be prepping and painting the interior of your 3 buildings, including the entry, hallway, and stairwell ceilings, walls, millwork- doors/frames, and service doors/frames. 

We are starting in the 1370 Building on the 1st floor and we will complete a floor at a time and then we'll move up to the 2nd and then continue to make our way up. 

We are starting with the prep and painting of the ceilings, followed by the millwork and walls. The 1410 Building will be 2nd and then the 1412 Building will be 3rd. 

Continue to follow the project progress here on the blog as we'll project status updates, project photos, and any other pertinent information regarding your project. 

Thanks so much for having us back and we'll looking forward to sprucing up your buildings. 

Isaac Vogel

Project Manager

Ph: 612-578- 2438

  • This email address is being protected from spambots. You need JavaScript enabled to view it.

Leave a comment

You are commenting as guest.

Request Your Free Estimate Today! Get A Free Estimate

facebook btn
linkedin btn
twitter btn
Reoll Painting

facebook btnlinkedin btntwitter btn