Reoll Painting
Waycliffe I- Wayzata

Waycliffe I- Wayzata

Rain Delay

Greetings and welcome to your project blog for the 2018 Painting Project at Waycliffe I in Wayzata! We are looking forward to being back onsite with you this summer!

 

Wayclife I - Tentative Finishing Schedule
Building Pressure Washing Date Prep/Painting Start Date
473/483 Thursday, 5/16 Tuesday, 5/21
435/665 Friday, 5/17 TBD
450/460 TBD TBD
500/510 TBD TBD

 

 

Tuesday, May 21st: Hello!

Updates regarding prep work and when painting will commence

The crew is onsite and prepping away. Due to the impending rain this afternoon and evening the crew is completing some prep steps. They are caulking, scraping, and priming select areas and then when the weather is dry and favorable we'll begin painting. Thanks! 

Waycliffe prep and caulk

 Caulking the seams. 

Waycliffe 1 prep

 Prepping and scraping this section of the 473/483 Building.

Monday, May 20th: Good morning residents of Waycliffe! We hope you all had a great weekend!

In honor of last night's final Game of Thrones episode and the unfortunate weather we're having here in MN, this meme is pretty perfect for today. 

MN winter weather meme

One can only hope this is the last 'cold spell.'

With the temperatures dipping lower than 'usual,' we've postponed our start date at Waycliffe. There also seems to be some wet weather upon us as well this week. We'll keep you updated with our impending arrival --- we just want to make sure the conditions are favorable and in line with our application methods and procedures. Thanks in advance for your patience and understanding!

Friday, May 17th: Good afternoon and TGIF!

The crew is taking care of the 435/665 Building today with pressure washing the exterior. The plan is to return on Monday to begin the prepping and painting of the 473/483 Building. We'll let you know via the blog if the impending weekend rain will affect our start--- thanks so much and have a great weekend!

Waycliffe PW siding of side

Spraying down the siding. 

Waycliffe PW 2nd building

435/665 Building is getting prepping for painting. 

Thursday, May 16th: Good afternoon! 

The crew is off and running at Waycliffe this morning. They are starting on the 473/483 Building with pressure washing the exterior of the building and will return to pressure wash the 435/665 Building tomorrow. 

With weather permitting, we'll then return on Monday to begin prepping and painting on the 473/483 Buildling- stay tuned for further updates. Thanks!

Waycliffe PW

Rain gear, or pressure washing gear rather, is out in full force at Waycliffe. 

Tuesday, May 14th: Good afternoon and welcome to your project blog for the 2018 Painting Project at Waycliffe I in Wayzata! 

We are excited to be back onsite and prepping and painting four of your buildings. We'll begin on Thursday, 5/16 with pressure washing the 473/483 Building. On Friday we will pressure wash the 435/665 Building.

For pressure washing, we kindly ask that you please remove all personal items from your deck for the pressure washing and small items from the outside of your home to allow for safe an unobstructed access while washing. Once the pressure washing is complete, you make return the contents to your deck. 

We'll then return on Monday, 5/20 to begin prepping and painting on your Building (473/483) and we anticipate 4-6 working days to complete your building. We'll be updating the 'Projected Finishing Schedule' above as we know more on completion times or as weather may affect our schedule. 

Please continue to check here on the blog for project updates, progress photos, and any other pertinent info regarding your project.

Thank you again for having us back onsite and we'll see you on Thursday!

Jesse Maki

Onsite Job Supervisor

Phone: 612-363-4586

  • This email address is being protected from spambots. You need JavaScript enabled to view it.

Nick Roell

Project Manager

Ph: 763-559-5296

  • This email address is being protected from spambots. You need JavaScript enabled to view it.

Leave a comment

You are commenting as guest.

Request Your Free Estimate Today! Get A Free Estimate

facebook btn
linkedin btn
twitter btn
Reoll Painting

facebook btnlinkedin btntwitter btn