Project IN PROGRESS

Greetings and welcome to your project blog for the 2019 painting project at Waycliffe II in Wayzata! We are looking forward to being onsite with you!

Waycliffe II

Route Map

 

Welcome to your Project Blog!

 

Building Addresses Pressure Washing Date Prep and Painting Start Date
#1 393/403 Thursday, June 6th Monday, June 10th 
#2 298/308 Thursday, June 6th Monday, June 17th
#3 208/356 Friday, June 7th Weather pending; Week of June 24th
#4 366/376 Friday, June 7th TBD

Tentative Finishing Schedule

 

 

Thursday, June 20th: Good morning!

The crew is prepping and painting on Building #2 and have about a days work left to complete it; however, there is rain in the forecast for the next few days. So we've updated the schedule for a projected start date on the 208/356 Building, likely early-mid week of June 24th. Thanks for your understanding as we just can't control the weather!

Waycliffe II paint paint window bump outs

Painting one of the window bump outs. 

Waycliffe II tape and cover for garage painting

Taping and covering one of the garages. 

Wednesday, June 19th: Greetings! 

The crew is continuing to prep and paint on Building #2 --- scraping, caulking, and priming and once complete they'll begin painting. 

Waycliffe II 2 primer gonig on

Priming in action!

Waycliffe II garage prep and paint

Taping off and prepping to paint the garage. 

Tuesday, June 18th: Good afternoon! 

The crew is continuing to prep and paint on Building #2 and will soon start brushing on the paint as well as spraying the siding. 

Waycliffe II building 2 scrape and prep

Lots of prep going into the siding.

Waycliffe II prep and caulk

Caulking at the seams. 

Waycliffe II scraping siding LOT

Extensive prep and scraping happening on the siding of Building #2.

Friday, June 14th: Hello and TGIF!

Lots happening around the Twin Cities this weekend to check out --- looks like a beautiful weather weekend as well! The Stone Arch Festival is this weekend, Fri-Sun in Minneapolis along Main St. in Minneapolis and not far from there, Boom Island Festival is Sat-Sun. If you're looking to cheer on the Twinkies, they've got a home- game stretch through next Wednesday and they are crushing it!

The crew is painting trim on Building #1 and will be moving into the 2nd Building on Monday starting with some prep work. Thanks and have a great weekend!

Thursday, June 13th: Good afternoon! 

Quick update for you today: the crew is continuing to prep and spray the siding of Building 393/403 as well as starting to paint the trim. We'll have some pictures for you tomorrow! 

Wednesday, June 12th: Greetings! 

The crew is continuing to prep on Building 1; they'll also begin spraying and brush and rolling on the paint! We're looking forward to sprucing up your buildings during your project. 

Waycliffe 2 prep caulk

 Caulking along the seams. 

Waycliffe 2 prep paper

 Ladders up to tape and paper off the soffits. 

Tuesday, June 11th: Good afternoon! 

The crew is not onsite today with the rainy weather today. They'll resume their prep and painting on Building #1 as the weather allows, which we're hopeful will be tomorrow. 

Waycliffe II prep 1

 A prep photo from yesterday, fingers crossed for sunny skies tomorrow!

Thursday, June 6th: Good morning residents of Waycliffe II! 

The crew is off and running this morning! They'll be pressure washing Buildings 1 & 2 today and will pressure wash Buildings 3 & 4 tomorrow. Thanks in advance for moving your items from your decks and outside of your home!

We'll then begin prep and painting on Building 1 on Monday, 6/10. Thanks!

Tuesday, June 4th: Greetings and welcome to your project blog for the upcoming painting project at Waycliffe II in Wayzata! We are looking forward to being onsite! 

We are thrilled to be back onsite and prepping and painting 4 of your buildings. We'll begin with pressure washing the 4 buildings on Thursday, 6/6 and will return to begin prepping and painting on Monday, 6/10. For the pressure washing, we kindly ask that you remove all personal items from your deck and small items from the outside of your home to allow for safe and unobstructed access during washing. Once the washing is complete you may return items to your deck. 

We are anticipating each building to take about 4-6 days to complete. We'll continue to update the schedule posted above as we near start dates for the remaining buildings. Stay tuned here on the blog for project updates, progress photos, and any changes to the schedule should they arise. 

Thanks so much for having us back at Waycliffe II and we'll see you on Thursday for pressure washing!

Isaac Vogel

Project Manager

Ph: 612-578- 2438

  • This email address is being protected from spambots. You need JavaScript enabled to view it.

Leave a comment

You are commenting as guest.

Request Your Free Estimate Today! Get A Free Estimate

facebook btn
linkedin btn
twitter btn
Reoll Painting

facebook btnlinkedin btntwitter btn