Bailey’s Arbor HOA – Woodbury

Project Complete


Greetings and welcome to your project blog for the upcoming painting project at Bailey’s Arbor HOA in Woodbury.  We are thrilled to be back onsite to spruce up your exteriors.

Front Door Scheduling Calendar:

February 2025
Mon
Tue
Wed
Thu
Fri
Sat
Sun
27
28
29
30
31
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
1
2

After making your appointment, if you do not receive a confirmation and/or approval email, please check your spam folder. 


Wednesday, November 6th: Good morning!

The crew has completed all of the added carpentry onsite.  This means your project is officially finished!  It has been a pleasure working with and for you this year.

Monday, October 28th: Greetings!

The crew has completed all painting onsite.  Carpentry has been added and is underway on select units. 

Friday, October 25th: Good afternoon!

Tomorrow is the last and final day to have your front door painted.  If you have not yet had yours painted please use the calendar tool above to schedule an appointment.  If you do not schedule an appointment and have not had your door painted, it will be painted tomorrow in the closed position. 

Wednesday, October 23rd: Good morning!

A production manager will be onsite in the next few days to do a walkthrough and mark any areas in need of touch ups.  The crew will then return to complete the needed touch ups by early next week and your project will be finished!

Friday, October 18th: Greetings!

The crew will be doing a final round of front door painting tomorrow.  Please make sure to sign up for an appointment if you still need your door painted.

Wednesday, October 16th: Good morning!

The crew has just about wrapped things up with your project.  They have a few more doors to complete but the project is officially done.

Thursday, October 10th: Greetings!

The crew is onsite continuing to work their way through your project.  Today they are painting front doors. 

Thursday, October 3rd: Good morning!

The crew has been working diligently on your project and is continuing to make great progress.  They are currently working on painting front doors.  Please remember to schedule an appointment to have your front door painted if you have not done so already.

Monday, September 23rd: Greetings!

The crew is continuing to make great progress on your project.  Today they have gone back to Building #10 to continue prepping and painting.

Wednesday, September 18th: Good morning!

The crew is onsite and has been making great progress this week.  Today they are working on prepping and painting Building # 12.

The sun is out and we are working away!

Friday, September 13th: Greetings!

The crew has made their way to Building # 5.  They will be completing the areas that do not require the use of a high ladder first and then returning to complete the higher areas later on each building. 

Monday, September 9th: Good afternoon!

Happy project start day!  The crew is onsite and your project is officially underway.  They have started prepping and painting at Building # 1.

Hard at work on Building # 1.

Wednesday, September 4th: Greetings Residents of Bailey’s Arbor!

Welcome to your project blog for the upcoming exterior project.  We are excited to be back working together on phase 3 this year!

Please be advised that our crews will soon begin preparation for the upcoming painting project of front doors & frames, garage door frames, entry pillars, and other accent trim.  We are projecting that preparation & painting tasks for the first building will start on Monday, September 9th (weather permitting).

We kindly request that each homeowner be aware of wet paint while entering or exiting their unit.  Roell Painting Company will not be responsible for any damages if paint gets on your clothes or personal belongings.  The included scope of work will take about 4 – 5 weeks to complete; however, your individual unit will take less time to finish the included accent areas.  Please be mindful that weather may alter this finishing schedule.

At a later time, we will be posting a notice regarding painting of the front doors.  This task will require the participation from each resident to paint the front doors in the open position.  We will be providing information on this in the coming weeks.  Overall, this project will have minimal impact to your daily routine.  In order to access the most current project information, view our projected painting schedule or any weather delays/impacts during the project, check back here.

If you have any immediate questions or concerns, please reach out to the contacts below.  We are looking forward to getting started next week!


Jason Schell

Production Manager
Ph: 651-503-2477
Email

Scott Chamberlain

Project Manager
Ph: 612-709-0337
Email