Townview HOA – Eagan

Townview HOA – Eagan

Project Complete 

Greetings and welcome to your project portal for the upcoming painting project at Townview HOA in Eagan. We are thrilled to be working with and for you this summer!


Tuesday, September 7th: Good afternoon! 

The crew is back onsite and starting off at Building 17. They are hopeful to finish the remaining buildings today as well. We’ll then return after areas have been marked with blue tape for touch ups. Thank you!

Completing the fencing on Building 17.

Teamwork on the privacy fencing.

Friday, September 3rd: Good morning!

We’ve got a Friday Rain Day! The crew will return Tuesday to continue with prep and painting. 

Wishing everyone a safe and restful Labor Day! 

Sending our appreciation and respect to the workers of every field. We thank you!

Thursday, September 2nd: Greetings! 

The crew is starting off at Building 16 today — we’re projecting to wrap up next week if we can keep this dry weather around. Thanks!

Building 16 is in progress.

Painting the divider fencing.

Wednesday, September 1st: Good morning! 

The crew is working at Building 15 and will continue along the route – thanks! 

Painting the fencing at Building 15.

Making our way to the finish line at Townview.

Monday, August 30th: Good afternoon! 

After a few rain days, the crew is onsite and resuming their prep and painting at Townview. 

The crew is prepping and painting at Building 12 and the carpentry crew is at Building 14. 

Prepping and caulking privacy fencing.

Painting at Building 12.

Replacing fencing pieces.

Carpentry crew is working at Building 14.

Friday, August 27th: Good morning! 

With all of the rain today and through tomorrow, the crew will tentatively be back on Monday to resume prep and painting. Thank you! 

Tuesday, August 25th: Greetings! 

The crew is back after yesterday’s rain delay. They are prepping and painting at Building 12. 

Refreshing the fencing at Buildig 12.

Monday, August 23rd: Good afternoon! 

The crew is prepping, priming and painting at Building 12. The carpentry crew is working at Building 6 – thank you!

Priming the railings at Building 12.

Carpentry happening at Building 6 this afternoon.

Friday, August 20th: Hello and TGIF! 

The crew is prepping and painting at Building #3 and they carpentry crew is working at Building 8. Thanks and have a great weekend!

Thursday, August 19th: Good morning!

The crew is continuing to prep and prime Building #1. They have also started working on the carpentry for Building #6.

Brushing on primer at Building 1.

Fixing the entry fence at Building 6.

Doing carpentry at Building 6.

Wednesday, August 18th: Greetings!

The crew is onsite today working on scraping, priming and prepping Building #1. 

Prep on Building #1.

Scraping the entry fencing.

Tuesday, August 17th: Good afternoon! 

The crew has completed pressure washing Buildings 1-18 and are finishing up the remaining 2 Buildings throughout the day. 

Monday, August 16th: Good morning! 

The crew in onsite and will be starting with pressure washing at Building 1 and then continuing the route over the next several days. After the areas have had time to dry, they’ll begin prepping and painting the included areas —- front a/c unit covers, fencing at your front entry door – both sides, and also your trash enclosures. 

The carpentry will begin as soon as material arrive either today or tomorrow. Thank you and please reach out if you have any questions. 

Pressure washing the privacy fencing.

Spraying entry fencing.

Wednesday, August 11th: Hello and welcome to your project blog! 

For your project we’ll be pressure washing and finishing front elevation privacy fencing, front elevation a/c surrounds, and the front elevation trash enclosures. We will also be completing carpentry repairs to select areas. 

The crew will kick off with pressure washing and carpentry on Monday, 8/16. For the washing we kindly ask that you remove all small items from your deck and small items from the outside of your home to allow for safe an unobstructed access for washing.

After surfaces have been washed (this will take 5-7 days to wash all 20 Buildings) the crew will return to begin prepping and finishing the included surfaces. The crew will follow the route above for carpentry, washing, and finishing. 

We’ll be onsite for about 5-6 weeks depending on weather delays, but the painting at your specific building will take much less time. Overall, the project will have minimal impact on your daily routine.

The best way to obtain a project status update and any impact it may have on your daily routine will be posted here as we’ll share progress throughout, photos, and any weather delays.

Please reach out to the contacts below if you have any questions.

We’re looking forward to getting started next week!


Dana Clark

Project Manager
Ph: 763-559-5296
Email

2021
Houzz Best Of 2021 - Client Satisfaction

Houzz Best Of 2021 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2020
Best of Houzz 2020 - Client Satisfaction

Best of Houzz 2020 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2019
Best of Houzz 2019 - Client Satisfaction

Best of Houzz 2019 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2018
Best of Houzz 2018 - Client Satisfaction

Best of Houzz 2018 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2017
Best of Houzz 2017 - Client Satisfaction

Best of Houzz 2017 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2016
Best of Houzz 2016 - Client Satisfaction

Best of Houzz 2016 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2015
Best of Houzz 2015 - Client Satisfaction

Best of Houzz 2015 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.

 


Tags:


Leave a comment

Questions? Ask the Blue Tape Guy

roell logo

Office: 763-559-5296
Fax: 763-557-9597
7301 Penn Avenue South
Minneapolis, MN 55423