Prep & Painting IN PROGRESS

Greetings and welcome to the project blog for the painting project at Timber Creek HOA in Eden Prairie. We are thrilled to be onsite with you!


Building Pressure Washing Start Date Tentative Prep/Painting Dates
1 Thursday, June 3rd Thursday, June 10th
2 Thursday, June 3rd Thursday, June 17th
3 Thursday, June 3rd June 21st – June 24th
4 Friday, June 11th June 24th – June 29th
5 Friday, June 11th June 29th – July 2nd
7 Friday, June 11th July 12th – July 16th
14 Friday, June 11th July 9th – July 11th
15 Friday, June 11th July 7th – July 9th
6 TBD July 2nd – July 7th
8 TBD July 13th – July 19th
9 TBD July 20th – July 22nd
10 TBD July 22nd – July 28th
11 TBD July 27th – July 31st
12 TBD July 30th – August 4th
13 TBD August 5th – August 8th


Thursday, June 24th: Good afternoon!

The crew is continuing to make fabulous progress out at Timber Creek. They are finishing up at Building 3 and will be starting the prep/painting at Building 4. 

Teamwork makes the dream work!

Lots of ladders are up & we are ready to get the job done!

Wednesday, June 23rd: Greetings!

Don’t worry Timber Creek, we’ve got you covered.

Isaac is onsite with Marvin!

Windows are covered and ready to go.

A ladder is a painter’s best friend!

Tuesday, June 22nd: Good afternoon!

We have updated our schedule with the tentative prep/painting dates for the remainder of the buildings. These dates are subject to change but we are projecting to follow this schedule for the rest of the summer. The crew is continuing to work on Building 3 today. Prep should begin for Building 4 late tomorrow or Thursday. 

Monday, June 21st: Greetings!

The crew is onsite this morning and accomplishing a lot. Building 2 is now mostly completed and the crew has moved on to Building 3. They started the preparations for Building 3 this morning and will continue working on this building the rest of the day. 

Prep on Building 3 is underway.

Focus is key to getting the job done right!

Thursday, June 17th: Good morning!

The crew has finished up Building 1 and it is looking great. They are now working on the preparations for Building 2 this morning.

Prep for Building 2 is underway!

Prep is looking good so far.

Wednesday, June 16th: Greetings!

The crew is continuing working hard on Building 1. They will be done by the end of the day today or tomorrow morning. Prep for Building 2 will start tomorrow morning and the crew is projecting that it will hopefully be completed by next Monday.

Tuesday, June 15th: Good afternoon!

The crew is onsite and working diligently on Building 1. It’s amazing what can be accomplished with 7 people rowing in the same direction! As large projects often go, it takes a bit for the crew to hit stride, and we were pleased with the progress we saw being made on Building 1. If the schedule holds, we anticipate that the majority of the work on Building 1 will be completed by the end of the day on Wednesday, and preparations will be ongoing on Building 2.  

Covering the adjacent areas thoroughly ensures that paint winds up in the spaces it is supposed to…what a novel concept!

A good, durable paint application involves not only spraying, but backrolling. This ensures that the coating being applied gets “worked in” to underlying substrates. Which in this case, is a fairly porous cedar.

In the immortal words of MC Hammer, “Here Comes the Hammer.” The guys are identifying nails that are sitting proud and pounding them flush!

Friday, June 11th: Greetings!

The crew is onsite pressure washing Buildings 4, 5, 7, 14, and 15 today. 

Pressure washing the side.

Lots of pressure washing today.

Ladders up and we are pressure washing away.

Thursday, June 10th: Good morning!

The crew is onsite today and has started prepping. They will prep Buildings 1 and 2 today and may also get to Building 3.

** UPDATE – we’ll be washing Buildings 4, 5, 7, 14, and 15 starting tomorrow. We are anticipating prep to begin on the 4th Building on Wednesday, 6/23. Thank you! Notices are being posted shortly.

Prepping is underway!

Tuesday, June 8th: Good afternoon!

With the beautiful weather at hand, we are working with your association board to start prepping (scraping, caulking, priming) Thursday and Friday this week. With painting then starting on Monday, June 14th. 

Thursday, June 3rd: Greetings and happy project start day!

The crew is onsite and the pressure washer is ready to roll! The crew has started to wash at Building 1 today. They will make their way around the route to pressure wash all of the buildings. Which will likely take several days to complete.

Carlos power washing the south side elevation.

Dilmer, Marvin, & Hector are ready to go!

Friday, May 28th: Good afternoon!

Welcome to your project blog for the upcoming project at Timber Creek in Eden Prairie. We are looking forward to being onsite this year!

For this year’s project we’ll be prepping and finishing select areas on 15 buildings in your association. 

We have a crew that will be kicking off with pressure washing on Thursday, 6/3 which will likely take the crew several days to complete.

We ask that you please remove any personal belongings from the front entry to allow for safe & unobstructed access to these areas for the washing. The project will take about 5-7 working days per building to complete each of the first three buildings. 

Tentatively, we are planning to start prepping at the first building (weather permitting) on Monday, June 14th.

We will be using our online blog to inform residents of the project status, schedule or any weather delays during the project.

Please reach out to the contacts below if you have any questions. 

We’re looking forward to getting started next week! 

Isaac Vogel

Project Manager
Ph: 612-578-2438
Email

Dana Clark

Project Manager
Ph: 763-559-5296
Email

Jesse Maki

Production Manager
Ph: 612-363-4586
Email

2021
Houzz Best Of 2021 - Client Satisfaction

Houzz Best Of 2021 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2020
Best of Houzz 2020 - Client Satisfaction

Best of Houzz 2020 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2019
Best of Houzz 2019 - Client Satisfaction

Best of Houzz 2019 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2018
Best of Houzz 2018 - Client Satisfaction

Best of Houzz 2018 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2017
Best of Houzz 2017 - Client Satisfaction

Best of Houzz 2017 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2016
Best of Houzz 2016 - Client Satisfaction

Best of Houzz 2016 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2015
Best of Houzz 2015 - Client Satisfaction

Best of Houzz 2015 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.

Tags:


Leave a comment

Questions? Ask the Blue Tape Guy

roell logo

Office: 763-559-5296
Fax: 763-557-9597
7144 Shady Oak Road
Eden Prairie, MN 55344