Timber Creek North – Eden Prairie
Timber Creek North – Eden Prairie
Project Complete
Greetings and welcome to the project blog for the painting project at Timber Creek HOA in Eden Prairie. We are thrilled to be onsite with you!
Building | Pressure Washing Start Date | Tentative Prep/Painting Dates |
1 | Thursday, June 3rd | Thursday, June 10th |
2 | Thursday, June 3rd | Thursday, June 17th |
3 | Thursday, June 3rd | June 21st – June 24th |
4 | Friday, June 11th | June 24th – June 29th |
5 | Friday, June 11th | June 29th – July 2nd |
7 | Friday, June 11th | July 5th – July 9th |
14 | Friday, June 11th | July 5th – July 7th |
15 | Friday, June 11th | June 30th – July 3rd |
6 | Friday, July 2nd/Saturday, July 3rd | Starting on July 13th |
8 | Friday, July 2nd/Saturday, July 3rd | July 16th – July 19th |
9 | Friday, July 2nd/Saturday, July 3rd | Starting on July 21st |
10 | Friday, July 2nd/Saturday, July 3rd | Starting on July 26th |
11 | Monday, July 26th | Monday, August 2nd |
12 | Monday, July 26th | resume on Monday, 8/9 |
13 | Monday, July 26th | Monday, August 16th |
Monday, August 23rd: Good afternoon!
The crew is working on prepping and staining select decks in the association as well as wrapping up on Building 13. Isaac and Jesse are walking the community and marking areas needing touch ups. The crew will begin on these over the next few days as well. Thank you!
Friday, August 16th: Good afternoon!
The crew is prepping and painting the final building at Timber Creek. They are starting off by prepping and covering the the front elevation.
Thursday, August 12th: Greetings
The crew is continuing to make progress prepping and painting Building #12.
Monday, August 9th: Good morning!
We hope you all had a great weekend!
The crew is resuming prep and painting on Building #12 — lots of covering with paper and plastic before we get started painting.
Wednesday, August 3rd: Good morning!
Just as a heads up, work will be paused on Building #12 — we will resume either on Friday 8/6 or Monday 8/9 as soon as Building #11 is complete… and looking ahead at some potential weather delays for tomorrow it will likely be Monday, 8/9. Thank you!
Monday, August 2nd: Hello and happy August!
Is it just us or is time flying by?
The crew is working on prep/painting at Building #11 today. We will have a 2nd crew onsite tomorrow to begin on Building #12 as well.
Thursday, July 29th: Greetings!
The crew is back onsite today after yesterday’s rain delay. They are continuing to prep Building 10, picking up where they left off on Tuesday.
Wednesday, July 28th: Good morning!
The crew will not be onsite today due to the rain. They will return when the surfaces have had time to dry so they can continue working on your project. Have a great rest of your day!
Monday, July 26th: Good afternoon!
The crew is prepping and painting at Building #10 today and also washing buildings 11, 12, and 13 starting today as well.
Friday, July 23rd: Greetings!
The crew is back onsite today after having to leave early because of the rain yesterday. They are picking up where they left off prepping and painting Building 9. Have a great weekend!
Thursday, July 22nd: Good morning!
**Update** Unfortunately due to the rain the crew had to leave early. Hopefully, they will be back tomorrow to continue working on your project but we will have to see what the weather does. Have a great rest of your day!
The crew will be pressure washing the remaining buildings on Monday, 7/26. Building 13 has the possibility to be washed Tuesday, 7/27 depending on how long Buildings 11 and 12 take the crew to wash. We are anticipating that the crew will begin prep/painting Building 11 on Monday, 8/2 but that is a tentative date.
Wednesday, July 21st: Good afternoon!
The crew is continuing along the route and has made their way to Building 9 today. The crew has started prepping and painting Building 9 today and will continue prepping and painting this building the rest of the week.
Tuesday, July 20th: Greetings!
The crew is onsite this morning and they are making great progress on your project. The crew is underway on Building 8. They started prepping Building 8 on Friday, 7/16 and have been continuing to work on this building since.
Thursday, July 15th: Good morning!
The crew is back onsite this morning after yesterday’s rain delay. They are picking up from where they left off on Tuesday prepping Building 6. The crew will be working on this Building for the remainder of the week and will be starting Building 8 either Friday, 7/16 or Saturday, 7/17.
Wednesday, July 14th: Good afternoon!
The crew will not be onsite today due to the rain. They should be back to continue working on your project tomorrow or Friday, weather permitting.
Tuesday, July 13th: Greetings!
The crew is continuing to work diligently on your project and they are making great progress. They started working on Building 6 today and will continue working on this building throughout the week, weather permitting.
Friday, July 9th: Good afternoon and TGIF!
The crew is working on Building 7. We’ve posted an updated schedule above. Please know this is tentative and has flexibility to change ahead or later due to weather, etc. Thanks so much for your cooperation and patience as we make our way through Timber Creek. Thanks!!
Wednesday, July 7th: Greetings!
The crew is back onsite today and continuing their work on your project. They are currently working on Building 7.
Tuesday, July 6th: Good morning!
We hope you all had a great weekend! The crew will not be onsite today but we should be back tomorrow or Thursday, weather permitting.
Friday, July 2nd: Greetings!
Wednesday, June 30th: Good morning!
The crew is continuing their diligent work on your project. They are currently prepping and painting at Building 5. The crew will be pressure washing Buildings 6, 8, 9, & 10 on Friday 7/2 or Saturday, 7/3.
Tuesday, June 29th: Good afternoon!
Monday, June 28th: Greetings!
We hope you all had a great weekend. The crew is onsite today and they are finishing up at Building 4. They are also starting the prep on Building 5 today as well.
Thursday, June 24th: Good afternoon!
The crew is continuing to make fabulous progress out at Timber Creek. They are finishing up at Building 3 and will be starting the prep/painting at Building 4.
Wednesday, June 23rd: Greetings!
Don’t worry Timber Creek, we’ve got you covered.
Tuesday, June 22nd: Good afternoon!
We have updated our schedule with the tentative prep/painting dates for the remainder of the buildings. These dates are subject to change but we are projecting to follow this schedule for the rest of the summer. The crew is continuing to work on Building 3 today. Prep should begin for Building 4 late tomorrow or Thursday.
Monday, June 21st: Greetings!
The crew is onsite this morning and accomplishing a lot. Building 2 is now mostly completed and the crew has moved on to Building 3. They started the preparations for Building 3 this morning and will continue working on this building the rest of the day.
Thursday, June 17th: Good morning!
The crew has finished up Building 1 and it is looking great. They are now working on the preparations for Building 2 this morning.
Wednesday, June 16th: Greetings!
The crew is continuing working hard on Building 1. They will be done by the end of the day today or tomorrow morning. Prep for Building 2 will start tomorrow morning and the crew is projecting that it will hopefully be completed by next Monday.
Tuesday, June 15th: Good afternoon!
The crew is onsite and working diligently on Building 1. It’s amazing what can be accomplished with 7 people rowing in the same direction! As large projects often go, it takes a bit for the crew to hit stride, and we were pleased with the progress we saw being made on Building 1. If the schedule holds, we anticipate that the majority of the work on Building 1 will be completed by the end of the day on Wednesday, and preparations will be ongoing on Building 2.
Friday, June 11th: Greetings!
The crew is onsite pressure washing Buildings 4, 5, 7, 14, and 15 today.
Thursday, June 10th: Good morning!
The crew is onsite today and has started prepping. They will prep Buildings 1 and 2 today and may also get to Building 3.
** UPDATE – we’ll be washing Buildings 4, 5, 7, 14, and 15 starting tomorrow. We are anticipating prep to begin on the 4th Building on Wednesday, 6/23. Thank you! Notices are being posted shortly.
Tuesday, June 8th: Good afternoon!
With the beautiful weather at hand, we are working with your association board to start prepping (scraping, caulking, priming) Thursday and Friday this week. With painting then starting on Monday, June 14th.
Thursday, June 3rd: Greetings and happy project start day!
The crew is onsite and the pressure washer is ready to roll! The crew has started to wash at Building 1 today. They will make their way around the route to pressure wash all of the buildings. Which will likely take several days to complete.
Friday, May 28th: Good afternoon!
Welcome to your project blog for the upcoming project at Timber Creek in Eden Prairie. We are looking forward to being onsite this year!
For this year’s project we’ll be prepping and finishing select areas on 15 buildings in your association.
We have a crew that will be kicking off with pressure washing on Thursday, 6/3 which will likely take the crew several days to complete.
We ask that you please remove any personal belongings from the front entry to allow for safe & unobstructed access to these areas for the washing. The project will take about 5-7 working days per building to complete each of the first three buildings.
Tentatively, we are planning to start prepping at the first building (weather permitting) on Monday, June 14th.
We will be using our online blog to inform residents of the project status, schedule or any weather delays during the project.
Please reach out to the contacts below if you have any questions.
We’re looking forward to getting started next week!
Roell Painting
Dana Clark
Houzz Best Of 2021 - Client Satisfaction
Best of Houzz 2020 - Client Satisfaction
Best of Houzz 2019 - Client Satisfaction
Best of Houzz 2018 - Client Satisfaction
Best of Houzz 2017 - Client Satisfaction
Best of Houzz 2016 - Client Satisfaction
Best of Houzz 2015 - Client Satisfaction
Tags: Completed Projects