Bellante HOA – Lakeville

Bellante HOA – Lakeville

Project Complete

Greetings and welcome to your project portal for the upcoming painting project at Bellante HOA in Lakeville. We are thrilled to be back working with and for you this summer!

Building Pressure Washing Start Date Prep/Painting Start Date
Building 1: 18218-18220 Monday, 6/14 Wednesday, 6/16
Building 2: 18222-18224 Monday, 6/14 Friday, 6/18
Building 3: 18240-18242 Wednesday, 6/16 Friday, 6/18
Building 4: 18236-18238 Wednesday, 6/16 Tuesday, 6/22
Building 5: 18244-18246 Thursday, 6/24 Monday, 6/28
Building 6: 18225-18227 Thursday, 6/24 Tuesday, 6/29
Building 7: 18241-18243 Thursday, 6/24 Wednesday, 7/7
Building 8: 18273-18275 Thursday, 7/1 Wednesday, 7/7
Building 9: 18300 Thursday, 7/1 Monday, 7/12
Building 10: 18304 Thursday, 7/1 Friday, 7/16
Building 11: 18320 Thursday, 7/1 Monday, 7/19
Building 12: 18350-18354 Thursday, 7/1 Monday, 7/26

Wednesday, August 4th: Good morning! 

Monday, July 19th: Greetings!

The crew is continuing to work diligently on your project and they are making great progress. They have started the prep work at Building 11 today and will be working on this Building for the remainder of the day.

Covering the windows with plastic to protect them from the paint.

The deck door and more windows have been covered.

Friday, July 16th: Good morning!

The crew is back onsite after the rain delay. They are picking up where they left off on Tuesday prepping and painting at Building 9. The crew has also started prepping and painting at Building 10 today as well. 

Spraying on the paint underneath the deck area.

The windows are covered and we are ready to paint.

Our ladders are up & we are ready to paint today!

Wednesday, July 14th: Good afternoon!

The crew will not be onsite today due to the rain. They should be back to continue working on your project tomorrow or Friday, weather permitting. 

Monday, July 12th: Greetings!

The crew is keeping on their projected schedule for your project. They have started prepping Building 9 today.

Preparations on Building 9 are underway.

Covering the windows to prepare for painting.

Friday, July 9th: Good morning and TGIF! 

The crew is continuing to prep and paint at Building 7 and 8. They are anticipating to start on Building 9 on Monday. 

Thanks and have a great weekend!

Going up to spray the siding.

Sprayed and ready to dry.

Building #8 is underway.

Wednesday, July 7th: Greetings!

The crew is back onsite today and is continuing to work diligently on your project. They are starting to prep and paint Buildings 7 and 8 today. 

Garage door prep.

The ladders are up & the windows are being prepped!

Tuesday, July 6th: Good morning!

We hope you all had a great weekend! The crew will not be onsite today but we should be back tomorrow or Thursday, weather permitting. 

Friday, July 2nd: Greetings!

Wednesday, June 30th: Good morning!

The crew is onsite and continuing to work diligently on Building 6. They are picking up on prepping and painting from where they left off yesterday.

The windows are prepped on Building 6.

Backrolling the paint.

Tuesday, June 29th: Good afternoon!

Monday, June 28th: Greetings!

The crew has started prepping and painting Building 5 today and will begin prepping at Building 6 tomorrow. They will be pressure washing the remainder of the Buildings on Thursday, 7/1. 

Thursday, June 24th: Good afternoon!

The crews are working on pressure washing Buildings 5, 6, and 7 today. They are also continuing to paint Building 4. A good, durable paint application involves not only spraying but back rolling. This ensures that the coating being applied gets “worked in” to underlying substrates. Which you can see the crew doing in the pictures below!

Spraying the paint on Building 4.

Back rolling after the paint has been sprayed on.

Another picture of back rolling in action.

Wow! Look at those results.

Monday, June 21st: Greetings!

We have updated our route map and schedule to now show all 12 buildings for the entire project this summer. The crew will start painting at Building 4 tomorrow. They plan on pressure washing Buildings 5, 6, and 7 on Thursday, 6/24. The crew will then return on Monday, 6/28 to begin prepping and painting at Building 5.

Friday, June 18th: Good afternoon!

The crew is continuing their diligent work at Building 1 today. They have also started prepping Building 2. Have a great weekend!

Prepping is underway at Building 2.

The preparations are looking good.

Thursday, June 17th: Greetings!

The crew has begun prepping at Building 1. They also started spraying at Building 1 as well.

Prepping is underway at Building 1.

We are ready to work on this beautiful Friday.

Spraying has begun!

Wednesday, June 16th: Good afternoon!

The crew is onsite working on Building 1. They are painting the trim and frames today.  Tomorrow the crews will begin prepping Building 1 for spraying. They pressure washed Building 3 today as well.

Painting the window trim.

Ladders are up & we are ready to go.

Monday, June 14th: Good morning!

The crew is off and running at Bellante this morning and the pressure washer is ready to roll! They have started washing at Building 1 and will make their way around the route to pressure wash all of the buildings today.

Your project is underway!

Pressure washing your buildings.

Friday, June 11th: Greetings residents of Bellante!

Welcome to your project blog for the upcoming painting project. We are looking forward to refreshing your exteriors.

Our crew will be kicking off on Monday, 6/14 with pressure washing your buildings. We are predicting the washing of each building to take one day. 

We kindly request that you please remove any and all small personal belongings from the outside of your home for the pressure washing to allow for safe and unobstructed access for washing. Please be sure to have your exterior water spigot turned on for the crew to utilize for washing.

Once the substrates have had time to dry, the crew will be back to start prepping & painting the exterior of your building. We are projecting this prepping & finishing to start on Wednesday, 6/16. 

This is a large project that will likely take about 5-7 weeks to complete all buildings.  In order to access the most current updates, check back here frequently to view any posted weather delays or other scheduling updates. Please reach out to the contacts below if you have any questions.

We’re looking forward to getting started next week!


Dana Clark

Project Manager
Ph: 763-559-5296
Email

2021
Houzz Best Of 2021 - Client Satisfaction

Houzz Best Of 2021 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2020
Best of Houzz 2020 - Client Satisfaction

Best of Houzz 2020 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2019
Best of Houzz 2019 - Client Satisfaction

Best of Houzz 2019 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2018
Best of Houzz 2018 - Client Satisfaction

Best of Houzz 2018 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2017
Best of Houzz 2017 - Client Satisfaction

Best of Houzz 2017 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2016
Best of Houzz 2016 - Client Satisfaction

Best of Houzz 2016 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2015
Best of Houzz 2015 - Client Satisfaction

Best of Houzz 2015 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.

Tags:


Leave a comment

Questions? Ask the Blue Tape Guy

roell logo

Office: 763-559-5296
Fax: 763-557-9597
7301 Penn Avenue South
Minneapolis, MN 55423