Greetings and welcome to your project blog for your upcoming painting project at Parkwoode HOA in Oakdale. We are thrilled to be onsite this summer to spruce up your exteriors.
Front Door Scheduling Calendar
Monday, September 25th: Greetings!
Due to the rain today the crew didn’t make it. Tomorrow we will be checking the dampness level of the included substrates before we return to paint.
Thanks everyone stay dry!
Friday, September 8th: Good afternoon!
Below is a chart with approximate start dates for the deck staining / painting on each building. This is subject to change should we end up ahead or behind schedule due to weather or other circumstances.
Please check back frequently for updates on your buildings start date.
Building Number | Tentative Deck Staining / Painting Date |
31 – 29 & 27 | Pending final walk through / touch-ups |
27 – 25 | Pending final walk through / touch-ups |
23 & 21 | Pending final walk through / touch-ups |
21 – 19 | Pending final walk through / touch-ups |
19 – 17 | Pending final walk through / touch-ups |
15 & 13 | Tuesday September 19th |
Finishing 13 – Starting 11 | Wednesday September 20th |
Finishing 11 – Starting 18 & 20 | Thursday September 21st |
22 & 24 | Friday September 22nd |
Thursday, September 7th: Good afternoon!
We have crews working on the first 3 buildings.
Here they are painting shutters, and entry railing.
Wednesday, August 30th: Greetings!
Welcome to your project blog for the upcoming exterior project. We are excited to be working together this year!
Our crew will begin pressure washing the decking in the first building (#33) of our proposed sequence listed on the map above on Tuesday, September 5th.
We kindly request that homeowners close their windows & remove any small personal items from the outside of your home and remove items from your deck and front porch (if you have wooden front porch) for the pressure washing to allow for safe & unobstructed access for washing.
After the decking surfaces have been washed, the wood will need time to dry and during that time we will begin painting front door frames, shutters, bollard posts, entry metal railings, gas meters, entry awning supports & garage door frames on Wednesday, September 6th in our proposed sequence.
We will be posting notices later on with a link to schedule an appointment for front door painting as we paint those in the open position. Date on front door painting is TBD as of now so stay tuned!
We anticipate that the entire project (deck painting and trim painting) will be completed within 4-6 weeks. However, your unit/building will be completed much sooner. Please be aware that the weather will likely affect our completion schedule.
We understand this project will have an impact to your daily routine & we will do our best to complete the project promptly so everyone may enjoy the remainder of the summer. In order to access the most up to date information, projected washing / painting schedule or any other weather delays / impacts, check back here frequently.
Please reach out to the contacts below if you have any questions.
Jason Schell
Danielle Baumgartner
Houzz Best Of 2021 - Client Satisfaction
Best of Houzz 2020 - Client Satisfaction
Best of Houzz 2019 - Client Satisfaction
Best of Houzz 2018 - Client Satisfaction
Best of Houzz 2017 - Client Satisfaction
Best of Houzz 2016 - Client Satisfaction
Best of Houzz 2015 - Client Satisfaction
Tags: Completed Projects