Nicols Ridge Summit HOA – Eagan

Nicols Ridge Summit HOA – Eagan

Prep & Painting IN PROGRESS

Greetings and welcome to your project portal for the upcoming painting project at Nicols Ridge Summit HOA in Eagan. We are thrilled to be working for and with you this summer.

Building Pressure Washing Start Date Prep/Painting Start Date
Building 1: 2100-2106 Friday, 6/25 Wednesday, 7/7
Building 2: 2108-2114 Friday, 6/25 Thursday, 7/15
Building 3: 2116-2122 Friday, 7/16 Wednesday, 7/21
Building 4: 2124-2130 Friday, 7/16 Monday, 7/26
Building 5: 2132-2138 Friday, 7/16 Thursday, 7/29
Building 6: 2140-2146 Monday, 7/26 TBD
Building 7: 2148-2154 Monday, 7/26 TBD
Building 8: 2156-2162 Monday, 7/26 TBD
Building 9: 4000-4006 TBD TBD
Building 10: 4008-4014 TBD TBD
Building 11: 4016-4022 TBD TBD
Building 12: 4024-4030 TBD TBD

Thursday, July 29th: Greetings!

The crew is back onsite today after yesterday’s rain delay. They have begun prepping Building 5, covering the surfaces that will not be painted. 

Taping off the garage on building 5.

Our ladder is up as we prep your windows.

Wednesday, July 28th: Good morning!

The crew will not be onsite today due to the rain. They will return when the surfaces have had time to dry so they can continue working on your project. Have a great rest of your day!

Monday, July 26th: Good afternoon! 

The crew is working on prep and painting at Building #4. They are also pressure washing buildings 6, 7, and 8. 

Building 4 in progress.

Prep and covering windows.

Up the ladder to spray the siding.

A completed elevation on Building 4.

Friday, July 23rd: Greetings!

The crew is onsite and making great progress on your project. They are removing the plastic from Building 2 and prepping/painting at Building 3. The crew will return on Monday, 7/26 to pressure wash Buildings 6, 7, & 8 and to begin prepping Building 4.

We have our ladder up to remove the plastic from Building 2.

Working on prep and painting at Building 3 today.

Wednesday, July 21st: Good morning!

The crew is onsite and they have started prepping Building 3. They are working on covering various areas to protect them from being painted. The crew will be working on this prep work for the rest of the day.

Working hard to prep.

Ladders are up and we are ready to prep.

Tuesday, July 20th: Greetings!

The crew is working diligently on your project this afternoon. They are continuing to make progress in prepping and painting Building 2. Tomorrow they will start prepping Building 3 in the late morning/early afternoon.

Our ladder is up and prepping is underway this afternoon at Building 2.

Spraying on the paint around the window.

Friday, July 16th: Good afternoon!

The crew is picking right up from where they left off yesterday. They are working on prepping Building 2 to get ready to paint. Buildings 3, 4, and 5 are being pressure washed today, and Building 3 will start being prepped next week.

Prep work is underway at Building 2.

Thursday, July 15th: Good morning!

The crew is back onsite this morning after yesterday’s rain delay. They are currently working on trim painting at Building 1. After lunch, they will return to start prepping at Building 2.

Tomorrow the crew will be onsite pressure washing Buildings 3, 4, and 5. They are projecting to start prepping and painting at Building 3 on Monday, 7/19.

Prep work being done before we can start to paint the trim.

Wednesday, July 14th: Greetings!

The crew will not be onsite today due to the rain. They should be back to continue working on your project tomorrow or Friday, weather permitting. 

Tuesday, July 13th: Good afternoon!

We are back onsite and picking up right where we left off at Building 1. The crew is working hard and making great progress so far at Nicols Ridge. They will return tomorrow to start prepping and painting Building 2.

Monday, July 12th: Greetings!

The crew is continuing their diligent work on your project. They are prepping and painting at Building 1 again today. 

Prepping the window.

Friday, July 9th: Good afternoon and TGIF! 

The crew is continuing to prep and paint their way around Building #1. They are projecting to begin prep work on #2 on Monday, 7/12. Have a great weekend!

Wednesday, July 7th: Good morning!

The crew is back onsite today and they have started prepping Building 1.

Prepping the window.

Ladder is up & we are prepping away.

Tuesday, July 6th: Greetings!

We hope you all had a great weekend! The crew will not be onsite today but we should be back tomorrow or Thursday, weather permitting. 

Friday, July 2nd: Good morning!

Tuesday, June 29th: Greetings!

We are waiting for the final color approval for your project. There is currently a paint shortage that we are experiencing right now. So we need to make sure that we have enough materials to complete your project before we are able to start. 

Paint colors.

Friday, June 25th: Good morning!

The crew is off and running at Nicols Ridge Summit this morning and the pressure washer is ready to roll! They have started washing Building 1 and will also wash Building 2 today. The crew will return on Tuesday, 6/29 to start prepping and painting Building 1.

Your project is underway!

Pressure washing Building 1.

Monday, June 21st: Good afternoon residents of Nicols Ridge Summit!

Welcome to your project blog for the upcoming painting project. We are excited to be onsite with you this year!

We have a crew that will be kicking off on Friday, 6/25 with pressure washing, which will likely take several days for the crew to complete.

We kindly request that homeowners close their windows & remove any small personal items from the outside of your home for the pressure washing to allow for safe & unobstructed access for washing.

After the surfaces have had time to dry the crew will return to begin their prep and painting on Building 1. We are projecting this prep/painting to begin on Tuesday, 6/29.

We are projecting that this project will take 4-6 weeks to complete. The best way to obtain a project status update and any impact it may have on your daily routine will be posted here as we’ll share progress throughout, photos, and any weather delays.

Please reach out to the contacts below if you have any questions.

We’re looking forward to getting started this week!


Dana Clark

Project Manager
Ph: 763-559-5296
Email

Jesse Maki

Production Manager
Ph: 612-363-4586
Email

2021
Houzz Best Of 2021 - Client Satisfaction

Houzz Best Of 2021 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2020
Best of Houzz 2020 - Client Satisfaction

Best of Houzz 2020 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2019
Best of Houzz 2019 - Client Satisfaction

Best of Houzz 2019 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2018
Best of Houzz 2018 - Client Satisfaction

Best of Houzz 2018 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2017
Best of Houzz 2017 - Client Satisfaction

Best of Houzz 2017 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2016
Best of Houzz 2016 - Client Satisfaction

Best of Houzz 2016 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2015
Best of Houzz 2015 - Client Satisfaction

Best of Houzz 2015 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.

Tags:


Leave a comment

Questions? Ask the Blue Tape Guy

roell logo

Office: 763-559-5296
Fax: 763-557-9597
7144 Shady Oak Road
Eden Prairie, MN 55344