Nicols Ridge Summit HOA – Eagan
Nicols Ridge Summit HOA – Eagan
Project Complete
Greetings and welcome to your project portal for the upcoming painting project at Nicols Ridge Summit HOA in Eagan. We are thrilled to be working for and with you this summer.
DOOR PAINTING SIGN UP
Building | Pressure Washing Start Date | Prep/Painting Start Date |
Building 1: 2100-2106 | Friday, 6/25 | Wednesday, 7/7 |
Building 2: 2108-2114 | Friday, 6/25 | Thursday, 7/15 |
Building 3: 2116-2122 | Friday, 7/16 | Wednesday, 7/21 |
Building 4: 2124-2130 | Friday, 7/16 | Monday, 7/26 |
Building 5: 2132-2138 | Friday, 7/16 | Thursday, 7/29 |
Building 6: 2140-2146 | Monday, 7/26 | Monday, 8/2 |
Building 7: 2148-2154 | Monday, 7/26 | Monday, 8/2 |
Building 8: 2156-2162 | Monday, 7/26 | Wednesday, 8/5 |
Building 9: 4000-4006 | Saturday, 8/7 | Tuesday, 8/10 |
Building 10: 4008-4014 | Saturday, 8/7 | Wednesday, 8/11 |
Building 11: 4016-4022 | Monday, 8/9 | Friday, 8/13 |
Building 12: 4024-4030 | Monday, 8/9 | Tuesday, 8/17 |
Monday, August 24th: Good morning!
The crew is wrapped up aside from doing our walk through and completing touch ups prior to calling everything fully complete. We’ll be walking and marking areas in the next few days and also completing the touch ups. Thank you!
Friday, August 20th: Good afternoon and TGIF!
The crew will be wrapping up on Building 12 by the end of the day and then continuing to knock and take appointments for door painting. If you have not done so already, please sign up for a window of time to be home and open your door to be painted. Thanks!
Thursday, August 19th: Good morning!
The crew is onsite working on Building 12. Front door painting starts tomorrow, the crew will follow the appointment list that is above.
Tuesday, August 17th: Good afternoon!
The crew is continuing to paint Buildings 10 and 11. They also plan to start working on Building 12 today.
Monday, August 16th: Good evening!
Apologies if you’ve gone to our site to make an appointment for door painting and did not see the calendar tool. It is now posted above. If your front door has not been painted, please use the tool to schedule a time on Friday or Saturday to be home, open your door, and then allow if to remain open and dry for at least 2.5 hours. Thank you!
Thursday, August 12th: Good afternoon!
The crew has picked up where they left off and are continuing to prep and paint Buildings 9 and 10.
Wednesday, August 11th: Good morning!
The crew is onsite this morning continuing to prep and paint Building 9. They have also began working on Building 10.
Tuesday, August 10th: Good afternoon!
The crew is back onsite today starting the process of prepping Building 9.
Friday, August 6th: Good morning and TGIF!
The crew is continuing to paint on Building #8 – they are prepping and painting on the rear elevation. They are tentative to start on #9 on Monday. Have a great weekend!
Thursday, August 5th: Good Morning!
The crew is back onsite today and they have started to prep Building #8.
Wednesday, August 4th: Greetings!
The crew is back onsite continuing to prep and paint Building 7 today.
Tuesday, August 3rd: Good afternoon!
The crew is onsite today working on prepping and painting Building #7.
Monday, August 2nd: Good afternoon!
We can hardly believe it’s already August. Where has the time gone?!
The crew is working at Buildings #6 and #7.
Friday, July 30th: Good morning!
The crew is continuing to work on Building 5 today. They are prepping and painting the back of the building currently.
Thursday, July 29th: Greetings!
The crew is back onsite today after yesterday’s rain delay. They have begun prepping Building 5, covering the surfaces that will not be painted.
Wednesday, July 28th: Good morning!
The crew will not be onsite today due to the rain. They will return when the surfaces have had time to dry so they can continue working on your project. Have a great rest of your day!
Monday, July 26th: Good afternoon!
The crew is working on prep and painting at Building #4. They are also pressure washing buildings 6, 7, and 8.
Friday, July 23rd: Greetings!
The crew is onsite and making great progress on your project. They are removing the plastic from Building 2 and prepping/painting at Building 3. The crew will return on Monday, 7/26 to pressure wash Buildings 6, 7, & 8 and to begin prepping Building 4.
Wednesday, July 21st: Good morning!
The crew is onsite and they have started prepping Building 3. They are working on covering various areas to protect them from being painted. The crew will be working on this prep work for the rest of the day.
Tuesday, July 20th: Greetings!
The crew is working diligently on your project this afternoon. They are continuing to make progress in prepping and painting Building 2. Tomorrow they will start prepping Building 3 in the late morning/early afternoon.
Friday, July 16th: Good afternoon!
The crew is picking right up from where they left off yesterday. They are working on prepping Building 2 to get ready to paint. Buildings 3, 4, and 5 are being pressure washed today, and Building 3 will start being prepped next week.
Thursday, July 15th: Good morning!
The crew is back onsite this morning after yesterday’s rain delay. They are currently working on trim painting at Building 1. After lunch, they will return to start prepping at Building 2.
Tomorrow the crew will be onsite pressure washing Buildings 3, 4, and 5. They are projecting to start prepping and painting at Building 3 on Monday, 7/19.
Wednesday, July 14th: Greetings!
The crew will not be onsite today due to the rain. They should be back to continue working on your project tomorrow or Friday, weather permitting.
Tuesday, July 13th: Good afternoon!
We are back onsite and picking up right where we left off at Building 1. The crew is working hard and making great progress so far at Nicols Ridge. They will return tomorrow to start prepping and painting Building 2.
Monday, July 12th: Greetings!
The crew is continuing their diligent work on your project. They are prepping and painting at Building 1 again today.
Friday, July 9th: Good afternoon and TGIF!
The crew is continuing to prep and paint their way around Building #1. They are projecting to begin prep work on #2 on Monday, 7/12. Have a great weekend!
Wednesday, July 7th: Good morning!
The crew is back onsite today and they have started prepping Building 1.
Tuesday, July 6th: Greetings!
We hope you all had a great weekend! The crew will not be onsite today but we should be back tomorrow or Thursday, weather permitting.
Friday, July 2nd: Good morning!
Tuesday, June 29th: Greetings!
We are waiting for the final color approval for your project. There is currently a paint shortage that we are experiencing right now. So we need to make sure that we have enough materials to complete your project before we are able to start.
Friday, June 25th: Good morning!
The crew is off and running at Nicols Ridge Summit this morning and the pressure washer is ready to roll! They have started washing Building 1 and will also wash Building 2 today. The crew will return on Tuesday, 6/29 to start prepping and painting Building 1.
Monday, June 21st: Good afternoon residents of Nicols Ridge Summit!
Welcome to your project blog for the upcoming painting project. We are excited to be onsite with you this year!
We have a crew that will be kicking off on Friday, 6/25 with pressure washing, which will likely take several days for the crew to complete.
We kindly request that homeowners close their windows & remove any small personal items from the outside of your home for the pressure washing to allow for safe & unobstructed access for washing.
After the surfaces have had time to dry the crew will return to begin their prep and painting on Building 1. We are projecting this prep/painting to begin on Tuesday, 6/29.
We are projecting that this project will take 4-6 weeks to complete. The best way to obtain a project status update and any impact it may have on your daily routine will be posted here as we’ll share progress throughout, photos, and any weather delays.
Please reach out to the contacts below if you have any questions.
We’re looking forward to getting started this week!
Dana Clark
Houzz Best Of 2021 - Client Satisfaction
Best of Houzz 2020 - Client Satisfaction
Best of Houzz 2019 - Client Satisfaction
Best of Houzz 2018 - Client Satisfaction
Best of Houzz 2017 - Client Satisfaction
Best of Houzz 2016 - Client Satisfaction
Best of Houzz 2015 - Client Satisfaction
Tags: Completed Projects