Greetings and welcome to your project blog for the 2019 painting project at Beachside I. We are thrilled to be back onsite in your association!

Welcome to your project blog!

Route Map
Orange indicates Touch Up Painting
Blue indicates Garage Door Painting


Friday, October 25th: Good Afternoon! 

We all have a little more pep in our step from the Vikings win last night! 

The crew is finishing up some touch ups and wrapping up the railings and garage doors today. Thanks! 

Thursday, October 24th: Greetings! 

Another beautiful fall day! The Viking are hosting the Kansas City Chiefs tonight for Thursday Night Football and Isaac is proudly wearing his Vikings purple today!

The crew is continuing to prep and paint the select garage doors that were discolored from some previous pressure washing. We are happy to be restoring them to their original and vibrant coloring.

They are hopeful to wrap up tomorrow or Saturday! We hope you’re having a great week and thank you again for having us back onsite to complete your 2019 painting!

Rubi and Melvin are digging today’s sunshine!

Another day and more railings to finish up.

Painting the top coat on a section of railing.

Wednesday, October 23rd: Good afternoon! 

We couldn’t be happier to see the sun shining and not be getting rained on! The crew is back onsite after our rain delay and they’ve picked up with finishing the touch ups on the last 7 buildings as well as painting the top coat on the railings, starting at the beginning of the route. Thanks! 

Moving along the route and painting the railings.

Painting the top coat on the entry railings.

Tuesday, October 22nd: Good morning! 

We’ve got another rain day, but wanted to update you on the progress of the project so far. The crew has completed their prep, prime and painting of the touch ups on Buildings 1- 20. There are 7 Buildings that have areas primed, but need the top coat. Also, all of the selected garage doors have been primed and will be painted as the weather allows. And finally, all of the entry railings have been primed and will be painted as the crew resumes onsite. Thanks!

Friday, October 18th: Good morning and TGIF! 

We’ve made it to Friday and it’s going to be a beautiful couple days… we’re just elated we’re not having a repeat of that weekend’s weather!

The crew is starting to paint the entry railings, starting at the beginning of the route as well as painting the newly replaced/primed areas. They are planning to paint on Saturday and Sunday – they’ll begin priming the included garage doors and then paint them on Sunday. They are also projecting to completed by Sunday with the garages, newly replaced/painted areas, and the railings. Thanks and have a great weekend!

Painting the entry railings.

Tackling another area of entry railings.

Thursday, October 17th: Good afternoon! 

The crew is off and running at Beachside I. We are just thrilled to be back at your community – it is a pleasure and privilege to be working for your again this year!

The crew is kicking off the project with priming the areas with new wood as well as priming the entry metal railings. They are also pressure washing the select included garage doors. 

They’ll be painting the primed areas tomorrow. Thanks! 

Priming a section of newly replaced wood.

Priming the garage frame.

Pressure washing one of the garage doors.

Tuesday, October 15th: Good morning! 

Welcome to your project blog for the upcoming painting project at Beachside I. We are thrilled to be back onsite in your community this year. 

We’ll be prepping and painting select newly replaced wood, select garage doors/frames, and your entry metal handrails. This will begin on Thursday, 10/17. We are anticipating the project to take about 7-9 working days to complete, weather pending. 

We kindly ask that you exercise caution as needed as there will be wet paint on select substrates – handrails- that are commonly used by homeowners and/or their guests. Thanks! 

You can continue to follow the project’s progress here on the blog and stay current on any weather delays as well. Thanks so much and we’re looking forward to getting started. 

See you on Thursday!

 

 

Roell Painting

Project Manager