Charleswood Crossing – Farmington
Charleswood Crossing – Farmington
Project Complete
Greetings and welcome to your project blog for the upcoming pressure washing and deck staining project at Charleswood Crossing in Farmington. We are thrilled to be onsite with you!
Route Map @ Charleswood Crossing
Thursday, August 29th: Good Afternoon!
Tuesday, August 27th: Greetings!
The crew is wrapping up their prep and painting of the deck skirt boards in Phase II. They get everything completed today as well. We wanted to extend a thank you to everyone for having us and we hope you enjoy your newly stained decks!
Monday, August 26th: Good morning!
We hope you all had a good weekend! Last week the crew finished up Phase I staining and moved on to stain the decks in Phase II. They’ll also be painting the deck skirt boards as the staining is finishing up.
The crew will be back as the weather allows – thanks!
Thursday, August 22nd: Greetings!
Today’s the start of the Great Minnesota Get Together and we can just smell the always delightful Sweet Martha’s! We’ve got 12 days to eat our hearts’ desire and explore the sights and scenes at the Fair! Take a look at our own Andrew Zimmern’s Food Fair Strategy:
The crew is starting to stain the decks on the 2nd Building in Phase I.
Wednesday, August 21st: Greetings!
The crew is holding off on staining the decks; they’re just too wet still. They are going around to decks in Phase I and Phase II and sanding the surfaces as applicable so when we get the go-ahead for staining we can get right to staining. Thanks!
Tuesday, August 20th: Good afternoon!
That morning rain kind of came out of no where! Thus, our staining crew will be pressing pause on the staining, but they will continue to pressure wash and strip the decks in Phase II.
Monday, August 19th: Hello and Happy Monday!
The crew has started to sand and stain decks on Phase I and is also pressure washing in Phase II.
Friday, August 16th: Hello and TGIF!
The decks were too wet from the rain to begin staining today. They’ll begin Phase I staining on Monday, 8/19 — please be so kind as to remove furniture from decks for the staining. Thanks!
We’ll also be washing Phase II on Monday, 8/19.
Have a great weekend!
Thursday, August 15th: Greetings!
The crew will begin prepping and staining the decks in Building 1 tomorrow. We’ll also be posting notices on the Phase II Buildings that we will pressure wash #3 and #4 starting on Monday, August 19th.
We’ll be chemically stripping the decks of previous stain, which is a multiple step process, thus the washing with take multiple days to complete for the 20 decks included in Phase I. For the pressure washing and stripping we kindly ask that you remove all personal belongings and furniture off of your deck. Once the washing is complete, you can return items to your deck as it will take some time for the surfaces to dry out completely. We’ll then ask you to clear the contents of your deck one more time so we can complete the staining.
We anticipate to return to begin staining select ‘Phase II’ decks on Thursday, August 22nd. We’ll be prepping and staining your deck floors and painting your skirt boards. This will mimic the work done in Phase I.
Thanks!
Tuesday, August 13th: Good afternoon!
The crew has completed the pressure washing and chemical stripping of the decks on Building 1 in Phase 1 and will complete Building 2 today as well. Then depending on weather, we’ll start the staining process on Thursday, 8/15— as long as it’s dry enough!
Stay tuned here for further updates regarding staining, project progress, and when we’ll begin in Phase II. Thanks!
Monday, August 12th: Hello and Happy Monday!
The crew is off and running in Phase I of the project. They’ve started the pressure washing and chemical stripped of the decks, starting at Building #1. The washing and stripping will take about 3 days to complete and from there we’ll begin the staining process. Thanks!
Wednesday, August 7th: Greetings and welcome to your project blog for the upcoming deck staining project!
We’ll begin on Monday, August 12th with pressure washing of the decking in Phase I— shown above in pink. We’ll be chemically stripping the decks of previous stain, which is a multiple step process, thus the washing with take multiple days to complete for the 20 decks included in Phase I. For the pressure washing and stripping we kindly ask that you remove all personal belongings and furniture off of your deck. Once the washing is complete, you can return items to your deck as it will take some time for the surfaces to dry out completely. We’ll then ask you to clear the contents of your deck one more time so we can complete the staining.
We anticipate to return to begin staining select ‘Phase I’ decks on Thursday, August 15th. We’ll be prepping and staining your deck floors and painting your skirt boards. The weather will have the most impact on the schedule of completion of your decks. You can continue to follow the project progress here on the blog as we’ll provide frequent updates, project photos, and any delays should they come up.
THANK YOU in advance for your cooperation and participation to move items off of your deck.
David Lee