Highcroft East & West HOA – Edina
Highcroft East & West – Edina
Project Complete
Greetings and welcome to your project portal for the upcoming painting project at Highcroft East & West in Edina. We are thrilled to be working with and for you this summer!
Building | Pressure Washing Start Date | Prep/Painting Start Date |
1 | Thursday, 7/1 | Wednesday, 7/7 |
2 | Thursday, 7/1 | Friday, 7/9 |
3 | Thursday, 7/1 | Tuesday, 7/13 |
4 | Thursday, 7/15 | Tuesday, 7/20; waiting on stucco paint |
5 | Thursday, 7/15 | Monday, 7/26 |
6 | Thursday, 7/15 | Thursday, 7/30 |
7 | Thursday, 7/15 | Monday, 8/2 |
Tuesday, August 17th: Good afternoon!
The crew is working on finishing up the door frames and gates today. Aside from a walk through and touch ups the crew should be all wrapped up by the end of the day.
Monday, August 9th: Good morning!
The crew is continuing with carpentry. They’re at Building #7 today. They’ve also started to pressure wash the privacy fencing. Thanks!
Friday, August 6th: Good morning and TGIF!
The crew is continuing with carpentry today at Highcroft.
Thursday, August 5th: Greetings!
The crew is onsite today working on carpentry and Buildings 4, 5 and 6.
Tuesday, August 3rd: Good afternoon!
The crew is onsite continuing to prep and paint Building #7 today.
Monday, August 2nd: Good morning!
We can hardly believe it’s already August! Where has the time done?!
The crew is prepping and painting at Building #7. They are also completing carpentry items.
Friday, July 30th: Greetings & TGIF!
The crew is continuing to work diligently on your project. They are prepping and painting Building 6 today.
Thursday, July 28th: Good afternoon!
The crew is onsite prepping and painting Buildings 5 & 6. They will continue working on these two buildings tomorrow as well.
Wednesday, July 28th: Good morning!
The crew will not be onsite today due to the rain. They will return when the surfaces have had time to dry so they can continue working on your project. Have a great rest of your day!
Tuesday, July 27th: Greetings!
The crew has returned to Building 4 today spraying the stucco that has arrived. They are also continuing the prepping and painting of Building 5.
Monday, July 26th: Good afternoon!
The crew is prepping and painting their way around Building #5. They will return to #4 when more paint for the stucco arrives – thanks!
Thursday, July 22nd: Greetings!
The crew is onsite and continuing to work diligently on your project. They are working on covering all surfaces that are not being painted. The crew has also started painting Building 4 as well.
The crew would also like to say a big thank you to the nice gentleman who bought them lunch yesterday!
Tuesday, July 20th: Good morning!
The crew has started the prep work for Building 4 this morning. So far they have covered the windows in plastic to protect them from the paint once that starts.
We would also like to share info about our process for painting, completing walk-throughs, and touch-ups. Generally, as a crew is completing a building and there happen to be some touch-ups areas, drips, or overspray, the crew will complete the clean-up and touch-ups either at the completion of the building or towards the end of the project.
Our field production supervisor Jesse is often onsite and checking in on progress. He will walk completed areas and mark areas needing touch-ups with blue tape. We will complete our own walk-through to mark areas prior to walking with a board member or property manager.
All to say is that the project is not complete until all touch-ups and outstanding items are taken care of. Please let us know if you have any questions. Thank you and we’re looking forward to continuing to refresh your buildings.
Friday, July 16th: Greetings!
The crew is onsite this beautiful Friday morning and they are picking up right where they left off on Building 3 from Tuesday. The crew is continuing to prep and paint and they are making great progress on your project.
Thursday, July 15th: Good morning!
The crew is back onsite this morning after yesterday’s rain delay. They will be pressure washing Buildings 4, 5, 6, and 7 today.
Wednesday, July 14th: Greetings!
The crew will not be onsite today due to the rain. They should be back to continue working on your project tomorrow or Friday, weather permitting.
Tuesday, July 13th: Good afternoon!
The crew has begun prepping and painting Building #3 today. They will also be doing some carpentry on Building #1. The crew will be pressure washing the remaining Buildings (4, 5, 6, & 7) on Thursday, 7/15.
Weather permitting, the crew will be starting the stucco painting tomorrow. If the weather does not allow this they will begin on Thursday, 7/15. The crew will start on the East and move West. Please remove any personal belongings from the stucco areas so the crew has unobstructed access to paint. Thank you!
Monday, July 12th: Greetings!
The crew is continuing their diligent work on Building #2 today.
Friday, July 9th: Good afternoon and TGIF!
The crew is working on prep and painting on Buildings #1 and #2.
Wednesday, July 7th: Good afternoon!
The crew is back onsite today and they are going to begin prepping and painting at Building 1.
Tuesday, July 6th: Greetings!
We hope you all had a great weekend! The crew will not be onsite today but we should be back tomorrow or Thursday, weather permitting.
Friday, July 2nd: Good morning!
Thursday, July 1st: Happy July & Project Start Day!
The crew is off and running at Highcroft and the pressure washer is ready to roll! They will likely be pressure washing today and tomorrow.
Monday, June 28th: Greetings Residents of Highcroft East & West!
Welcome to your project blog for the upcoming painting project. We are looking forward to refreshing your exteriors.
For this year’s project, we will be prepping and finishing select areas of your exterior including lap siding, soffits, fascia, metal entry railings/gates, front door frames (including sidelights & transoms), garage door frames, porch/deck support posts, deck railings, lattice and exterior screen frames (where applicable), gas/electric meters (to replicate current to match siding color), and privacy fence sections on the perimeter of the property.
We have a crew that will be kicking off with pressure washing on Thursday, 7/1 which will likely take 1-2 days to complete.
We ask that you please remove any personal belongings from the outside of your home to allow for safe & unobstructed access to these areas for the washing.
Once the substrates have had time to dry, carpenters will be back to start on the first building. We are projecting this prepping & finishing of the first building to start on either Monday, 7/5 or Tuesday 7/6
The best way to obtain a project status update and any impact it may have to your daily routine will be posted here as we’ll share progress throughout, photos, and any weather delays.
Please reach out to the contacts below if you have any questions.
We are looking forward to getting started next week!
Trent Stern
Houzz Best Of 2021 - Client Satisfaction
Best of Houzz 2020 - Client Satisfaction
Best of Houzz 2019 - Client Satisfaction
Best of Houzz 2018 - Client Satisfaction
Best of Houzz 2017 - Client Satisfaction
Best of Houzz 2016 - Client Satisfaction
Best of Houzz 2015 - Client Satisfaction
Tags: Completed Projects