Waycliffe 1 – Wayzata

Waycliffe 1 – Wayzata

Project Complete

Greetings and welcome to your project blog for the upcoming painting project at Waycliffe 1 in Wayzata. We are thrilled to be back onsite this year to spruce up your exteriors.


Buildings Pressure Washing Start Date Prep/Painting Start Date
370 – 380 Thursday, 4/29 Thursday, May 6th; Paint Monday, 5/10
375 – 385 Friday, 4/30 Thursday, May 13th
540 – 550 Tuesday, 5/11 Tuesday, May 24th
565 – 575 Wednesday, 5/12 Thursday, June 3rd

Thursday, June 17th: One last thank you!

Tuesday, June 15th: Good morning! 

It’s been a while! Apologies for the delay in updates here. We have great news to report, your project is fully complete! 

It has been our pleasure to be onsite and to refresh the 4 buildings set for completion this summer. We hope you are enjoying the newly painted exteriors and have a great rest of the summer! 

Tuesday, June 8th: Good morning!

The crew is continuing to work on Building 4 where they left off prepping and painting. 

Ladder is up and painting is underway!

Prepping the window.

Painting Building 4.

Friday, June 3rd: Happy Friday!

The crew is onsite and will be prepping and painting Building 4 today. They are also staining the deck floors. 

Ladders up and we are ready to prep, prep, prep.

The deck stain looks great!

Caulking the garage door.

Wednesday, June 2nd: Greetings!

The crew is almost done with Building 3 and will finish by the end of the day. They will begin prepping Building 4 tomorrow. The crew will start staining the deck floors tomorrow as well.

Almost done with Building 3.

Painting away this afternoon.

Ladder is up and the crew is working hard!

Friday, May 28th: Good afternoon!

The crew is back onsite today. They have finished the front of Building 3 and will return on Tuesday to work on the back. Have a great memorial weekend!

Thursday, May 27th: Good morning!

The crew will not be onsite today but we are hoping to be back tomorrow as long as the weather cooperates. 

Wednesday, May 26th: Greetings!

The crew is onsite on this sunny spring day. They are continuing to prep Building 3 and have started painting Building 3 as well. 

Prepping the windows on Building 3.

Painting is underway at Building 3!

Tuesday, May 25th: Good afternoon!

The crew is scraping and prepping the 3rd building today. 

Scraping the siding.

Prepping of the 3rd building is underway!

Monday, May 24th: Greetings!

The crew is onsite and will finish the 2nd building today. They will start prep on the 3rd building tomorrow.

Thursday, May 20th: Good morning!

Unfortunately, due to the rain again today the crew will not be onsite.

Wednesday, May 19th: Greetings!

Due to the rain yesterday the crew will not be onsite today. They will hopefully return tomorrow, weather permitting. 

Tuesday, May 18th: Good morning!

The crew is onsite and painting the 2nd building today. They will start prepping and painting the 3rd building on Thursday.

Painting is underway this morning.

Working hard to paint building 2!

Hard at work today.

Enjoying painting on this beautiful day!

Monday, May 17th: Greetings!

The crew is continuing to prep and paint siding and trim areas on the 2nd building today.

Building is prepped and ready to be painted

Painting is underway.

Building has been prepped!

Friday, May 14th: Good afternoon and happy Friday! 

The crew is continuing to prep and paint siding and trim areas on the 2nd Building. 

Thumbs up and trim painting.

Resident doors are also getting a refresh!

Transforming your garage doors.

Wednesday, May 12th: Good morning! 

The crew is continuing to prep/paint around Building 1 and will also be washing the final building – 565/575 today. They are set to start prep/covering/scraping on the 2nd Building tomorrow as well.

Pressure washing the final building today.

Cleaning surfaces for painting.

Tuesday, May 11th: Good afternoon! 

Prep and painting continues around the first building at Waycliffe for this year’s painting – 370-380 Building. 

They’ll continue to prep and scrape sections before spraying and then back rolling the areas. We are also pressure washing Building 540/550 today and 565/675 tomorrow. 

Scrape, spray, back roll and repeat.

Working our way around Building 1.

Spraying and rolling the siding.

Monday, May 10th: Greetings! 

The crew is onsite and prepping and also starting to spray the siding areas. Refresh is in progress!

And we’re painting!

Prep and priming before we spray.

Prepping the chimney stacks.

Friday, May 7th: Good afternoon and happy Friday! 

The crew is continuing to prep and prime select areas. They’ll start to paint the first building on Monday, 5/10. 

Have a great weekend!

Spot priming on Building 1.

Readying the surfaces for painting.

Prime day… and not the Amazon kind : )

Reach for it!

Thursday, May 6th: Good afternoon! 

The crew is starting prep on the first building today – 370/380. They’ll continue to prep, cover, scrape, caulk and ready the surfaces for another 1-2 days before they start spraying. 

Scraping is underway.

Hello Waycliffe! Happy to be back onsite😎

Ladders up to scrape above the garage doors.

Onsite and ready to prep, prep, and prep.

Thursday, April 29th: Greetings and happy project start day!

The crew is off and running at Waycliffe this morning with pressure washing the 370-380 Building and they’ll return tomorrow to pressure wash the 375-385 Building.

Spraying the chimney stacks.

Things are looking up!

I spy…

Thursday, April 22nd: Good afternoon!

Welcome to your project blog for the upcoming painting at Waycliffe 1 in Wayzata. We are looking forward to working with and for you over the next few weeks!

We are tentatively set to start pressure washing select buildings on Thursday, April 29th. We kindly ask that you please remove all personal items from your deck for the pressure washing and small items from outside your home to allow for safe and unobstructed access for washing. Once the washing is complete, you may return the items to your deck. 

Once the substrates have had adequate time to dry, the crew will return to begin prepping and finishing the included surfaces. We anticipate that prep and painting start date to be — TBD. With the weather being the biggest factor in our schedule, we can’t commit to a start date for prep/painting. 

We will soon post a tentative finishing schedule with dates for pressure washing and prep/painting in regards to each building.

We will be monitoring the weather and also updating the blog frequently throughout your project for progress, project photos, and any weather delays. 

You can continue to follow the project progress here on the blog and please reach out if you have any questions. 

We’re looking forward to getting started next week! Have a great weekend!


Dana Clark

Project Manager
Ph: 763-559-5296
Email

2021
Houzz Best Of 2021 - Client Satisfaction

Houzz Best Of 2021 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2020
Best of Houzz 2020 - Client Satisfaction

Best of Houzz 2020 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2019
Best of Houzz 2019 - Client Satisfaction

Best of Houzz 2019 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2018
Best of Houzz 2018 - Client Satisfaction

Best of Houzz 2018 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2017
Best of Houzz 2017 - Client Satisfaction

Best of Houzz 2017 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2016
Best of Houzz 2016 - Client Satisfaction

Best of Houzz 2016 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2015
Best of Houzz 2015 - Client Satisfaction

Best of Houzz 2015 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.

Tags:


Leave a comment

Questions? Ask the Blue Tape Guy