Concordia Meadows – Roseville

Concordia Meadows – Roseville

Project Complete

Greetings and welcome to your project blog for the upcoming painting project at Concordia Meadows in Roseville. We’re looking forward to being onsite! 


Wednesday, August 26th: Good afternoon! 

The crew is finishing with the prep and painting of select trim areas. We’ll soon be marking areas for touch ups and get those completed in the next several days. 

Tuesday, August 25th: Greetings! 

The crew is back onsite and the crew is prepping and painting at Building 11. 

Painting door frames at Building 11.

Monday, August 24th: Good morning! 

The crew will not be onsite today with the overnight and morning rain. We’ll resume tomorrow – thanks! 

Friday, August 21st: Hello and TGIF! 

The crew is painting their way along the route and starting off at Building 7 this morning. 

Thanks and have a great weekend! 

Painting door frames at Concordia Meadows.

Thursday, August 20th: Greetings! 

The crew is continuing at Building 6 this morning and will continue along the route above. 

Prep and priming.

Wednesday, August 19th: Good afternoon! 

The crew is continuing along the route and will be starting off at Building 6 today. 

Building 6 is is underway.

Tuesday, August 18th: Greetings! 

The crew is continuing to paint and are starting at Building 4 today. 

Painting your patio sliding door trim.

Monday, August 17th: Good afternoon! 

The painting crew is getting started today at Building 1 to prep and paint your front door frames and patio door frames as listed above on the map. 

Thursday, August 13th: Good morning! 

The crew is on their way and working on carpentry replacements for the brick mold and the kick plates. They had made it through 4 buildings before the rain stopped our work yesterday. 

We’ll keep you posted as to when the painting portion will begin. Thanks! 

Monday, August 10th: Good afternoon! 

Welcome to your project blog for the upcoming painting project at Concordia Meadows. We’ll be kicking off your project on Tuesday, 8/11 with carpentry repairs and painting of select areas.

We kindly as that you remove any small belongings from the front entry of your home as we are prepping and finishing your entry door frames and patio door kickplates. We are also asking you to leave your storm doors unlocked as applicable so we can paint your entire frame. 

We’ve posted a route map above to indicate the order of process for both the carpentry and also painting. We are anticipating the entire project to be completed in 8-12 working days.  

You can continue to follow the project progress here on the blog as we’ll provide frequent updates on progress, share photos, and inform you of any weather delays.

Thank you so much for having us and we are looking forward to being onsite!


Trent Stern

Project Manager
Ph: 612-803-5131
Email

Dana Clark

Project Manager
Ph: 763-559-5296
Email


Tags:


Leave a comment

Questions? Ask the Blue Tape Guy

roell logo

Office: 763-559-5296
Fax: 763-557-9597
7301 Penn Avenue South
Minneapolis, MN 55423