Greetings and welcome to your project blog for the upcoming painting project at Villages at Rice Creek in Shoreview. We are looking forward to being onsite!


Friday, June 26th: Greetings! 

Happy Friday ya’ll! 

We’ll be wrapping up at Villages at Rice Creek today. It has been our pleasure painting in your association and sprucing up your trim areas. Have a great rest of the summer!

Ladders up to paint the louvers.

Cruising through the garage door frames.

Thursday, June 25th: Good morning!

The crew has one more working day left! They will be finishing up tomorrow.

Painting the finishing touches!

Prepping the garage door.

Wednesday, June 24th: Good afternoon!

The crew is onsite again today continuing to prep and paint the garage doors.

Working hard painting the garage frames!

Painting garage door frame.

Tuesday, June 23rd: Greetings! 

Another beautiful day and the crew is back onsite! 

They’re about 50% through the project so we’d anticipate 2 -4 more working days. Thanks!

Garage door frame in progress

Prep and taping off the garage frame.

Monday, June 22nd: Good morning!

The crew is continuing to prep and paint the garage door frames and the gable louvers.

Taping off one of the garage door frames.

Prepping and taping off the edges.

Friday, June 19th: Good afternoon! 

The crew will return on Monday – have a great weekend!

Thursday, June 18th: Good morning! 

The crew will not be onsite today with the forecasted rain. We’ll keep you posted on their return. Thanks!

Wednesday, June 17th: Good morning! 

Welcome to your project blog for the painting project at Villages at Rice Creek in Shoreview! Here you can stay apprised of project progress, scheduling updates, and any weather delays should they come up. 

We kicked off your project yesterday and will be prepping and painting the garage door frames and the gable louvers on all of the 2 story homes. We are beginning with the prep and painting of the louvers and will start on garage doors on Thursday, 6/18. As we are prepping the louvers, there will be paint chip remnants and will be coming back to clean it up. 

This project should have minimal impact on your daily routine and we are anticipating to be onsite for 4-5 working days. 

You can continue to follow the project progress here on the blog and we’re looking forward to sprucing up your property. Thanks! 

Painting one of the gable louvers.

 


Dana Clark

Project Manager
Ph: 763-559-5296
Email
Hirsh Logo
Sherwin Williams Logo
Cabot Stain Logo
PPG Logo
Sikkens Logo
Benjamin Moore Logo

Tags:


Leave a comment

Questions? Ask the Blue Tape Guy

roell logo

Office: 763-559-5296
Fax: 763-557-9597
7301 Penn Avenue South
Minneapolis, MN 55423