Greetings and welcome to your project blog for the painting project at The Lowry. We’re looking forward to being onsite with you!


Friday, February 19th: Good morning and TGIF! 

The crew has wrapped and finished painting and cleaning up in the atrium area yesterday. They’ll be back in the next few days once areas are marked with blue tape to complete touch ups. Please leave the blue tape up as it marks areas for the crew. 

Thank you!

And time to take down the plastic.

Wrap up and clean up in the stairways.

Cleaning up in the atrium area.

Wednesday, February 17th: Greetings! 

The crew is continuing to paint in the atrium. They are utilizing the lift to paint the ceiling/skylight beams. They are also prepping the walls – smoothing, patching, and sanding areas before they paint. 

They are anticipating to be wrapped up on Friday. 

Painting the atrium beams.

Wall prep.

Going up!

Prepping and covering for wall painting.

Monday, February 15th: Good afternoon! 

The crew is prepping and covering in the atrium area. We’ll be spraying the ceiling first so lots of covering of railings, flooring, etc. After the ceiling is done, we’ll move on to paint the walls. We are anticipating 3-4 more working days in the atrium – thank you and stay warm!

All covered and ready to spray ceilings.

Refreshed and brightened up on the ceiling.

Cover, cover, and more covering.

Looking out from the top.

Covering some serious surface area in the atrium.

Brought a lift onsite to reach those top areas.

Thursday, February 11th: Good morning! 

The crew is continuing to prep and paint in the stairs wells. Prepping and covering, painting walls and ceilings, and then going through to clean up. They’ll begin on the atrium early next week. Thanks!

Ceiling prep in the stairwells.

Clean up crew.

Rolling on the paint.

Tuesday, February 9th: Good afternoon! 

At least it’s sunny outside right?! It is definitely appreciated with the polar freeze we’re in. 

The crew is working to wrap up on the 1st floor and completing some clean up and painting of select doors. They are also working in the larger stairwell – 4 stories tall. Please be mindful of wet paint and the crew in this space. Thank you!

The crew is anticipating to wrap up with the painting of 1st floor and remainder of stairwells this week and then continue to paint in the 1st floor atrium. 

Cleaning up the workspace.

Trust your ladders.

Taking over to refresh the main stairwell.

Clean up on the 1st floor.

Prep, patch, repair and paint.

Friday, February 5th: Good afternoon and TGIF! 

The crew is continuing to prep and paint in sections along the 1st floor hallway. 

Ladders going up!

Refreshing the hallway walls.

Go go gadget rollers.

Wednesday, February 3rd: Greetings! 

The crew has transitioned to the 1st floor. They’ll continue to work in sections of prepping the walls, taping off and covering areas with plastic, and then spraying the ceilings before they roll on the wall paint. 

Prepping and painting down a section of the 1st floor.

Taping off signs and plaques.

Wall prep in progress.

Monday, February 1st: Good afternoon and happy February! 

The crew is onsite and continuing on the 2nd floor. They are anticipating to be moving to the 1st floor on Wednesday of this week. After the 1st floor, they’ll move into the stairwells. 

Spraying ceilings on a section of the 2nd floor.

Prep, paint, repeat.

Prepping and smoothing the walls.

Thursday, January 28th: Greetings! 

The crew is continuing to cruise through the 2nd floor hallway – prepping and painting in sections. 

Prepping along another section of the hallway.

Ceilings get refreshed!

Paper, tape, and plastic – oh my!

Wednesday, January 27th: Good morning! 

The crew sprayed the ceiling on the 2nd floor yesterday and also started to paint the hallway walls. They’ll also begin to paint the select doors and frames. They’ll continue to work in sections of the 2nd floor – ceilings, walls, and then frames. The crew is anticipating to move down to the 1st level early next week. Thanks!

Up and then down we roll on the wall paint.

Brightening up the ceilings.

Spraying ceilings on the 2nd floor.

Refreshing the walls.

Monday, January 25th: Greetings and happy project start day!

The crew is off and running at The Lowry and we’re thrilled to be onsite and sprucing up select areas of your building. The crew will be getting started on the 2nd floor. They’ll begin with prep – taping edges, covering lights and areas we will not be completing before they get started painting. 

Covering the 2nd floor carpets.

Prepping and covering down the hallway.

Putting plastic up and over the light fixtures.

Taping off edges, trim, door frames, etc.

Friday, January 22nd: Good afternoon and welcome to your project blog for the painting project at The Lowry. We’re looking forward to getting started next week!

For your project we’ll be prepping and painting select areas in the 1st and 2nd floor hallways as well as the stairwells. Included also are select doors/frames and entry vestibule walls. 

We kindly ask that you are mindful of wet paint when traversing through the hallways – thank you! 

You can continue to follow the project progress here on the blog as we’ll post frequent updated on the crews’ progress and which floor they are working on and anticipated schedule to move to other areas. 

Please leave a comment or reach out to the contacts below with any questions or comments. Thanks!

We’re looking forward to getting started on Monday. Have a great weekend!


Dana Clark

Project Manager
Ph: 763-559-5296
Email

Hirsh Logo
Sherwin Williams Logo
Cabot Stain Logo
PPG Logo
Sikkens Logo
Benjamin Moore Logo

Tags:


Leave a comment

Questions? Ask the Blue Tape Guy

roell logo

Office: 763-559-5296
Fax: 763-557-9597
7301 Penn Avenue South
Minneapolis, MN 55423