Waycliffe II – Wayzata 2020

Waycliffe II – Wayzata

Painting Complete

Greetings and welcome to your project blog for the 2020 Painting Project at Waycliffe II in Wayzata! We are looking forward to being back onsite with you this spring!


Waycliffe II – Tentative Finishing Schedule

Building Pressure Washing Date Prep/Painting Start Date
#1 – 416/426 Tuesday, June 9th Thursday, June 11th
#2 – 238/248 Tuesday, June 9th Friday, June 12th
#3 – 278/288 Tuesday, June 9th Monday, 7/20
#4 – 318/328 Tuesday, June 9th Wednesday, June 17th


Monday, July 27th: Greetings! 

We hope you all had a great weekend! 

The crew will be returning tomorrow to complete the 2 remaining decks that need to be stained. Thanks! 

Wednesday, July 22nd: Good afternoon! 

After yesterday’s rain we have resumed our prep and painting at Waycliffe – Building #3. Thanks!

Building 3 is in progress.

Ladders up to prep and cover.

Monday, July 20th: Greetings! 

We are back onsite at Waycliffe to complete the 3rd and final building. 

Tuesday, June 23rd: Good afternoon! 

The crew has completed painting at the included buildings for painting. There are a few outstanding items that the crew will be taking care of in the next few days. Thanks so much for having us onsite and it has been our pleasure sprucing up your homes!

Friday, June 19th: Good afternoon and TGIF! 

The crew is onsite and working their way around Building #4 — painting the siding and also painting the trim. 

All hands on deck at the front entry.

Rolling on the siding.

Painting up on the peak.

Ta-da!

Thursday, June 18th: Good Morning!

The crew will be onsite until 11:30. They will be spraying at Building #4!

Working away on Building 4!

The paint is looking great.

Wednesday, June 17th: Good morning! 

Here’s an update on progress – Building #1 is complete aside from one remaining deck, #2 is complete, #3 we are skipping over for now, and #4 we are underway with prep and will begin painting soon as well. Thanks!

#4 is in progress with scraping and prepping.

Covering surfaces on the rear elevation.

Tuesday, June 16th: Greetings! 

It’s a steamy one out there! Stay cool and stay hydrated.

The crew is continuing on Buildings 1 and 2.  We’ll be skipping over the 3rd Building for now to finalize colors and be jumping from #2 to #4. Thanks!

Painting trim on Building #2.

Monday, June 15th: Good Afternoon!

The crew is onsite again today finishing up painting the deck on Building #1 and getting started on spraying and back rolling Building #2.

Back rolling on Building #2.

Spraying the siding on Building #2.

Covering for Building #2.

Friday, June 12th: Good morning! 

Happy Friday ya’ll! It’s a beautiful day to be onsite at Waycliffe II. We have crews prepping and painting at both Building #1 and #2. 

Back rolling on Building 1.

Spraying the siding on Building 1.

Prepping and covering around Building 2.

Taping off around Building 2.

Thursday, June 11th: Good afternoon! 

We are back onsite and prepping on Building #1. We’ll begin with prep work — lots of scraping, caulking, taping and covering before we begin painting. 

Finding the shade while scraping the side elevation.

Working on prep on Building 1.

Prep Day!

Tuesday, June 9th: Greetings! 

We are off! 

The crew is onsite and pressure washing all four buildings today. They are set to complete the washing on all four as well. Thanks! 

Teamwork to ready the buildings for painting.

Spraying down the siding.

Can you hear that hum of pressure washers?!

Monday, June 8th: Good morning! 

We’ll be kicking off your project tomorrow with pressure washing Buildings 1 & 2. Once the substrates are dry we’ll return to begin our prep and painting at Building #1. We are anticipating this to begin on Thursday, June 11th.

You can continue to follow the project progress here on the blog as we’ll update the finishing schedule, share progress, and alert you to any weather delays. Thanks so much for having us back onsite! 

We’re looking forward to sprucing up your buildings. See you tomorrow!

Friday, June 5th: Good afternoon! 

We are thrilled to be back onsite and refreshing several of your buildings this summer! 

We’ll be getting started the week of June 8th and will soon post more details including a route map and also a finishing schedule once they are finalized. Thanks! 

We’ll be starting with pressure washing and then return to prep and paint on the first building once the substrates have had adequate time to dry.  Thank you in advance for removing items for the pressure washing. 

We’ll see you next week! 


Dana Clark

Project Manager
Ph: 763-559-5296
Email

 


Tags:


Comments (2)

  • Judy Mitcheldon

    |

    Any idea when 238 Waycliffe will be painted?

    Reply

    • Dana

      |

      Hi Judy – I’ve added a finishing schedule and route map to the blog page. The 238 Buildings is labeled #2 so we will be washing yours and #1 tomorrow. Then set to start painting #1 on Thursday. Once complete, we’ll move to your building. This would all change if there is rain or weather delay. Stay tuned to the blog for the most up to date information. Thanks – Dana

      Reply