Waycliffe I – Wayzata

Waycliffe I – Wayzata

Project Complete

Greetings and welcome to your project blog for the 2020 Painting Project at Waycliffe I in Wayzata! We are looking forward to being back onsite with you this spring!


Waycliffe I – Tentative Finishing Schedule

Building Pressure Washing Date Prep/Painting Start Date
453-463 Monday, April 20th  May 11th
330-340 Tuesday, April 21st Monday, May 18th
520/530 Monday, April 20th Wednesday, May 20th


Wednesday, May 27th: Good morning! 

We’ll be pressing pause today with all of the overnight rain. We’re hopeful to return tomorrow. Thanks!

Tuesday, May 26th: Good afternoon! 

We hope you all had a restful and safe holiday weekend! 

After a delay this morning the crew returned this afternoon to continue on the 3rd and final building. They are anticipating one more full days worth of work. Thanks! 

Painting the trim on the side elevation.

Painting shutters on Building 3.

Friday, May 22nd: Greetings and Happy Friday!

Thanks to those who gave their lives in service to our country and those who continue to serve.

The crew is working on your decks today. We love seeing the refresh!

All brightened up!

‘Before.’

Taking a line from Bon Jovi’s ‘we’re halfway there.

Thursday, May 21st: Good afternoon! 

The crew is continuing on the 3rd and final building. Once complete, they’ll make their way around to complete areas needing touch ups as well as areas with woodpecker holes. Thanks!

Wednesday, May 20th: Greetings! 

The crew is making their way around the 2nd building and they are also starting to prep on the 3rd building today too. 

Sprucing up your entry areas.

Trim painting around Building 2.

Fresh coat of paint on the garage doors.

Tuesday, May 19th: Good afternoon! 

The crew is continuing to paint their way around Building #2. They will begin some prep work – scraping and caulking. Thanks!

Spray and back roll – repeat.

Prepping and painting the garages.

Monday, May 18th: Greetings! 

We couldn’t be happier that the rain has passed! And just in time for us to be back onsite at Waycliffe. 

The crew is starting their prep and painting at Building #2 today. 

Prepping and taping off windows at Waycliffe.

A section of Building #2 getting all prepped and covered.

Taping around Building #2.

Friday, May 15th: Good morning and happy Friday!

It’s a beautiful day and the crew is onsite and continuing their prep and painting at Building 1. They are mostly painting trim areas and will begin their prep on Building #2 on Monday, 5/18 (330-340). We will be holding off to stain any decks until after Memorial Day and the repairs are complete – thanks!

Ladders up to paint the trim.

Painting on the front elevation of Building #1.

Thursday, May 14th: Good afternoon! 

The crew is back onsite this afternoon after allowing the substrates to dry out this morning. They are continuing to prep and paint sections of Building #1. They will be starting on Building #2 on Monday, 5/18. 

Spraying the garage doors.

All fresh and spruced up!

Painting a section of siding.

Wednesday, May 13th: Greetings! 

The crew will not be onsite today with the forecasted rain. They’ll return tomorrow – thanks! 

Tuesday, May 12th: Good morning! 

It’s going to be a beautiful day! The crew is onsite and continuing to prep and prime areas before we begin painting at the 453/463 Building.

Starting at the top!

Priming a section of wood siding.

Refreshing the garage doors.

Spraying the soffits.

Monday, May 11th: Good afternoon! 

Man it feels good to be back! We are onsite and it’s prep day. We are scraping, taping, and covering on the 453/463 Building. 

Scraping around the window bump outs.

Caulking seams.

Monday, April 20th: Good morning! 

Happy project kick off day! We are thrilled to be back onsite this year and refreshing 3 of your buildings. Today we’ll be washing the 330/340 and 520/530 Buildings.

We’ll be getting started with pressure washing the 330/340 & 530/540 Buildings today and tomorrow they will wash the 453/463 Building. 

Once the areas have been washed, we’ll take a brief break before we begin our prep and painting. You will have another contractor onsite to complete the necessary carpentry work. Thanks! 

All shiny and like new!! We’ll complete the staining towards the end of the painting portion.

Cleaning off the dirt and debris.

Pressure washing your deck floors.

Friday, April 17th: Greetings and welcome to your project blog! 

We are thrilled to be back onsite this year to be prepping and finishing three more buildings in your association. As in previous years, we’ve posted a finishing schedule above to reflect start dates for each building relating to pressure washing and then prepping/painting. We are closely monitoring the weather and will update the prep/paint start date as we finalize them. Once they begin, we are anticipating about 4-6 working days to complete each building. 

You can continue to follow the project’s progress here on the blog as we’ll post daily updated in regards to progress made, any scheduling update or changes, as well as project photos. 

We are looking forward to kicking off exterior painting season at your association and can’t wait to spruce up these three buildings. Thank you all in advance for your cooperation as we work in your association! 

As always please reach out with any questions, comments or concerns as we are navigating this new normal during this global health pandemic. We are committed to the health and safety of our clients and our employees and are following the guidelines put out by the WHO and the CDC. 

 

Nick Roell

Project Manager