Winchester HOA – Blaine

Winchester HOA – Blaine

Painting Complete; Touch Ups remain

Greetings and welcome to your project blog for the upcoming deck staining and painting project at Winchester in Blaine. We are thrilled to be onsite with you!

Winchester – Route Map


Thursday, July 16th: Greetings! 

The crew has wrapped up the prep and painting on your decking. We will be going back through to complete touch ups in the next week. Thank you! 

Wednesday, July 15th: Good afternoon!

The crew is working on the deck trim on Buildings 7 and 8 today.

Painting the deck trim.

Working hard!

Tuesday, July 14th: Greetings! 

With all of the rain, the crew will not be onsite today. We’ll keep you posted on our return. Thanks!

Monday, July 13th: Good morning! 

The crew is prepping and painting starting off at Building #5 today. 

Taping off the door frame for painting.

Starting off at Building #5 today.

Friday, June 10th: Greetings!

It’s not a rain day! (Insert HAPPY DANCE) 🎉☀️

The crew is onsite and resuming their painting on the decking areas — starting at Building 1 and 2. 

Painting the deck skirts.

Prep and painting on the front entries.

Painting the door trim.

Thursday, July 9th: Good morning!

The crew will not be onsite today due to the morning rain. We hope to be able to return tomorrow. Thanks!

Wednesday, July 8th: Greetings!

Unfortunately we have yet another morning rain session that is keeping the crews offsite again today. They will return tomorrow to start painting.

Tuesday, July 7th: Good morning! 

Another morning rain session that is keeping the crew off site. They’ll return tomorrow to start painting. 

They finished up the staining on Friday and will begin the panting once they’re back onsite. Thanks!

Monday, July 6th: Greetings!

There is a rain delay today. The crew will return as surfaces dry out. We will keep you posted. 

Thursday, July 2nd: Good morning! 

The crew is getting started this morning at Buildings 4 and 5 for staining. They are planning to be onsite tomorrow and then will return on Monday, 7/6 if they don’t finish the staining tomorrow. 

Thanks so much and have a great 4th of July!

Happy and safe 4th of July!

Staining the entry steps.

Please wait ~24 hours before returning items to your decking.

Ladders up to stain edges.

Wednesday, July 1st: Greetings!

The crew has begun the staining process. They are working on Buildings #1 and #2. Thanks!

Starting to stain!

Before photo!

Making progress on the staining.

Monday, June 29th: Good morning!

There is a rain delay today due to all of the overnight and morning rain. The crew will return as surfaces dry out. We will keep you posted! 

Friday, June 26th: Greetings and happy Friday ya’ll!

The crew has completed the pressure washing. We are waiting to confirm if we are going to be chemically stripping the decks before applying the stain or proceeding with the staining as is. Thanks!

Thursday, June 25th: Good morning!

The crew is continuing to pressure wash your decks today. They are starting at Building 6. 

Pressure washing the deck.

Ladders are up to pressure wash the upper decks!

Wednesday, June 24th: Greetings!

We are off and running at Winchester! The crew is starting today with pressure washing your decks. They will be starting at Building 1 and following the map shown above. 

Monday, June 22nd: Good afternoon! 

Welcome to your project blog for the upcoming deck staining and painting project at Winchester in Blaine. 

We’ll be getting started with pressure washing of the decks and entry stairs/landings on Wednesday, June 24th. We kindly request that you please remove all personal items from your deck for the pressure washing and staining to allow for safe and unobstructed access. 

Once the substrates have had time to dry, the crew will return to begin staining the deck floors and we are projecting this to be on Monday, June 29th. Please note that the weather will impact our finishing schedule. 

You can check project progress, weather delays, and schedule  changes here on the blog as we’ll update it frequently. 

Our plan is to complete all of the deck staining the week of 6/29 before the holiday weekend so you may return items to your deck and enjoy your patios! 

We will then coming to paint the deck skirts, posts, and other areas after the deck floors are completed. 

We understand having items off of your decks for some time is inconvenient and we will do our best to complete the project promptly so you may return your items to your deck. 

Thank you so much for having us and we’re looking forward to getting started on Wednesday! 

 


Dana Clark

Project Manager
Ph: 763-559-5296
Email
Hirsh Logo
Sherwin Williams Logo
Cabot Stain Logo
PPG Logo
Sikkens Logo
Benjamin Moore Logo

Tags:


Leave a comment

Questions? Ask the Blue Tape Guy

roell logo

Office: 763-559-5296
Fax: 763-557-9597
7301 Penn Avenue South
Minneapolis, MN 55423