Shady Oak Neighbors Association – Minnetonka

Shady Oak – Minnetonka

Project Complete 

Greetings and welcome to your project blog for the upcoming painting project at Shady Oak in Minnetonka. We are thrilled to be back onsite with you!

Shady Oak – Route Map

Tentative Finishing Schedule at Shady Oak
Building Pressure Washing Start Date Prep/Painting Start Date
Building #1 – 5911, 5915, 5919, 5923 Abbott Ct Friday, 6/11 Monday, 6/14
Building #2 – 5916, 5920 Abbott Ct Saturday, 6/12 Friday, 6/25
Building #3 – 5900, 5904, 5908, 5912 Abbott Ct Monday, 6/28 Thursday, 7/1
Building #4 – 5901, 5905, 5909, 5915 Abbott Pl Wednesday, 6/30 Monday, 7/12
Building #5 – 5919, 5923, 5927, 5931 Abbott Pl Saturday, 7/3 Thursday, 7/22
Building #6 – 5920, 5924, 5928, 5932 Abbott Pl Saturday, 7/17 Friday, 7/30

Monday, August 9th: Good morning! 

The crew has wrapped up at Shady Oak — we’ll be onsite in the next few days to mark buildings/areas with blue tape for the crew to return and complete the touch ups. 

Thank you again for having us onsite! It has been our pleasure to be at Shady Oak the for last 2 months to refresh the buildings!

Thursday, August 5th: Greetings!

With the overnight and morning rain, the crew will not be onsite today. They will return tomorrow. 

Tuesday, August 3rd: Good morning!

The crew is onsite today applying primer and prepping the sides of Building #6. 

Rolling the primer on.

Prepping building 6.

Monday, August 2nd: Good afternoon! 

We can hardly believe it’s already August; time is flying! 

The crew is prepping and painting on Building #6. 

Spraying the entry ceiling.

Primer up on the siding at Building 6.

Thursday, July 29th: Greetings!

The crew is back onsite today continuing to prep and paint Building 5. Due to the rain delay yesterday Building 6 will no longer be getting started today. The crew will begin prepping it tomorrow, 7/30.

Building 5 is all prepped.

Taping off your windows and doors.

Wednesday, July 28th: Good morning!

The crew will not be onsite today due to the rain. They will return when the surfaces have had time to dry so they can continue working on your project. Have a great rest of your day!

Tuesday, July 27th: Good afternoon!

The crew is onsite today continuing to prep and paint Building 5. They are planning to start working on Building 6 on Thursday 7/29

Ladders are up as we’re taping off the windows.

Building 5 is prepped.

Thursday, July 22nd: Greetings!

The crew is moving right along the route. They have made their way to Building 5 today and have started prepping and priming.

Priming the surfaces before painting.

Tuesday, July 20th: Good afternoon!

The crew is continuing their work on Building #4 today. They are currently working on prepping and priming the surfaces. You can see this happening in the photos below.

Prepping Building #4 to be painted.

Priming the surfaces before painting so the when the paint is applied it is even.

Monday, July 19th: Good morning!

The crew is onsite this morning and they are continuing to work on Building #4. We are very pleased with the progress and results the crew has made so far and we hope you are as well!

Thursday, July 15th: Greetings!

The crew is back onsite this morning after yesterday’s rain delay. They are continuing to work on Building #4, picking up right where they left off before the rain!

Hard at work on Building 4.

Wednesday, July 14th: Good morning!

The crew will not be onsite today due to the rain. They should be back to continue working on your project tomorrow or Friday, weather permitting. 

Tuesday, July 13th: Good afternoon!

The crew is continuing their diligent work on your project and they are making great progress. Today they are picking up from where they left off yesterday spraying and backrolling at Building #4.

Spraying on the paint with the back roller ready at hand to go after the paint is on.

Monday, July 12th: Good morning!

The crew is onsite and they have moved on to prepping and painting at Building #4. 

Spraying at Building #4.

Friday, July 9th: Greetings and TGIF! 

The crew is continuing prep on Building #3 and is also starting to spray and back roll sections. 

Backing rolling the siding.

A section that is prepped, covered, scraped and ready for paint.

Thursday, July 8th: Good afternoon! 

The crew is back onsite and continuing to scrape and prep on Building #3. They’ll then spot prime these areas before starting to paint the building. 

Prep is underway on Building #3.

Scraping & spot priming.

Wednesday, July 7th: Greetings!

Unfortunately, it is still too wet for the crew to work so they will not be onsite today. They will return tomorrow to continue on your project!

Tuesday, July 6th: Good Morning!

We hope you all had a great weekend! The crew will not be onsite today but we should be back tomorrow or Thursday, weather permitting. 

Friday, July 2nd: Greetings!

The crew is continuing to prep and paint at Building #3 today. Enjoy your weekend!

Thursday, July 1st: Good morning!

Wednesday, June 30th: Greetings!

The crew is onsite and pressure washing Building #4 today. They will return tomorrow to start prepping Building #3.

Pressure washing is underway at Building #4!

Tuesday, June 29th: Good morning!

The crew is prepping and painting Building #2 today. They will be pressure washing Building #4 tomorrow.

Prepping Building #2.

Working hard on Building #2.

Monday, June 28th: Greetings!

Hope you all had a great weekend. The crew is onsite today and they are pressure washing Building #3.

Pressure washing Building #3.

The crew is ready to wash, wash, wash today!

Thursday, June 24th: Good afternoon!

The crew is continuing their work on Building #1 today. They will be pressure washing Building #3 on Monday, 6/28.

The ladder is up and we are working away.

Ready to be painted!

Wednesday, June 23rd: Greetings!

The crew is still working diligently on Building #1. They are painting the trim today.

Ladder up and painting away.

Working hard!

Tuesday, June 22nd: Good afternoon!

The crew is back onsite today and is continuing their work on Building #1. They are currently prepping and painting under the deck.

Prepping under the deck.

The paint is looking good!

Monday, June 21st: Good morning!

The crew has been waiting on carpentry for Buildings #1 and #2 to be able to return to continue/start with the prep and painting. They will be onsite on Monday, 6/28 to pressure wash Building #3.

Wednesday, June 16th: Greetings!

The crew is continuing their prep work on Building #1 today.

Ladders up & we are ready to go.

Building #1.

Tuesday, June 15th: Good afternoon!

The crew is continuing their diligent work prepping and painting Building #1 today. 

Paint scrapings.

Monday, June 14th: Good morning!

The crew is onsite this morning prepping and painting Building #1.

Friday, June 11th: Greetings & happy project start day!

The crew is off and running at Shady Oak today and the pressure washer is ready to roll! They have started washing Building #1 and will start washing Building #2 tomorrow. 

Wednesday, June 9th: Good afternoon! 

Welcome to your project blog for the upcoming painting project. We are excited to be back onsite this year!

Our crew will be kicking off on Friday, 6/11 with pressure washing. The crew will wash Building #1 – shown on the map above on Friday and then they’ll wash Building #2 on Saturday 6/12. 

We kindly request that homeowners close their windows & remove any small personal items from the outside of your home for the pressure washing to allow for safe & unobstructed access for washing. 

After the surfaces have had time to dry the crew will return to begin prep and painting on Building 1. We are projecting this prep/painting to begin on Monday, 6/14.

We are projecting that this project will likely take 5-7 weeks to complete all buildings in the 2021 scope of work so please look at our projected schedule for when work is to be performed on your specific building.

The best way to obtain a project status update and any impact it may have to your daily routine will be posted here as we’ll share progress throughout, photos, and any weather delays.

We will post subsequent notices before washing buildings 3 – 6. You can follow the progress here on the blog as we’ll update the projected finishing schedule and share any pertinent information. 

Please reach out to the contacts below if you have any questions.

We are looking forward to getting started later this week!

 


Trent Stern

Project Manager
Ph: 612-803-5131
Email

2021
Houzz Best Of 2021 - Client Satisfaction

Houzz Best Of 2021 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2020
Best of Houzz 2020 - Client Satisfaction

Best of Houzz 2020 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2019
Best of Houzz 2019 - Client Satisfaction

Best of Houzz 2019 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2018
Best of Houzz 2018 - Client Satisfaction

Best of Houzz 2018 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2017
Best of Houzz 2017 - Client Satisfaction

Best of Houzz 2017 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2016
Best of Houzz 2016 - Client Satisfaction

Best of Houzz 2016 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2015
Best of Houzz 2015 - Client Satisfaction

Best of Houzz 2015 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.

Tags:


Leave a comment

Questions? Ask the Blue Tape Guy

roell logo

Office: 763-559-5296
Fax: 763-557-9597
7301 Penn Avenue South
Minneapolis, MN 55423