Kingslee Heights HOA – Bloomington
Kingslee Heights HOA – Bloomington
Project Complete
Greetings and welcome to your project blog for the upcoming project at Kingslee Heights in Bloomington. We are thrilled to be onsite this summer.
Tuesday, August 1st: Good afternoon!
We return with great news. The crew has completed the touch ups which means your project is officially completed! Thank you again for allowing us to work for and with you this year. It has been a pleasure sprucing up your exteriors.
Tuesday, July 18th: Good morning!
The crew has completed all of the buildings for your project. A project manager will come onsite to do a final walk through and mark any areas that need touch ups. The crew will then return after that to complete any touch ups.
Thursday, July 13th: Greetings!
Your project is moving along swiftly and looking great so far. The crew is continuing to work in the West circle today.
Wednesday, July 12th: Good afternoon!
The crew is continuing to work diligently on your project. Today they are working on Buildings 10 and 11. They will be working in the West circle the remainder of the week.
Tuesday, July 11th: Good morning!
We apologize for the delay in updates but your project has been making great progress. Today the crew will be finishing up with the second coat on Buildings 1-3.
Wednesday, July 5th: Greetings!
The crew will be working on prepping and painting Buildings 1-3 and Building 5 today. Tomorrow they will be pressure washing Buildings 11 and 12.
Monday, July 3rd: Good morning!
Our crew is back onsite this morning ready to tackle Building 10. Today we will be washing Building 10, we will be returning Wednesday, July 5th to wash Buildings 11 and again on Thursday to wash Building 12. Have a great fourth!
Friday, June 30th: Good afternoon!
The crew will be onsite to wash Building 10 on Monday, July 3rd. They will return on Thursday, July 6th to wash Buildings 11 and 12.
Thursday, June 29th: Greetings!
The crew is continuing to work diligently on your project. They are making great progress on Building 6 today.
Tuesday, June 27th: Good afternoon!
After yesterday’s rain delay the crew is back onsite today working in the South circle. Tomorrow, 6/28 the crew will begin the prep work on Building 6 and pressure washing at Building 8.
Monday, June 26th: Good morning!
Your project is underway! Our crew was onsite over the weekend to start pressure washing the buildings in the South circle. Due to the poor weather today, our crew will most likely not be able to make it onsite today. We hope you all have a great day!
Monday, June 19th: Greetings!
Welcome to your project blog for the upcoming painting project. We are excited to be working together this year!
We will be finishing window trim, garage doorframes, deck railings and posts as well as other carpentry.
We are hoping to kick off your project at the end of this week!
The best way to obtain a project status update and any impact it may have to your daily routine will be posted here as we’ll share progress throughout, photos, and any weather delays.
Please reach out to the contacts below if you have any questions.
Angel Lopez
Trent Stern
Houzz Best Of 2021 - Client Satisfaction
Best of Houzz 2020 - Client Satisfaction
Best of Houzz 2019 - Client Satisfaction
Best of Houzz 2018 - Client Satisfaction
Best of Houzz 2017 - Client Satisfaction
Best of Houzz 2016 - Client Satisfaction
Best of Houzz 2015 - Client Satisfaction
Tags: Completed Projects