Lyndale Green – Bloomington
Lyndale Green – Bloomington
Project Complete
Greetings and welcome to your project blog for the upcoming painting project at Lyndale Green. We are thrilled to be back onsite with you!
Monday, September 14th: Good morning!
The crew is onsite and finishing up the shutters on the last building. We’ll be wrapping up and taking care of touch ups soon as well. Thanks!

Shutters are in progress at Building 8.

Wrapping up at Lyndale Green.
Friday, September 11th: Good afternoon!
The crew is working at Building #8 today.

Building #8 is underway.
Thursday, September 10th: Good morning!
The crew is back onsite to continuing prepping and painting at Buildings 7 & 8 today.

Prepping before we spray the stucco.

Taping off and covering windows.
Tuesday, September 8th: Greetings!
We hope you had an enjoyable and restful long holiday weekend!
The crew is prepping and painting at Building 4 & 5 today.

Prepping and covering before we paint at Buildings 4 and 5.

Spraying the stucco siding.
Friday, September 4th: Good afternoon!
The crew is painting the stucco at Building 3 and then we have a crew painting shutters at Building 6. We are anticipating to be wrapping up by mid-week next week.
Thanks and have a great holiday weekend!

Spraying the stucco.

Painting shutters at Building 6.
Wednesday, September 2nd: Good afternoon!
The crew is prepping and painting at Buildings 2 and 3 today.
Friday, August 28th: Good morning!
Welcome to your project blog for the upcoming painting project at Lyndale Green. We’ll be kicking off your project on Monday, 8/31 with prep and painting.
We’ve posted a route map above to indicate the order of process for the painting.
You can continue to follow the project progress here on the blog as we’ll provide frequent updates on progress, share photos, and inform you of any weather delays.
Thank you so much for having us and we are looking forward to being onsite!
Ben Abel
Dana Clark






Tags: Completed Projects