Rice Lake Woods – Maple Grove

Rice Lake Woods – Maple Grove

Painting Complete; Add ons remain

Greetings and welcome to your project blog for the upcoming painting project at Rice Lake Woods. We are thrilled to be onsite!

Building PW Start Date Prep and Painting Start Date
1 Friday, May 29th Monday, June 1st
2 Friday, May 29th Tuesday, June 2nd
3 Tuesday, June 2nd Thursday, June 4th
4 Tuesday, June 2nd Thursday, June 4th
5 Wednesday, June 3rd Saturday, June 6th or Monday, June 7th
6  Wednesday, June 3rd Tuesday, June 8th
7 Tuesday, June 9th Monday, June 15th
8 Thursday, June 11th Tuesday, June 16th
9 Thursday, June 11th Wednesday, June 17th


Thursday, June 18th: Good Morning!

The crew is finishing on Buildings 8 and 9 today! The walk through will be scheduled soon and then we will complete our final touch ups as well once the blue tape is marked. 

Wednesday, June 17th: Greetings!

The crews are prepping and painting at Buildings 8 and 9 today and  will be completing touch ups on Friday. We should be all wrapped up by Friday!

Nice to find some shade on this warm day!

Getting the job done!

Hard at work painting the buildings.

Painting is in progress!

Tuesday, June 16th: Good afternoon! 

It’s a hot one folks! Stay cool & stay hydrated!

The crew is finishing up on Buildings 6 and 7 today and they are also starting their prep on Building 8. Will post photos when we get them from the crew – thanks!

Friday, June 12th: Happy Friday ya’ll! 

The crew is prepping and painting at Buildings 6 and 7. 

Have a great weekend!

Thursday, June 11th: Greetings! 

Buildings 5 and 6 are in progress today and also pressure washing the last two buildings. 

Pressure Washing in progress.

Carpenters in action!

Wednesday, June 10th: Good afternoon! 

The rain has cleared and the surfaces have dried out. We are back onsite! 

The carpenters are working at Building 7 and then crews are painting on Building 6. They are also completing touch ups on the 3 and 4th Buildings. Thanks!

Tuesday, June 9th: Greetings! 

Busy day for our crew! They are wrapping up on Buildings 4 and 5 today and will also begin on Building 6. They are washing Buildings 7 and 8 too. 

With the impending afternoon rain, they’ll likely have to press pause and will return as they’re able. Thanks!

Monday, June 8th: Good afternoon! 

It’s a HOT one out there!

The crews are prepping and painting at Buildings 4 and 5 today. They will start on 6 tomorrow as well as pressure wash Buildings 7 and 8. 

Painting trim at the entry.

Carpentry in progress.

Trim painting on Building 5.

Friday, June 5th: Greetings and happy Friday! 

The crew is prepping and painting at both 3 and 4 today. They are planning to start on 5 either tomorrow or Monday. Thanks!

Thursday, June 4th: Good afternoon! 

The crew is finishing up on Buildings 1 and 2 today. They will also be starting their prep work on both Buildings 3 and 4 as well as finishing the pressure washing on 5 and 6 — busy day! 

Spraying across the front elevation.

Carpentry in progress on Buildings 1 and 2.

Painting trim.

Pressure washing in progress for Buildings 5 and 6.

Painting trim and removing plastic from windows.

Tuesday, June 2nd: Greetings! 

We are prepping and painting at Buildings 1 & 2 today and also washing 3 & 4. Tomorrow we will pressure washing 5 & 6.

Ladders up — spraying across Building 1.

Prepping and painting on the rear elevation.

Painting the soffits.

Pressure washing Buildings 3 and 4 today.

Monday, June 1st: Good afternoon! 

The crew is onsite and prepping and painting at Building #1 today. We will also be washing more buildings this week — 3/4 on Tuesday, 6/2 and 5/6 on Wednesday, 6/3. Thank you!

Friday, May 29th: Greetings and Happy Friday! 

The crew is onsite and pressure washing Buildings 1 & 2 today. They will return on Monday, June 1st to begin their prep and painting at Building 1 – thanks!

Spraying down the siding.

Team work and washing before painting.

Pressure washing is in progress.

Wednesday, May 27th: Good afternoon! 

Welcome to your project blog for the painting project at Rice Lake Woods. The crew we be onsite on Friday, May 29th to start with pressure washing of Building #1 and #2. We kindly ask that you remove any small or personal items from the outside of your home for the pressure washing to allow for safe and unobstructed access for washing. 

Once the substrates have had time to dry, the crew will return to begin prepping and finishing of the included areas of your home: siding, soffits, misc. fascia, front support brackets, deck posts/skirts, wood deck railings/spindles, front door frames, garage doors/frames, and previously painted patio door frames. 

We are projecting to be back and start at the first building on Monday, June 1st. This is a large project that will likely take about a month to complete all of the buildings. 

We will soon post a project finishing schedule so you can know when to anticipate painting at your building. We will be updating this blog site frequently with progress, photos, and any changes to the schedule or weather delays should they come up!

Thank you again for having us and we’re looking forward to being onsite on Friday, May 29th!

 


Dana Clark

Project Manager
Ph: 763-559-5296
Email

 

Hirsh Logo
Sherwin Williams Logo
Cabot Stain Logo
PPG Logo
Sikkens Logo
Benjamin Moore Logo

Tags:


Leave a comment

Questions? Ask the Blue Tape Guy

roell logo

Office: 763-559-5296
Fax: 763-557-9597
7301 Penn Avenue South
Minneapolis, MN 55423