Greetings and welcome to your project blog for the upcoming deck repair and staining project! We’re looking forward to being onsite with you!

Buildings Staining Start Date
1-3 Friday, 7/2
4-6 Thursday, 7/8
7-9 Friday, 7/9
10-12 Monday, 7/12
13-15 Tuesday, 7/13
16-18 Friday, 7/16
19-21 Monday, 7/19
22-24 Tuesday, 7/20
25-27 Wednesday, 7/21
28-29 Thursday, 7/22
30-32 Friday, 7/23

Wednesday, August 5th: Good afternoon! 

Thursday, July 29th: Good afternoon!

The crew is back onsite after yesterday’s rain delay. They are picking up where they left off and are continuing to stain your decks. The crew should be wrapping up tomorrow hopefully. 

Wednesday, July 28th: Good morning!

The crew will not be onsite today due to the rain. They will return when the surfaces have had time to dry so they can wrap up your project. Have a great rest of your day!

Monday, July 26th: Good afternoon! 

The finish line is in sight and we are approaching the end of the project. Thank you all for your patience as we made our way through the route and stained 125 decks. 

They are working at Building #30 today and will be wrapped up by Wednesday, as long as the weather can stay dry. 

Crew is working at Building 30 today.

Loving the refreshed stained decks.

Thursday, July 22nd: Good afternoon!

Another day means more staining at Crossroads! The crew is close to wrapping up your staining project. They are starting out today staining the deck at Building 28.

Building 28’s deck is looking great!

Wednesday, July 21st: Greetings!

Keeping to their schedule, the crew has made their way to stain the decks at Buildings 25-27. They will most likely be finishing up staining the decks at all of the buildings on Friday. 

We love the results on Building 25 so far!

Working hard on Building 26.

Tuesday, July 20th: Good afternoon!

The crew is moving right along the route and making great progress. They are staining the decks at Buildings 22-24 today. 

Working diligently to stain your decks.

Monday, July 19th: Greetings!

The crew is back at it this morning at Crossroads. They are staining the deck at Building 20 currently. If the weather cooperates the crew should be wrapping up with staining your decks by the end of the week/early next week.

Staining away this Monday morning.

Friday, July 16th: Good morning!

The crew is back onsite after the rain delay. They are returning to the beginning of the route to stain the new wood on the decks at these Buildings. We’ve posted an updated schedule above. Please know this is tentative and has the flexibility to change ahead or later due to weather, etc. Thanks so much for your cooperation and patience as we make our way through Crossroads!

Staining the new wood at Building 1.

Working hard at Building 2 this Friday morning.

Thursday, July 15th: Greetings!

Unfortunately, the crew will not be back onsite today because the surfaces are still too wet to stain. They will return tomorrow when the decks have had ample time to dry. 

Wednesday, July 14th: Good morning!

The crew will not be onsite today due to the rain. They should be back to continue working on your project tomorrow or Friday, weather permitting. 

Tuesday, July 13th: Good afternoon!

The crew is continuing on track with the schedule posted above. They are making great progress and your decks are looking great! Today the crew started off staining the decks of Buildings 13 and 14. 

Sprucing up the deck at Building 13.

Even from afar, you can see how much of a difference the stain is making & it looks great!

Monday, July 12th: Good morning!

The crew has returned after the weekend and is starting off on Buildings 10 and 11.

Prepping underneath the deck.

Staining in progress!

Friday, July 9th: Good afternoon and TGIF! 

The crew is starting off at Building 7 and 8 today. 

Staining at Building #8.

Sprucing up the decks at Building 7.

Thursday, July 8th: Greetings! 

The crew is back onsite and picking up where they left off at Building #4. We’ve pushed back the tentative schedule above to account for the few rain days. We appreciate your patience as we depend on clear and dry conditions to continue staining. Thank you!

Kicking off at Building #4 this morning.

Staining in progress.

Wednesday, July 7th: Good afternoon!

Unfortunately, it is still too wet for the crew to work so they will not be onsite today. They will return tomorrow to continue on your project!

Tuesday, July 6th: Greetings!

We hope you all had a great weekend! The crew will not be onsite today but we should be back tomorrow or Thursday, weather permitting. 

Friday, July 2nd: Good morning!

The crew started staining at Building 1 today. They are projecting to complete about 15 decks each day, weather permitting, so about 3-4 buildings will be stained each day. We are working to get more product and will resume staining on Tuesday, 7/6 pending we have product on site. There will be no staining this Saturday, Sunday, or Monday. We recommend that homeowners wait about 24 hours after staining before returning items to their decks. Enjoy your weekend!

The stain color is looking great!

Staining your decks is underway.

Wednesday, June 30th: Good afternoon!

The crew is back onsite today and following along their route. They have made their way to Buildings 25 and 26.

Pressure washing Building 26 on this beautiful day!

The crew is working hard to pressure wash your buildings!

Tuesday, June 29th: Good morning!

The crew is continuing along their route and is pressure washing at Building 17 currently.

Working hard!

Monday, June 28th: Good afternoon!

Hope you all had a great weekend. The crew is onsite and they are pressure washing at Building 15.

The sun is out and we are pressure washing away!

Friday, June 25th: Greetings!

The crew is continuing along the route to pressure wash all of the buildings. They are currently washing at Building 12.

Pressure washing away this afternoon.

Thumbs up for Friday!

Thursday, June 24th: Good afternoon!

Another day, more buildings to pressure wash! The crew has started washing at Buildings 7 and 8 today. 

A great day for pressure washing!

Wednesday, June 23rd: Greetings!

The crew is continuing along their pressure washing route today! They are washing at Building 5 currently.

Pressure washing at Building 5.

Look at that focus!

Tuesday, June 22nd: Good afternoon!

The crew is off and running at Crossroads Townhomes today and the pressure washer is ready to roll! We had a bit of confusion with the route this morning so the crew started at Building 18 and washed both 18 and 17 before returning to the original route. They are now washing at Building 1 and will work their way around the route to pressure wash all of the buildings in the next several days.

Your project is underway!

Pressure washing the deck at Building 1.

Monday, June 21st: Good morning! 

Welcome to your project blog for the upcoming deck repair and staining project at Crossroads Townhomes in Lakeville!

Our crew will be kicking off on Tuesday, 6/22 with pressure washing your decks. We understand this project will have an impact on your daily routine and we will do our best to complete the project promptly so everyone may return the contents of your deck and enjoy the remainder of the summer. 

After washing, the crew will return to begin prep and staining on the first building and the crew will stain the buildings in the same order as they were pressure washed. Please note that the weather will impact our schedule as we will need the decks to be dry before applying the stain.

We are projecting this prep/staining to begin on Monday, 6/28 at the beginning of the route. 

You can continue to follow the project progress here on the blog as we’ll post updates, share photos, update the finishing schedule and alert you of any weather delays. Please reach out to the contacts below if you have any questions. 

We’re looking forward to getting started soon!


Trent Stern

Project Manager
Ph: 612-803-5131
Email

Dana Clark

Project Manager
Ph: 763-559-5296
Email

2021
Houzz Best Of 2021 - Client Satisfaction

Houzz Best Of 2021 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2020
Best of Houzz 2020 - Client Satisfaction

Best of Houzz 2020 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2019
Best of Houzz 2019 - Client Satisfaction

Best of Houzz 2019 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2018
Best of Houzz 2018 - Client Satisfaction

Best of Houzz 2018 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2017
Best of Houzz 2017 - Client Satisfaction

Best of Houzz 2017 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2016
Best of Houzz 2016 - Client Satisfaction

Best of Houzz 2016 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2015
Best of Houzz 2015 - Client Satisfaction

Best of Houzz 2015 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.

Tags:


Leave a comment

Questions? Ask the Blue Tape Guy

roell logo

Office: 763-559-5296
Fax: 763-557-9597
7301 Penn Avenue South
Minneapolis, MN 55423