Greetings and welcome to your project blog for the 2018 painting project at Timber Creek Crossing in Plymouth. We are thrilled to be back onsite!


Route Map @ Timber Creek

Welcome Video


Tuesday, July 3rd: Good morning residents of Timber Creek!

The passing rain has halted our painting for today and with the holiday tomorrow, the crew will return on Thursday and start at the 24th Building.

We have a skeleton crew in our office the rest of the week as we’re spending time with family and enjoying the holiday, but we will resume with daily updates on Monday. Though with clear weather, we anticipate to finish by week’s end. Thanks and have a happy and safe 4th of July and a great rest of the week

Nothing more nostalgic than Ray Charles singing ‘America the Beautiful’ and the gang playing a night game of baseball. 

Thanks and we hope you have a great 4th of July holiday!


Monday, July 2nd: Greetings and happy July! 

We can’t believe it’s already July; the summer us flying by!

The crew started their staining on Building 20 today and they are anticipating to be done by tomorrow will all of the decks, pillars, and stairs. 

Ladder manuevering skills, check!

Taking care of the deck support pillars.


Friday, June 29th: Hello and TGIF! 

It’s a hot one out there folks! We hope you’re all staying cool!

The crew is starting their prep, painting, and staining at Building #17 today. And they hope to get through all the buildings by early next week, weather permitting.

Painting your support columns.

Step by step.


Wednesday, June 27th: Hello and welcome back after a few rainy and wet day! 

We are glad to be back onsite. The crew is starting on Building #8 today with prepping and painting your deck skirts, posts, and entry risers and skirts. Thanks!

Priming one of the entry pillars.

Completing prep work: caulking one of the entry pillars.


Friday, June 22nd: Hello and TGIF! This week has flown by and the crew is making their way along the route to your decks and entry stairs. 

The crew is starting their day on Buildings #5 and #6 ~ so they’re getting through 4/5 each day. They are prepping and painting deck skirts, posts, and entry stair risers and skirts. 

Have a great weekend!

Painting your entry risers.

Painting the deck skirt.


Thursday, June 21st: Good afternoon! 

The crew is off an running at your association. They’ve started staining your decks at the 4012 Building and will follow the route posted above. They are anticipating to get through 5 Buildings a day. We will continue to post progress updates so you can know when to expect us at your deck- Thanks!

Painting your deck skirts.

Painting one of the entry pillars.

Painting a deck support column.


Wednesday, June 20th: Good morning residents of Timber Creek! 

Our crew lead was onsite this morning inspecting your buildings and they are still wet from all of the rain. We’ll reutrn tomorrow to begin our prep and painting. Thanks for your understanding and patience!


Friday, June 15th: Mother Nature has ordered up some ‘Hot & Humid’ weather for the weekend with the possibility of showers/storms scattered throughout. You can take your chances and head outdoors for numerous Farmer’s Markets as well as the Stone Arch Bridge Festival happening over the weekend. Don’t forget about Father’s Day on Sunday! 3 cheers for all the dads, grandpas, uncles, great-grandpas, and all of the dudes that have influenced you!

The crew is onsite pressure washing in advance of our prep and painting. Thanks and have a great weekend!

Nothing beats the heat like pressure washing!

We’re pressure washing in advance of painting to prep the surfaces for optimal adhesion.


Thursday, June 15th: Hello residents of Timber Creek and welcome to your project blog! This summer we’ll be finishing numerous areas throughout your association: deck trim on the front and rear elevations of your home including rear elevation deck pillars, deck skirts, and entry risers and skirts only. 

We’ll begin with pressure washing on Friday, June 15th. Once the surfaces have had time to dry, we’ll be back onsite to begin the prepping and painting portion of the project. We’ll be posting a route map to designate the route our crew will follow when completing your buildings- this will allow you to know when we’ll be at your unit. We anticipate the entire project to take 8-12 working days, weather permitting. And we are tentatively planning to begin prepping and painting on the first building on Monday, June 18th. 

Thanks so much and we’ll see you tomorrow for pressure washing!


Roell Painting

Project Manager
Ph: 763-559-5296
Email

Tags:


Questions? Ask the Blue Tape Guy

roell logo

Office: 763-559-5296
Fax: 763-557-9597
7301 Penn Avenue South
Minneapolis, MN 55423