Linden Park HOA – New Hope

Linden Park HOA – New Hope

Project Complete

Greetings and welcome to your project blog for the upcoming painting and staining project at Linden Park in New Hope. We are thrilled to be onsite!


Tuesday, September 8th: Good morning! 

We hope you all had a great holiday weekend! 

The crew is onsite today completing some repair and replacement work to a few of these decks. We will be letting the decks sit and cure for a bit and we’ll return in about 2 weeks to stain these areas. Thanks! 

Replacements in progress.

Carpentry work today at Linden Park.

Friday, September 4th: Good morning! 

The crew has started to stain the deck stacks today. They are also making their way along the front of the building with their prep and painting of decking items. They are projecting to be onsite for 2-4 more working days. 

Thanks and have a great holiday weekend!

Making our way across the front of the building.

Onsite and starting to stain.

Starting to stain the stacks at the beginning of the route.

Tuesday, September 1st: Good afternoon! 

The crew is off and running at Linden Park. 

They’ll begin in the SE corner and work on the deck stacks in a clockwise motion. 

Painting the door trim on your deck stacks.

Ladders going up to paint at your deck.

Monday, August 31st: Good morning Linden Park!

With the morning rain, we’ll be postponing our painting start until tomorrow. Thanks! 

Friday, August 28th: Greetings and TGIF! 

We’ll be getting started on Monday, 8/31. The crew will start in the SE corner and move clockwise around the building. NOTE this is updated from a previous post. 

We will first be completing the painting aspects of the project – patio door frames, HVAC doors/frames. Then carpentry repairs will be completed to repair/replace marked deck boards. Once repaired/replaced we will stain the decks. 

The crew will move around the building and complete the decks in ‘stacks.’ 

Have a great weekend and we’ll see you onsite on Monday, 8/31. 

Wednesday, August 26th: Good afternoon! 

The crew is wrapping up with the pressure washing today and will return on Monday to begin staining. Thanks! 

Tuesday, August 25th: Greetings! 

We are off!!

The crew is pressure washing at Linden Park. They’ll be starting along the SE side of the buildings and working their way counter clockwise around the Building. 

Spraying down your deck stacks.

Washing and prepping for staining.

Monday, August 24th: Good morning! 

We’ll be getting started at Linden Park tomorrow with pressure washing of the included decks. Thanks and see you tomorrow!

Wednesday, August 19th: Good afternoon! 

Hello and welcome to your project blog for the deck trim and deck staining project at Linden Park. We are looking forward to being onsite with you! 

The crew will be kicking off on Monday, August 24th with pressure washing of the included areas within your complex. For the washing, we kindly request that you close your windows and remove all personal items from your deck to allow unobstructed access to the decking while washing. 

Once we’ve washed your deck you may return the contents to your deck; however, you will need to remove them one more time for the staining. We are projecting the staining to begin at the beginning of the route on Wednesday, August 26th. 

We anticipate to be onsite for about 2-3 weeks to complete the staining. You can continue to follow the project progress here as we’ll post frequent updates, share photos, and alert you of any weather delays should they come up. Thanks and we’ll see you onsite on Tuesday! 


Roell Painting

Project Manager
Ph: 763-559-5296
Email

Hirsh Logo
Sherwin Williams Logo
Cabot Stain Logo
PPG Logo
Sikkens Logo
Benjamin Moore Logo

Tags:


Leave a comment

Questions? Ask the Blue Tape Guy

roell logo

Office: 763-559-5296
Fax: 763-557-9597
7301 Penn Avenue South
Minneapolis, MN 55423