Highlands at Lakeside HOA – Chanhassen 2024

Highlands at Lakeside HOA – Chanhassen

Project Complete

Greetings and welcome to your project blog for the upcoming painting project at Highlands at Lakeside in Chanhassen. We are thrilled to be back working with you this summer!

 

Building

Pressure Washing Date

Prep / Painting Start Date

8728/8736/8744 Lake Riley Drive Thursday, July 25th  Monday, July 29th
8711/8719/8727 Lake Riley Drive Thursday, July 25th  Tuesday, August 6th
8800/8808 Lake Riley Drive  Thursday, July 25th  Monday, August 12th

Thursday, October 3rd: Good morning!

The crew has completed all of the touch ups that were needed which means your project is officially finished!  It was our pleasure to be onsite working with and for you. 

Friday, August 16th: Greetings!

The crew made great progress this week and was able to complete all of the buildings yesterday.  A production manager will be onsite to complete a walk through in the coming days and mark any areas in need of touch ups.  Have a great weekend!

Monday, August 12th: Good morning!

We hope everyone had a great weekend.  The crew is onsite and working on the last building of your project!  

Thursday, August 8th: Good afternoon!

The crew began the 2nd building on Tuesday, 8/6.  They are continuing to work diligently on this building.

Monday, August 5th: Good morning! 

We’ve completed building 1 and will be starting prep on the 2nd building tomorrow. Thank you all for your cooperation while we completed Building 1. Once all buildings are complete, we will set up a walk through to mark any areas missed, touch ups spots, etc before we are fully finished. 

Have a great week!

Thursday, July 25th: Good morning! 

We’re off and running with the pressure washers today. Thanks for your cooperation to move any small items / rugs away from the exteriors. We’re looking forward to getting started painting next week. We’ve listed the tentative finishing schedule above. We will be able to better project the start dates of the 2nd and 3rd buildings once we get started, but likely about 7-10 working days for each building.

Walking through the project scope.

Monday, July 22nd: Greetings Residents of Highlands at Lakeside!

Welcome to your project blog for the upcoming exterior painting project. We are excited to be working together again this year!

Our crew will be pressure washing, and prepping & painting select exterior surfaces of three buildings for the scope of this project – 8800/8808 & 8711/8719/8727 & 8728/8736/8744.

The pressure washing will begin on Thursday, 7/25 and we will wash all buildings. Once the substrates have had adequate time to dry, the crew will return to begin prepping & painting process on the first building – 8800/8808. We are projecting that prep & painting will begin on Monday, 7/29. We are projecting that each building will take approximately 7-10 days to complete. Please be mindful that weather may alter this finishing schedule.

We understand this project will have an impact to your daily routine so we will do our best to complete the project promptly to be sure everyone can return to their daily routine as soon as possible. The best way to obtain a project status update will be posted here as we will share progress throughout, photos, and any weather delays.

Please reach out to the contacts below if you have any questions.

We are looking forward to getting started later this week!


Angel Lopez

Production Manager
Ph: 952-208-0895
Email

Dana Clark

Project Manager
Ph: 763-559-5296
Email

2021
Houzz Best Of 2021 - Client Satisfaction

Houzz Best Of 2021 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2020
Best of Houzz 2020 - Client Satisfaction

Best of Houzz 2020 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2019
Best of Houzz 2019 - Client Satisfaction

Best of Houzz 2019 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2018
Best of Houzz 2018 - Client Satisfaction

Best of Houzz 2018 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2017
Best of Houzz 2017 - Client Satisfaction

Best of Houzz 2017 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2016
Best of Houzz 2016 - Client Satisfaction

Best of Houzz 2016 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2015
Best of Houzz 2015 - Client Satisfaction

Best of Houzz 2015 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.

Tags:


Leave a comment

Questions? Ask the Blue Tape Guy

roell logo

Office: 763-559-5296
Fax: 763-557-9597
7301 Penn Avenue South
Minneapolis, MN 55423