Rice Lake Woods – Maple Grove

Rice Lake Woods – Maple Grove

Project Complete

Greetings and welcome to your project blog for your upcoming painting project at Rice Lake Woods in Maple Grove. We are thrilled to be back onsite this summer to spruce up your exteriors.

Building Pressure Washing Start Date Prep/Painting Start Date
1 Wednesday, 6/9 Saturday, 6/12
2 Wednesday, 6/9 Saturday, 6/19
3 Tuesday, 6/22 Monday, 6/28
4 Tuesday, 6/22 Wednesday, 7/7
5 Wednesday, 6/23 Thursday, 7/15
6 Tuesday, 6/29 Tuesday, 7/20
7 Tuesday, 6/29 Tuesday, 8/3
8 Friday, 7/2 Monday, 8/9
9 Friday, 7/2 Wednesday, 8/11

Wednesday, August 18th: Good afternoon!

The crew is onsite today finishing up Building 9.

Thumbs up for wrapping up Building 9.

Giving Building 9 a fresh coat.

Putting the finishing touches on Building 9.

Wednesday, August 11: Greetings! 

The crew is finishing up on Building 8 today and will begin their prep work on Building 9 as well. They are hoping to be wrapping up with this final building next week Tuesday or Wednesday, weather permitting. 

Thank you!

Spraying the new paint onto your buildings.

Thursday, August 5th: Good morning! 

The crew is continuing on Building 7 – they are tentatively set to start on Building 8 on Monday. Thanks!

Protecting your windows from paint.

Continuing to prep Building 7.

Covering all surfaces that will not be painted.

Wednesday, August 4th: Greetings!

The crew is onsite continuing the prepping and painting of building 7 that was started yesterday. 

Building 7 is all prepped.

Spraying paint onto the building.

Monday, August 2nd: Good afternoon! 

SO crazy it’s now August – where has the summer gone?!

The crew is painting the trim on Building 6 and will start prep/painting on Building 7 tomorrow. 

Painting trim on the roof line.

Finishing up the trim on #6.

Refreshing the window frames.

Thursday, July 29th: Good afternoon!

The crew is onsite today after another rain delay yesterday. They are finishing the prep and painting on Building 6. The crew will be starting the prep work on Building 7 on Monday, 8/2.

Finishing up Building 6!

Thursday, July 22nd: Good morning!

**Update** Unfortunately due to the rain the crew had to leave early. Hopefully, they will be back tomorrow to continue working on your project but we will have to see what the weather does. Have a great rest of your day!

The crew started prepping Building 6 on Tuesday and they have been working on prepping and painting this building since. Today they are currently working on covering windows with plastic to protect them from the paint.

Lots of prep work is happening at Building 6 this morning.

Monday, July 19th: Greetings!

The crew is continuing their work on Building 5 today. They are working on spraying and trim painting the finishing currently. The crew will begin prepping and painting Building 6 tomorrow. 

Prepping the door frame.

Look at that focus!

Covering the door with plastic.

Friday, July 16th: Good morning!

The crew is back onsite this morning and they are continuing to progress around the route. The crew started prepping and painting at Building 5 yesterday and today they will be continuing to work on this Building. 

Preparations on Building 5 are underway.

Caulking to prepare for painting.

Wednesday, July 14th: Good afternoon!

Unfortunately, the weather did not hold out for us so the crew will not be onsite today due to the rain. They should be back to continue working on your project tomorrow or Friday, weather permitting. 

Tuesday, July 13th: Greetings!

The crew has been continuing to work diligently on your project and they are making great progress. They are continuing to prep and paint at Building #4 today and are projecting to start Building #5 tomorrow, weather permitting.

Thursday, July 8th: Good afternoon! 

The crew is prepping and painting their way around Building #4. They are projecting to start on the next Building, #5 on Monday, 7/12. 

Spraying the siding on Building 4.

Prep and caulking continues on Building #4 as well.

Taping off and covering the doors and windows.

Wednesday, July 7th: Good afternoon!

The crew is back onsite and is continuing their diligent work on your project. They are finishing up on Building 3 and are starting on Building 4 as well.

Painting the window frame.

Time to prep, prep, prep!

Tuesday, July 6th: Good morning!

We hope you all had a great weekend! The crew will not be onsite today but we should be back tomorrow or Thursday, weather permitting. 

Friday, July 2nd: Greetings!

Wednesday, June 30th: Good morning!

Tuesday, June 29th: Greetings!

The crew will be pressure washing Buildings 6 and 7 today. They will also be continuing to work on Building 3.

Monday, June 28th: Good afternoon!

The crew is onsite and they are working diligently on your project. They are finishing up painting Building 2. The crew has also started prepping Building 3 today. 

Friday, June 25th: Greetings!

The crew is onsite and they are painting the trim on Building 2. Have a great weekend!

The trim painting is looking great.

Thursday, June 24th: Good afternoon!

The crew is continuing to spray and back roll on Building 2. It is key to follow up spraying with back rolling to ensure that the coating being applied gets “worked in: to underlying substrates. You can see the crew spraying the paint in the photos below.

Spraying above the garage door.

The paint is looking great!

Wednesday, June 23rd: Greetings!

The crew is pressure washing Building 5 today. They are also spraying and back rolling the paint on Building 2 as well. 

Tuesday, June 22nd: Good afternoon!

The crew is onsite today pressure washing Buildings 3 and 4. They are also prepping and priming at Building 2.

Pressure washing is underway.

Priming the railing.

Thursday, June 17th: Greetings!

The crew should be wrapping up their work on Building 1 by the end of the day today or early tomorrow. They will then transition to begin prepping Building 2 on Saturday. The crew will be back on Monday, 6/21 to pressure wash Buildings 3 and 4.

Painting the trim on Building 1.

Building 1 railings being painted.

Wednesday, June 16th: Good afternoon!

The crew is continuing their diligent work on Building 1 today. They are picking up from where they left off yesterday with prepping and priming.

Ladders up & we are priming away.

Action shot of the crew caulking.

Monday, June 14th: Greetings!

The crew is onsite this morning prepping and priming Building 1.

Priming Building 1.

Alejandro, Santiago, Uriel, & Omar are onsite and ready to get to work!

Prep, prep, prep!

Lots of prepping this morning.

Wednesday, June 9th: Good afternoon & happy project start day!

The crew is off and running at Rice Lake Woods today and the pressure washer is ready to roll! They have started washing at Buildings 1 and 2 and will make their way around the route to pressure wash all of the buildings in the next few days.

Pressure washing is underway!

Monday, June 7th: Good morning!

Welcome to your project blog for the upcoming painting project. We are excited to be back onsite this year!

Our crew will be kicking off on Wednesday, 6/9 with pressure washing, which will likely take the crew several days to complete.

We kindly request that homeowners close their windows & remove any small personal items from the outside of your home for the pressure washing to allow for safe & unobstructed access for washing. 

After the surfaces have had time to dry the crew will return to begin their prep and painting on Building 1. We are projecting this prep/painting to begin on Friday, 6/11.

We are projecting that this project will likely take 5-7 weeks to complete all buildings in the 2021 scope of work so please look at our projected schedule for when work is to be performed on your specific building.

The best way to obtain a project status update and any impact it may have to your daily routine will be posted here as we’ll share progress throughout, photos, and any weather delays.

Please reach out to the contacts below if you have any questions.

We are looking forward to getting started this week!


Roell Painting

Project Manager
Ph: 763-559-5296
Email

2021
Houzz Best Of 2021 - Client Satisfaction

Houzz Best Of 2021 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2020
Best of Houzz 2020 - Client Satisfaction

Best of Houzz 2020 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2019
Best of Houzz 2019 - Client Satisfaction

Best of Houzz 2019 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2018
Best of Houzz 2018 - Client Satisfaction

Best of Houzz 2018 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2017
Best of Houzz 2017 - Client Satisfaction

Best of Houzz 2017 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2016
Best of Houzz 2016 - Client Satisfaction

Best of Houzz 2016 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2015
Best of Houzz 2015 - Client Satisfaction

Best of Houzz 2015 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.