Prep & Painting IN PROGRESS

Greetings and welcome to your project blog for the upcoming pressure washing and painting project. We’re looking forward to being onsite and refreshing the exteriors of your buildings!

Building Pressure Washing Start Date Prep/Painting Start Date
1 Thursday, 5/13 Monday, 5/17
2 Thursday, 5/20 Wednesday, 5/26
3 Thursday, 6/3 Wednesday, 6/9
4 Wednesday, 6/9 Monday, 6/14
5 Monday, 6/14 Wednesday, 6/16
6 Wednesday, 6/16 Friday, 6/18
7 Monday, 6/21 Wednesday, 6/23


Thursday, June 24th: Good afternoon!

The crew is continuing to work diligently on Building 7. They are prepping and painting, as well as replacing deck boards. 

Prepping the window.

Window prep on one side, painting on the other!

Deck board replacement.

Wednesday, June 23rd: Good morning!

The crew is back onsite today and has started prepping and painting at Building 7.

Painting at Building 7 has begun!

Teamwork is key!

Monday, June 21st: Greetings!

The crew is pressure washing Building 7 today. They are also doing touch-ups and carpentry on Building 6 today as well.

Friday, June 18th: Good afternoon!

The crew is onsite today and they have started prepping and painting at Building 6. Have a great weekend!

Prepping the door.

Thursday, June 17th: Greetings!

The crew is continuing their work on Building 5 today. They will finish up with both the painting and carpentry by the end of the day. The crew will then start prep/painting and carpentry on Building 6 tomorrow.

Wednesday, June 16th: Good afternoon!

The crew is onsite today and is working diligently on Building 5. They have started painting and are also working on the carpentry for this building today.

Tuesday, June 15th: Greetings!

The crew pressure washed Building #5 yesterday. Today they are working on prepping and painting Buildings #3 and #4.

Prepping the garage door.

Painting the deck railing.

Monday, June 14th: Good morning!

The crew is onsite this morning painting Building #3. They will also start prepping Building #4.

Thursday, June 10th: Greetings!

The crew is continuing their work on prepping Building #3 today.

Prepping the stairs.

Wednesday, June 9th: Good morning!

The crew is onsite and has started prepping at Building #3.

Prepping is underway at Building #3.

Prepping the window.

Tuesday, June 8th: Good afternoon!

The crew is continuing to paint Building #2 today. They are currently working on the backside of the building. 

Focused and working hard!

Prepping away.

Monday, June 7th: Good morning!

Hope you all stayed cool this weekend! The crew is onsite and picking up where they left off on painting Building #2.

Painting Building 2

Working hard to get the job done.

Friday, June 4th: Greetings!

The crew is back onsite today and they are continuing to paint Building #2. Have a great weekend!

Ladders up and we are painting away.

Thursday, June 3rd: Good morning!

The crew has started painting Building #2 today.

All ready to go.

Tuesday, June 1st: Good afternoon and Happy June!

The crew is back onsite after a beautiful memorial weekend! They are continuing their work from where they left off last Wednesday. 

Friday, May 28th: Greetings!

The crew will not be onsite today because it is still too wet to work. Have a great memorial weekend!

Thursday, May 27th: Good morning!

The crew will not be onsite today but we are hoping to be back tomorrow as long as the weather cooperates. 

Wednesday, May 26th: Greetings!

The crew is almost done with Building #1 and should be starting on Building #2 soon. They have also begun prep for Building #3.

Tuesday, May 25th: Good afternoon! 

The crew is continuing to prep and paint in sections of Building #1. We are also completing the select carpentry on Building #1 and the other as well. Please know that if you have made Ted from your management company or Trent from Roell aware of your carpentry need we do have it on our list and we will get it completed. It may look sporadic in the crews carpentry movement, but we just have an evolving list and will work our way through the approved adds, changes, etc. 

If you do have a carpentry concern or additional work, please email Trent – contact info listed below. Thank you!  

Monday, May 24th: Greetings!

The crew is onsite and painting Building #1 today. 

Ladders are up and the crew is ready to paint!

Friday, May 21st: Good morning!

Another rain delay unfortunately, so the crew will not be onsite today. Have a great weekend!

Thursday, May 20th: Greetings!

Unfortunately, due to the rain again today the crew will not be onsite.

Wednesday, May 19th: Good morning!

Due to the rain yesterday we are going to let things dry out before coming onsite today. The crew will be back around lunchtime to continue working!

The crew is now back onsite doing some carpentry.

Back at it!

Tuesday, May 18th: Greetings!

The crew is prepping Building #1 today. The carpentry is complete on Buildings #1 and #2. They will pressure wash Building #2 later this week.

Prepping is underway.

The crew is hard at work!

Ladder is up and the crew is ready to go.

Monday, May 17th: Good Afternoon!

Hope you all had a great weekend! The crew is back on site and prepping Building #1 today. 

Ladders up and ready to prep.

Prepping Building #1.

Thursday, May 13th: Greetings! 

We are off and running at Cahill with pressure washing on Buildings #1 and #2. The crew will also begin to complete carpentry repairs. The repairs will be completed prior to beginning any painting, but some prep – scraping caulking etc will be happening prior as well. 

Spraying the siding areas.

Wednesday, May 12th: Good morning! 

Welcome to your project blog for the upcoming painting project at Cahill of Edina! 

We are thrilled to be back onsite this summer. We’ll be kicking off your project with pressure washing tomorrow, May 13th. We’ll begin washing areas in preparation for painting. The crew may also be cleaning your gutters while we make our way through and pressure wash. 

Please remove any small items, furniture, plants away from working areas to allow for unobstructed access while washing and also prep/painting. 

We’ve posted a map above to designate the route the crew will follow to wash and prep/paint your buildings. We’ll be getting started on the south end of the property and work our way from Building #1 – Building #7. In total we are anticipating to be onsite for 8 – 10 weeks to complete the washing, carpentry repairs, and then painting. 

Once buildings are washed, the carpenters will be making their way around the building to complete their repairs before any of the painting can begin. So you may notice some time between washing and seeing a crew back to complete carpentry and then prep/painting at your building. 

You can stay apprised of project progress here on the blog as we’ll post frequent updates regarding washing dates, and then prep/painting start dates for each building, and any weather delays should they come up.

Please reach out if you have any questions and we’re looking forward to getting started this week! 


Trent Stern

Project Manager
Ph: 612-803-5131
Email

Dana Clark

Project Manager
Ph: 763-559-5296
Email

2021
Houzz Best Of 2021 - Client Satisfaction

Houzz Best Of 2021 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2020
Best of Houzz 2020 - Client Satisfaction

Best of Houzz 2020 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2019
Best of Houzz 2019 - Client Satisfaction

Best of Houzz 2019 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2018
Best of Houzz 2018 - Client Satisfaction

Best of Houzz 2018 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2017
Best of Houzz 2017 - Client Satisfaction

Best of Houzz 2017 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2016
Best of Houzz 2016 - Client Satisfaction

Best of Houzz 2016 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2015
Best of Houzz 2015 - Client Satisfaction

Best of Houzz 2015 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.

Tags:


Leave a comment

Questions? Ask the Blue Tape Guy

roell logo

Office: 763-559-5296
Fax: 763-557-9597
7144 Shady Oak Road
Eden Prairie, MN 55344