Villas at River’s Edge – Rodgers

Villas at River’s Edge – Rodgers

Project Complete

Greetings and welcome to your project blog for your upcoming painting project at Villas at Rivers Edge in Rodgers. We are thrilled to be onsite this summer to spruce up your exteriors.

Building Pressure Washing Start Date Prep/Painting Start Date
Building 1 – 24117, 24119 Tuesday, 6/15 Friday, 6/18
Building 2 – 24161, 24163 Tuesday, 6/15 Monday, 6/21
Building 3 – 24223, 24227 Tuesday, 6/15 Tuesday, 6/22
Building 4 – 24235, 24239 Tuesday, 6/22 Thursday, 6/24
Building 5 – 24185, 24187, 24193, 24195 Tuesday, 6/22 Friday, 6/25
Building 6 – 24124, 24122, 24126, 24128 Tuesday, 6/22 Wednesday, 6/30
Building 7 – 24063, 24065, 24067, 24069 Monday, 6/28 Tuesday, 7/6
Building 8 – 24051, 24053, 24057, 24055 Monday, 6/28 Friday, 7/9
Building 9 – 24105, 24107 Monday, 6/28 Monday, 7/12

Friday, July 16th: Good morning!

We have great news to report, your project is fully complete! It was our pleasure being onsite and working with and for you. We hope you are enjoying the newly painted exteriors and have a great rest of your summer!

Tuesday, July 13th: Good afternoon!

The crew will be wrapping things up at Villas at River’s Edge by the end of the day today. We will be doing our walk-through and marking things up with blue tape for touch-ups in the next several days. Please do not remove the tape, this indicates to the crew what needs to be touched up. Thank you!

Monday, July 12th: Greetings!

The crew is continuing their diligent work on your project and is near wrapping it up! They have started prepping and painting on Building 9 today and will complete it by the end of the day tomorrow.

The windows have been covered at Building 9.

The crew is hard at work on your building.

Friday, July 9th: Good afternoon and TGIF! 

The crew is starting to prep on Building #8. 

Taping off and covering at Building #8.

And off we go on #8!

Thursday, July 8th: Greetings! 

The crew is continuing to prep and paint Building 7. Building 8 is projected to be started tomorrow. 

Prepping Building 7

Results look great!

 

Wednesday, July 7th: Good afternoon!

Tuesday, July 6th: Good morning!

We hope you all had a great weekend! The crew will not be onsite today but we should be back tomorrow or Thursday, weather permitting. 

Friday, July 2nd: Greetings!

Wednesday, June 30th: Good morning!

The crew is almost finished with Building 5 and will be wrapping up there soon. They will start prepping and painting Building 6 around noon.

Building 5 is looking great!

Tuesday, June 29th: Good afternoon!

Monday, June 28th: Greetings!

The crew is onsite today and will be pressure washing Buildings 7, 8, and 9. They will not be painting today because there is a possibility of rain at noon. 

Pressure washing 3 buildings today.

Friday, June 25th: Good morning!

The crew has been making great progress at Villas at River’s Edge! They will be finishing up painting Building 4 today and then will begin the prep and painting of Building 5. On Monday the crew will return to pressure wash the last three Buildings.

Building 4 is looking great!

The results are awesome.

Tuesday, June 22nd: Good afternoon!

The crew is onsite and the pressure washer is ready to roll again. Today they will be washing Buildings 4, 5, & 6. The crew will also be starting the prep and painting on Building 3.

The pressure washer is ready to go!

Monday, June 21st: Greetings!

The crew has started prepping and painting at Building 2 today. They will be pressure washing Buildings 4, 5, and 6 tomorrow.

Prepping is underway at Building 2.

Ready to start painting!

Friday, June 18th: Good afternoon!

The crew is back onsite today and they have started prepping and painting at Building 1. They will be back tomorrow as well to continue working on Building 1. Have a great weekend!

Thursday, June 17th: Good morning!

The crew had an add-on at a previous project that they are finishing up so they will not be onsite today. They will return tomorrow to start prepping and painting Building 1. 

Tuesday, June 15th: Greetings!

The crew is off and running at Villas at River’s Edge and the pressure washer is ready to roll! They have started washing at Building 1 and will make their way around the route to pressure wash all of the buildings in the next few days. 

Your project is underway!

Ladder is up & we are ready to go.

Monday, June 7th: Good afternoon!

Welcome to your project blog for the upcoming painting project. We are excited to be back onsite this year!

Our crew will be kicking off on Tuesday, 6/15 with pressure washing, which will likely take about 1-2 days for the crew to complete.

 We kindly request that homeowners close their windows & remove any small personal items from the outside of your home for the pressure washing to allow for safe & unobstructed access for washing. 

After the surfaces have had time to dry the crew will return to begin their prep and painting on Building 1. We are projecting this prep/painting to begin on Thursday, 6/17.

We are projecting that this project will take 3-4 weeks to complete. The best way to obtain a project status update and any impact it may have to your daily routine will be posted here as we’ll share progress throughout, photos, and any weather delays.

Please reach out to the contacts below if you have any questions.

We are looking forward to getting started next week!


Nick Roell

Project Manager
Ph: 763-559-5296
Email

2021
Houzz Best Of 2021 - Client Satisfaction

Houzz Best Of 2021 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2020
Best of Houzz 2020 - Client Satisfaction

Best of Houzz 2020 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2019
Best of Houzz 2019 - Client Satisfaction

Best of Houzz 2019 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2018
Best of Houzz 2018 - Client Satisfaction

Best of Houzz 2018 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2017
Best of Houzz 2017 - Client Satisfaction

Best of Houzz 2017 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2016
Best of Houzz 2016 - Client Satisfaction

Best of Houzz 2016 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2015
Best of Houzz 2015 - Client Satisfaction

Best of Houzz 2015 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.

Tags:


Leave a comment

Questions? Ask the Blue Tape Guy

roell logo

Office: 763-559-5296
Fax: 763-557-9597
7301 Penn Avenue South
Minneapolis, MN 55423