Parkview at Parker’s Lake – Plymouth
Parkview at Parkers Lake – Plymouth
Painting Complete
Greetings and welcome to your project blog for the 2020 painting project at Parkview at Parker’s Lake in Plymouth. We are thrilled to be onsite with you!
Parkview at Parkers Lake – Tentative Schedule |
||
Building | Pressure Washing Date | Prep/Painting Start Date |
Phase I: Buildings 1-6 | Thursday, May 14th | Monday, May 18th |
Phase 2: Buildings 7-12 | Tuesday, May 26th | Wednesday, June 3rd |
Phase 3: Buildings 13-18 | Monday, June 8th | Thursday, June 18th |
Wednesday, July 22nd: Good afternoon!
The crew is completing their touch ups at Parkview today and will be wrapping up tomorrow by lunchtime. We’ll then present the project to your Board/Manager for a Final Walkthrough and take care of any outstanding areas.
Thanks!
Tuesday, July 21st: Greetings!
Our Production Manager Jesse will be onsite this afternoon to mark the buildings with blue tape. This is depict areas needing touch ups. Please leave the tape up for the crew. Thank you!
The crew will return onsite within the next few days to complete the touch ups.
Wednesday, July 15th: Good afternoon!
The crew is finishing up the remaining areas at Parkview today and through the end of the week. They will be completing touch ups after the blue tape is marked.
Friday, June 10th: Greetings!
It’s not a rain day! (Insert HAPPY DANCE) 🎉☀️
We are back onsite and rounding out Building 18 today – hopefully we finish up today if not tomorrow. We’ll then be marking areas with blue tape for touch ups. Please leave these up for the crew – thanks!
Thursday, July 9th: Good morning!
The crew will not be onsite today due to the morning rain. We hope to be able to return tomorrow.
Wednesday, July 8th: Good afternoon!
The rain has cleared and we are back onsite!
The crew is prepping and painting at Building #18 today— we can see the finish line!
Monday, July 6th: Greetings!
The crew will not be onsite today with the morning rain. We are hopeful to return tomorrow. Thanks!
Tuesday, July 7th: Good morning!
This week is off to a rainy start — but the rest of the week looks clear, fingers crossed. We’ll be back tomorrow!
Thursday, July 2nd: Good morning!
The crew will resume their painting today and tomorrow -and they are hopeful to finish up by tomorrow. We’ll then be completing touch ups after blue tape is marked next week. Thanks!
Wishing everyone a safe and happy 4th of July!
Wednesday, July 1st: Happy July!
The crew is onsite and starting at Building 17 today.
Tuesday, June 16th: Good afternoon!
The crew is back onsite after yesterday’s rain and they are getting started at Building #16 today.
Monday, June 29th: Good morning!
There is a rain delay today due to all of the overnight and morning rain. The crew will return as surfaces dry out. We will keep you posted!
Friday, June 26th: Good morning!
The crew is hoping to return after lunch. It was raining a bit this morning — we’ll keep you posted on their return.
Thursday, June 25th: Greetings!
The crew is working at Building 15 today.
Wednesday, June 24th: Good Afternoon!
The crew is starting at Building 14 today. They will continue to prep and paint the select areas on this building.
Monday, June 22nd: Good Morning!
The crew is starting off on Building 13 today.
Friday, June 19th: Hello and TGIF!
We are into Phase III. The crew is prepping and painting at Building 13 today.
Have a great weekend!
Thursday, June 18th: Good Morning!
The crew is working on Building 12 today and should be able to finish it as long as the rain holds off!
Wednesday, June 17th: Greetings!
The crew needed to spend more time working on Building 11 yesterday. They’ll be finished with it before lunch and then return after lunch to start at Building 12.
Tuesday, June 16th: Good afternoon!
It’s a steamy one folks – make sure to stay hydrated!
The crew is back on track and working at 11 and then onto 12 today too.
Monday, June 15th: Good morning!
We hope you all had a great weekend!
We had a mix-up with our labeled buildings/route map and apologize for any confusion with whether buildings had been complete.
Today they are finishing on #10 and will move onto #11. Thank you!
Friday, June 12th: Good afternoon and TGIF!
The crew is working on and finishing Building 12 and also starting on 13 — we have reached Phase III!
Thursday, June 11th: Good morning!
We are finishing up on Building 11 this morning and will be started on Building 12 after lunch. Thanks!
Wednesday, June 10th: Good afternoon!
The rain has cleared and surfaces have dried. We are starting out at Building #11 today.
Tuesday, June 9th: Good afternoon!
The crew got started at Building #10 today. The forecasted rain has rolled in and they are pressing pause for the day. Stay tuned for their return tomorrow – thanks!
Monday, June 8th: Greetings!
It’ a HOT one, but there’s no place we’d rather be than sprucing up your buildings at Parkview!
The crew is starting off at Building #9 today. They are also beginning to wash buildings in the final phase, Phase III (Buildings 13-18) today as well. Thanks!
Friday, June 5th: Good afternoon!
We are prepping and painting at Building 8 today. We’ll also be washing the buildings in Phase III starting on Monday, 6/8. Thanks and have a great weekend!
Thursday, June 4th: Greetings!
The crew is wrapping up on Building 7 and will move on 8 today as well. Thanks!
Wednesday, June 3rd: Good afternoon!
The crew finished up on Building 6 today and then started on Building 7 after lunch. Moving right along on schedule and on the route!
Tuesday, June 2nd: Greetings!
We are continuing on Building #6 today — prep, cover, and painting included trim areas.
Monday, June 1st: Good afternoon!
We are back onsite and the crew is finishing up their prep and painting of Building 5 and will move onto Building 6 tomorrow morning. They’ll be into Phase II mid-late week as well.
Friday, May 29th: Greetings and Happy Friday!
The crew is onsite and working their way around Building 5 and will be starting 6 tomorrow or Monday, 6/1. They’ll then be moving into Phase II with Building 7. Thanks!
Thursday, May 28th: Good afternoon!
The rain has passed and the substrates have dried fully. The crew is back onsite and they are currently on Building #4.
Wednesday, May 27th: Good morning!
We’ll be pressing pause on painting today with all of the overnight rain. We’re hopeful to return tomorrow. We will be finishing up the pressure washing of Buildings 7-12 today though. Thanks!
Tuesday, May 26th: Good afternoon!
We hope you all had a restful and safe holiday weekend!
The crew is back onsite and they are finished with Buildings 1 & 2 and are painting at Building 3. They are also pressure washing Phase II – Buildings 7-12 over the course of today and tomorrow. Thanks in advance for moving small items from the exterior of your home!
Friday, May 22nd: Greetings and Happy Friday!
The crew is starting their prep and painting at Building #3 today. We will be washing Phase II – Buildings 7-12
Wednesday, May 20th: Good afternoon!
The crew is wrapping up on Building 1 and is also working on Building 2 today.
Tuesday, May 19th: Greetings!
The crew is onsite and continuing to prep and paint select trim on the units in Building #1.
Monday, May 18th: Good afternoon!
Prep day— as you can see from the video and photos, we are taking our time to thoroughly prep and cover areas we are not painting. This makes it so much more efficient to have everything ready to go before we start spraying and back rolling.
Looking forward to being onsite with you all for the next few weeks!
Thursday, May 14th: Good morning!
Happy Project Kick-off Day!
We have started onsite at Parkview at Parkers Lake with pressure washing the first six buildings. We’ll then return on Monday, 5/18 to begin prep and painting your wood trim at Building #1.
Wednesday, May 13th: Good morning!
Welcome to your project blog for the upcoming painting project at Parkview at Parker’s Lake. We are thrilled to be onsite with you!
We’ll be getting started on Thursday, May 14th and Friday, May 15th with pressure washing of the first 6 Buildings – Phase I – see above for our route map. Building #1 is the 2100 Building and then we’ll be moving clockwise around Shenandoah Ct and finally ending at the 2185 Building. We will be completing the necessary carpentry work at this time as well before we get started with the painting.
We kindly ask that you please remove any some personal items from the exterior of your home for the pressure washing to allow for safe and unobstructed access during the washing. Once the washing is complete, you may return these items.
Once these areas have had time to dry completely we’ll return onsite to begin our prep and painting, starting at Building #1, which we anticipate to be on Monday, May 18th. The areas we will be finishing select areas of your trim (door frames, fascia, and louvers).
You can continue to follow the project progress here on the blog as we’ll post frequent updates, project photos, and any weather delays should they come up.
We want to thank you for having us and we are looking forward to sprucing up your buildings!
Dana Clark