Greetings and welcome to your project blog for the upcoming project at International Village in Bloomington. We are thrilled to be back onsite.


Wednesday, July 27th: Greetings!

The crew has essentially wrapped things up with your project and now it is just a matter of coordinating schedules so your project supervisor, Jesse, can come out and mark areas in need of touch ups with blue tape. We kindly ask that after the blue tape pieces are put up that residents leave them where they are as they direct the team members to fix accordinly.

Wednesday, July 20th: Good morning!

The crew is onsite and continuing to paint the Heidelberg Building. They will be wrapping things up with this building by the end of the week.

The crew is hard at work painting the trim this morning.

 

Tuesday, July 19th: Greetings!

Monday, July 18th: Good afternoon!

The crew is continuing to prep and paint at the Heidelberg Building today. They will be wrapping things up with your project on Friday, 7/22. Then your project supervisor, Jesse, will come onsite to walk through and mark areas in need of touch ups.

Continuing to work diligently on the prep and painting of the Heidelberg Building.

Friday, July 15th: Greetings!

The crew is onsite and they are continuing to work diligently on your project. They are picking up where they left off with the prep and painting today. Have a great weekend!

Up, up & away we paint on our ladders.

Getting some caulking work done before the painting begins.

Monday, July 11th: Good morning!

Friday, July 8th: Greetings & Happy Friday!

The crew will not be onsite today as the stucco is wet and therefore they are not able to paint. They will return on Monday to continue painting the Heidelberg building, weather permitting.

Wednesday, July 6th: Good morning!

Painting continues on the Heidelberg Building this morning. We are very pleased with the progress that has been made thus far.

The Heidelberg Building is looking good!

Tuesday, July 5th: Greetings again residents of International Village.

Hope you all had a terrific and long holiday weekend! Work continues on the Heidelberg Building. Consistent with the spirit the building, the crew is working with German like efficiency! 

Friday, July 1st: Happy July!

The crew is onsite and working on painting the Heidelberg Building today.

Painting away at the Heidelberg Building this morning.

Wednesday, June 29th: Good afternoon!

The crew is onsite and continuing to work diligently on your project. Today they are prepping the Heidelberg Building to get it ready to be painted.

Prep, prep, prepping away!

Monday, June 27th: Greetings!

The crew will be finishing up with the Orleans Building today. The Heidelberg Building was pressure washed on Saturday. The crew will begin the prep work on this building today as well.

Friday, June 24th: Good afternoon!

The crew is onsite and painting the window frames on the Orleans Building. Tomorrow they will return to pressure wash the Heidelberg Building. The crew will begin the prep and painting for the the Heidelberg Building on Monday, June 27th.

Painting the window frames on the Orleans Building.

Monday, June 20th: Greetings!

The crew has started painting window frames on the Yorkshire Building. They are also working on prepping the garage at the Orleans Building. Stay cool today!

Painting the window frames at the Yorkshire Building.

Prep work is underway on the garage at the Orleans Building.

Friday, June 17th: Good morning!

The rain is finally gone and the crew is onsite! They are continuing to work on the Yorkshire Building today. Have a great weekend!

Painting the Yorkshire Building on this sunny Friday.

Wednesday, June 15th: Greetings!

Another rain delay unfortunately out at International Village today. The crew will be able to return tomorrow to continue working on the Yorkshire Building. 

Tuesday, June 14th: Good morning!

The crew is back onsite today after the rain delay. They are beginning the prep work to paint the stucco on the Yorkshire Building.

Monday, June 13th: Greetings!

The crew will not be onsite today due to the rain. They will return once the substrates have had time to dry.

Friday, June 10th: Good morning!

The crew will be wrapping up with the stucco painting on the Orleans Building today. Have a great weekend!

Painting away on this beautiful Friday.

Wednesday, June 8th: Greetings!

The crew is onsite and continuing their hard work on the Orleans Building. They are spraying on the paint and then following it by back rolling to make sure the paint is pressed firmly and evenly into the substrates.

Working together to apply the paint to the Orleans Building.

Thursday, June 2nd: Good afternoon!

The crew is continuing to work diligently on your project. They are picking up where they left off yesterday on the Orleans Building.

Working on prepping the windows.

Windows are prepping and we are ready to paint!

Wednesday, June 1st: Greetings!

Tuesday, May 31st: Good afternoon!

We hope everyone had a wonderful Memorial Day Weekend. The crew is back onsite and continuing to work on prepping and priming the Orleans building. They will begin painting tomorrow, weather permitting.

Priming the surfaces to be ready to paint.

Back after the weekend & working hard!

Friday, May 27th: Happy Friday!

The crew is working on prepping and priming the Orleans building today. They will return on Tuesday, May 31st to start painting. Have a great Memorial Day Weekend!

Working hard on this beautiful Friday.

Thursday, May 26th: Good Morning!

The crew is back onsite after yesterday’s rain delay. They are currently working on the carpentry for the Yorkshire building. 

Working hard on Yorkshire.

Ladder is up and we are working away!

Wednesday, May 25th: Good Afternoon!

Tuesday, May 24th: Greetings!

The crew will begin painting on Thursday, 5/26 weather permitting.

Monday, May 23rd: Good Afternoon!

The crew is onsite today pressure washing the Orleans building. They are also continuing to do carpentry work. 

Ladders up and we are ready to go!

Pressure washing is underway.

Tuesday, May 3rd: Greetings Residents of International Village!

Welcome to your project blog for the upcoming project. We are looking forward to being onsite!

This year’s project is going to involve the performance of misc carpentry repairs, aesthetic updates and painting to 3 apartment buildings & 7 garage buildings on the property including: Heidelberg (including 2 detached garages), Orleans (including 2 detached garages), Yorkshire (including 2 detached garages), Taj Mahal garage, and Barcelona garage.

We will be doing the prep & finishing of select surfaces on the resident buildings & detached garages including the following: stucco siding, wood siding (where applicable), soffits, fascia, wood windows, A/C covers, and door frames. 

Please reach out to the contacts below if you have any questions.


Trent Stern

Project Manager
Ph: 612-803-5131
Email

2021
Houzz Best Of 2021 - Client Satisfaction

Houzz Best Of 2021 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2020
Best of Houzz 2020 - Client Satisfaction

Best of Houzz 2020 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2019
Best of Houzz 2019 - Client Satisfaction

Best of Houzz 2019 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2018
Best of Houzz 2018 - Client Satisfaction

Best of Houzz 2018 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2017
Best of Houzz 2017 - Client Satisfaction

Best of Houzz 2017 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2016
Best of Houzz 2016 - Client Satisfaction

Best of Houzz 2016 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2015
Best of Houzz 2015 - Client Satisfaction

Best of Houzz 2015 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.

Tags:


Leave a comment

Questions? Ask the Blue Tape Guy

roell logo

Office: 763-559-5296
Fax: 763-557-9597
7301 Penn Avenue South
Minneapolis, MN 55423