Riverview at Upper Landing – St. Paul

Riverview at Upper Landing – St. Paul

Project Complete

Greetings and welcome to your project blog! We are thrilled to be onsite working with and for you on this project!

F – Front (Lift) B – Back (Ladder) Green – Completed

Thursday, July 25th: Good afternoon!

The crew has officially wrapped things up with your project!  It has been a pleasure working with and for you this summer and we hope you enjoy your newly refreshed exteriors.

Thursday, July 18th: Greetings!

The crew was onsite earlier and was working diligently on your project.  Today they were working on Stack 14B. 

Working hard on this sunny day!

Tuesday, July 16th: Good afternoon!

After yesterday’s rain delay the crew is back onsite!  They are continuing to work on Stack 11B as well as Stack 12B.

The crew is continuing to work their way around your property!

Monday, July 15th: Greetings!

We hope everyone had a great weekend.  The crew will not be onsite today due to the rain.

Thursday, July 11th: Good afternoon!

Our crew is onsite today completing work on Stack 11B. Your project is coming together!

Stack 11B getting its new makeover.

Tuesday, July 9th: Greetings!

Our crew has been onsite today working on completing work on Stack 10 B. The project is getting close to being completed, anticipation is building to see the final result. 

Our ladders are our and ready to complete work at Stack 10B.

Monday, July 8th: Good afternoon!

Our crew has been working onsite continuing to make progress on the project. We are now at stack 9B, these stacks will be completed with ladders rather than lifts. 

The ladders are onsite at Stack 9B today.

Tuesday, July 2nd: Good morning!

Due to unfortunate weather conditions, we are unable to work onsite today. We apologize for any inconveniences this may cause and we hope to be back onsite as soon as we can, weather permitting of course. 

Monday, July 1st: Greetings!

Our crew has been onsite today working on Stack 15F. We are over the halfway mark and anticipation grows everyday to see this end result. 

Giving stack 15F a renovated look.

Wednesday, June 26th: Good afternoon!

Our crew has been onsite today working on stack 9F. We are excited about the progress being made on the project despite Mother Nature not being on our side. 

Using a lift on the outside buildings to effectively paint every surface.

Stack 9F getting a refreshing coat of paint.

Monday, June 24th: Greetings!

Our crew is onsite today working on Stack 7F. They will continue to work in numerical order around the Building, then they will complete the inside (Blue) stacks. 

Prepping and painting Stack 7.

Thursday, June 20th: Good afternoon!

Due to the expected rainy weather, our crew is unable to be onsite and complete work today. We hope to be back onsite as soon as weather permits, have a great day!

Monday, June 17th: Good morning!

Due to unfortunate weather, our crew is unable to preform work onsite today. We apologize for any inconveniences this may cause and we hope to return onsite as soon as weather permits. 

Tuesday, June 11th: Greetings!

Our crew was onsite yesterday painting stacks 1F,2F, and 3F. Due to a weather delay, we will not be able to make it onsite and complete work today, we hope to be back out tomorrow to paint stack 4F, and 19F, weather permitting of course. Once Stack 19F is completed, we will move onto 1B and work in numerical order up to 7B. 

We also plan on starting 7F this Thursday 6/13 or Friday 6/14 depending on weather conditions. 

When spraying paint onto your stack, you may notice partial or full plastic on the windows. This is to protect your windows from any paint and cannot be removed until the paint is full dried, we apologize for any inconvenience this may cause. 

Thursday, June 6th: Good morning!

Unfortunately, the strong wind has made it difficult for our crew to spray and preform work. We are hoping to be back onsite as soon as possible, weather permitting of course. 

Tuesday, June 4th: Good afternoon!

Our crew is back onsite this morning working on prep work. We hope to continue being onsite throughout the week however, the unfortunate weather has made it hard to complete work onsite. We ask that you bear with us through this rain and apologize for any inconveniences this may cause. 

All hands on deck when it comes to prepping a building.

Monday, June 3rd: Good morning!

Due to last night’s rain, the property is not dry enough for our crew to be onsite today. We apologize for any inconveniences this may cause, we look forward to getting back onsite as soon as we can. 

Wednesday, May 29th: Greetings!

The crew is back onsite and working diligently on your project.  They are currently working on stack 4F.

Tuesday, May 28th: Good morning!

We hope everyone had a great weekend.  Due to the weather the crew will not be onsite today.

Wednesday, May 22nd: Greetings!

Due to the surfaces still being too wet to paint the crew will not be onsite today.  They will return tomorrow to continue painting!

Please note the new map above.  We will update this as the crew continues to complete stacks by filling in the completed stacks in green.

Monday, May 20th: Good morning!

The crew will not be onsite today due to the rain.  Weather permitting, they will return tomorrow to continue painting. 

Friday, May 17th: Greetings!

The crew is onsite and painting today!  If you see us outside your window your stack is coming up next.  As long as we do not have any rain delays we will be onsite and painting throughout the week.  Have a great weekend!

Painting away on this sunny Friday!

Wednesday, May 16th: Good morning!

The crew will not be onsite today due to the rain.  As long as the surfaces have time to dry they will return tomorrow to continue.

Tuesday, May 14th: Good afternoon!

The crew has begun the painting process onsite! It looks as though they will be completing about one stack per day.  On Thursday, the crew will start in the courtyard with ladder work.

Friday, May 10th: Greetings!

The crew is continuing to prep around the building.  Have a great weekend!

Wednesday, May 8th: Good afternoon!

The crew is continuing to work on caulking around the building. We hope everyone has been enjoying this sunny day!

More caulk work!

Monday, May 6th: Good morning!

The crew will be finishing up with pressure washing today as well as beginning the caulking.

Pressure washing away on this sunny day!

Thursday, May 2nd: Greetings Residents of Riverview at Upper Landing!

This project blog will be used as a communication tool to relay pertinent project information regarding start dates, photos of progress, and updates to the finishing schedule. We are excited to be a part of your renovation project.

You have probably noticed our crew onsite the past few days! They have begun the pressure washing process for your project. The fronts and sides of the buildings have been washed so far this week. Tomorrow the courtyards will be washed and the crew should be finished with these on Monday. Once the pressure washing is complete the crew will begin caulking on Monday, 5/6 followed by painting likely starting on Wednesday, 5/8, weather permitting.

We will begin painting on the North elevation of the 360 Building following the route posted on the map above.  The crew will be working off the lift completing one stack at a time.  After the first day of painting we will have a better idea of how many stacks we are able to complete each day, giving us a clearer timeline for the remaining stacks on the buildings.  In conjunction with the lift work being performed on the front and sides of the buildings, the painters will be painting courtyard elevations.  We will have more information on these soon!

If you have any questions or concerns please reach out to the contacts below! We are looking forward to getting started next week.


Jason Schell

Production Manager
Ph: 651-503-2477
Email

David Lee

Project Manager
Ph: 763-559-5296
Email

2021
Houzz Best Of 2021 - Client Satisfaction

Houzz Best Of 2021 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2020
Best of Houzz 2020 - Client Satisfaction

Best of Houzz 2020 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2019
Best of Houzz 2019 - Client Satisfaction

Best of Houzz 2019 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2018
Best of Houzz 2018 - Client Satisfaction

Best of Houzz 2018 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2017
Best of Houzz 2017 - Client Satisfaction

Best of Houzz 2017 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2016
Best of Houzz 2016 - Client Satisfaction

Best of Houzz 2016 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2015
Best of Houzz 2015 - Client Satisfaction

Best of Houzz 2015 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.

Tags:


Leave a comment

Questions? Ask the Blue Tape Guy

roell logo

Office: 763-559-5296
Fax: 763-557-9597
7301 Penn Avenue South
Minneapolis, MN 55423