Centennial Lakes – Edina 

Project Complete


Greetings ands welcome to the blog for your upcoming project at Centennial Lakes in Edina. We are thrilled to be onsite completing work for you this summer! 


Wednesday, August 7th: Good morning!

The crew has returned to complete all of the additional touch ups that were needed.  This means your project is officially completed!  It has been a pleasure to work with and for you this summer.

Monday, July 29th: Greetings!

We hope everyone had a great weekend!  The crew has completed all of the decks for your project.  They still need to return to complete additional touch ups in the buildings. 

Friday, July 19th: Good afternoon!

The crew has been working diligently on your project and is making great progress throughout!  Have a great weekend. 

Monday, July 15th: Good morning!

Happy project kick off day!  The crew is onsite and ready to start your project. 

Tuesday, July 9th: Greetings!

This project blog will be used as a communication tool to relay pertinent project information regarding start dates, photos of progress, and updates to the finishing schedule. We are excited to be a part of your renovation project.

This project consists of renovating and repairing deck railings. We are anticipating starting to prep and paint on Monday, July 15th weather permitting of course. 

This project is expected to take only 12-15 working days to complete. This project should have minimal impact on your daily routine. 

If you have any questions or concerns please reach out to the contacts below! We are looking forward to getting started next week.