Century Commons – Oakdale 

Prep & Painting In Progress


Greetings and welcome to your project blog for your upcoming painting project at Century Commons in Oakdale. We are thrilled to be onsite this spring to spruce up your exteriors.


 


Thursday, May 14th: Good morning, all! The crew was onsite this morning to begin preparation for painting work. Here is the planned sequence of work below:

Building # Prep & Painting Start Date Status
First Group – 40, 27, 43, 33, 23 5/14/2026 In Progress
Second Group – 35, 1, 4, 14, 6 5/15/2026 (estimated)  Not Started
Third Group – 16, 8, 12, 11, 21 5/18/2026 (estimated) Not Started

Wednesday, May 13th: Hi all – carpentry began today and we will be onsite tomorrow to start preparation for the painting work. See the map above – any house with black trim is planned to be part of the project work. Please see the project welcome video above from the Project Manager, Danielle. Reach out to us if you have any questions and we’ll get an update tomorrow.

Have a great evening!

Tuesday, May 12th: Hello residents – carpentry was expected to begin today but we will be starting carpentry work tomorrow. The prep for painting will begin as planned on Thursday, May 14th.

Friday, May 8th: Greetings!

Welcome to your project blog for the upcoming exterior project. We are excited to be working together this year! Our carpenter will soon begin exterior carpentry repairs in select areas of the association as part of the preparation for the upcoming spring painting project. We expect to begin on: TUESDAY, MAY 12TH    

 We anticipate that the specified carpentry scope of work that was approved by the community’s association Board to be completed in 2 – 3 business days.

We plan to return to begin preparation for painting on: THURSDAY, MAY 14TH

We anticipate that the specified painting scope of work that was approved by the community’s association Board to be completed in 5 – 7 business days. Overall, this project will have minimal impact your daily routine and we appreciate your patience and cooperation. To stay up to date on project progress, scheduling updates (including weather delays), and other important information, please visit your property-specific project portal at:

Please reach out to the contacts below if you have any questions.

We’re looking forward to working together!


Production Manager –

Jason Schell

Production Manager
Ph: 763-559-5296
Jason@roellpainting.com

Paint Project Manager –

Danielle Baumgartner

Carpentry Project Manager –

Trent Stern