Greetings and welcome to your project portal for the upcoming painting project at Diamond Path in Apple Valley. We are thrilled to be working for and with you this summer.

Building Pressure Washing Start Date  Prep/Painting Dates
1 Tuesday, 7/6 Thursday, 7/8
2 Wednesday, 7/7 Tuesday, 7/13
3 Wednesday, 7/7 Monday, 7/19
4 Wednesday, 7/7 Monday, 7/19
5 Monday, 7/19 Thursday, 7/22
6 Week of 7/19 Thursday, 7/22
7 Week of 7/19 Friday, 7/30
8 Week of 7/19 Friday, 7/30

Wednesday, August 11th: Good afternoon! 

Friday, August 6th: Greetings and TGIF! 

The crew is wrapping up on Building 8 and cleaning up as well. We’ll soon be marking areas with blue tape that indicate touch ups. Please leave the tape for the crew. They’ll return in the next week or so after we mark the tape. Thanks! 

Putting the finishing touches on Building #8.

Rolling, Rolling on the river… per Ike and Tina Turner.

Wednesday, August 4th: Good afternoon!

The crew is continuing to make progress on Buildings 7 & 8. They plan on being done with Building 7 today and finishing Building 8 tomorrow. 

Thumbs up for finishing Building 7.

Prepping and painting both buildings.

Tuesday, August 3rd: Good morning!

The crew is back onsite today continuing with the prepping and painting on Buildings 7 & 8 that they started yesterday. 

Covering all the garage doors before painting.

Our ladders are up and we’re ready to prep and paint.

Monday, August 2nd: Good afternoon! 

We can hardly believe it’s already August! 

The crew is working at Buildings 7 & 8. They are projecting to wrap up at the end of the week as well!

Taping off and covering on the top elevation.

Prep & covering windows.

Friday, July 30th: Good morning!

The crew has started the prep work for Buildings 7 and 8. They will return on Monday, 8/2 to begin painting these two buildings. Have a great weekend!

Priming is key before beginning to paint!

Prepping the railing.

Wednesday, July 28th: Greetings!

The crew will not be onsite today due to the rain. They will return when the surfaces have had time to dry so they can continue working on your project. Have a great rest of your day!

Tuesday, July 27th: Good morning!

The crew is back onsite continuing to make progress on your project. They have picked up where they left off prepping and painting building 5 & 6. 

First we spray the paint on…

Then we roll the paint on to your buildings.

Monday, July 26th: Good afternoon! 

The crew is onsite and continuing to prep, scrape, and prime areas on Buildings 5 & 6. 

The proof is in the prep.

Scrape & repeat.

Prepping and scraping at Buildings 5 & 6.

Friday, July 23rd: Good morning!

The crew is back onsite today after having to leave early yesterday from the rain. They are picking up where they left off prepping Buildings 5 and 6. 

Scraping the paint off so it is ready to be painted.

Thursday, July 22nd: Greetings!

**Update** Unfortunately due to the rain the crew had to leave early. Hopefully, they will be back tomorrow to continue working on your project but we will have to see what the weather does. Have a great rest of your day!

The crew will be finishing up with the painting of Buildings 3 and 4 today. They will also be starting to prep Buildings 5 and 6 today as well.

Painting around the door area this afternoon.

Prepping the screens before painting.

Wednesday, July 21st: Good afternoon! 

The crew is onsite today working hard on your project. They are continuing the prep and painting on Buildings 3 and 4. They are planning to start on Building 5 tomorrow. 

Taping off the garage prior to painting.

Working hard to cover all the surfaces that won’t be painted.

Tuesday, July 20th: Greetings!

The crew is onsite and continuing to make great progress with your project. They are picking up where they left off yesterday prepping and painting Buildings 3 and 4. They are currently spraying and backrolling which you can see in the pictures below.

First, we spray on the paint…

Then we back roll the paint into the substrates.

Monday, July 19th: Good morning!

The crew has started pressure washing Building 5 this morning. They will be pressure washing the remaining buildings throughout the week as well. The crew is also prepping Buildings 3 and 4 to get ready to be painted. 

Pressure washing is underway at Building 5.

Our ladder is up and we are pressure washing away.

Friday, July 16th: Greetings & Happy Friday!

The crew is continuing their prep work on Buildings 1 and 2 this morning. The surfaces have had ample time to dry so they will soon begin painting at both of these Buildings today as well. 

Prepping the deck before painting.

Thursday, July 15th: Good morning!

The crew is back onsite after being cut short yesterday due to the rain. They are continuing to prep Building 2. Tomorrow the crew will continue to paint Buildings 1 and 2. They are not able to paint today because the surfaces are still too wet so they start painting again tomorrow once they have had time to dry. 

Prepping Building 2 so that it will be ready to paint tomorrow.

The crew is working hard to prepare your building to be painted.

Wednesday, July 14th: Good afternoon!

Today the crew will just be prepping at Building 2 due to the rain that will be coming shortly. They will be back onsite tomorrow or Friday, weather permitting, to continue working on your project. 

Paint scrapings from the siding.

Tuesday, July 13th: Greetings!

The crew is continuing to prep and paint Building 1 and they have also started on Building 2. On Monday, 7/19 the crew will start washing the remaining Buildings.

Painting your building with focus!

Monday, July 12th: Good morning!

The crew is continuing to work diligently on your project as they pick up where they left off preparing Building 1 to be painted. Tomorrow they will start preparing and painting Building 2.

Prepping the doorway area.

Friday, July 9th: Good afternoon and TGIF! 

Prepping, scraping, and priming continues on Building 1. They are hoping to start painting today as well. 

Prep, prep, and more prep.

Scraping with a view👌🏻

Thursday, July 8th: Greetings!

The crew is onsite currently prepping building 1 today. 

Working hard getting building prepped!

Prepping building 1.

Thursday, July 8th: Good morning residents of Diamond Path. 

We got a bit ahead of ourselves and washed buildings 3, 4, and 5 yesterday. We apologize for not posting notices on these buildings prior to them being washed and for any confusion caused. We’ll be posting notices next week to wash the remaining buildings the week of 7/19. 

We’ve updated our TENTATIVE finishing schedule for pressure washing and also painting. Please keep in mind this is a projection and that it will likely be altered due to weather. We hope that setting some tentative dates, will give residents the timeframe needed to anticipate when crew will be working on their building. We will update the schedule as needed so please continue to check back for progress updates, changes, and weather delay information. Thank you! 

Wednesday, July 7th: Good morning!

The crew is following their route and pressure washing Building 2 currently. They are also doing carpentry at Building 7.

Pressure washing Building 2.

Working hard on repairs for Building 7.

Tuesday, July 6th: Greetings!

The crew is off and running at Diamond Path and the pressure washer is ready to roll! They have started pressure washing at Building 1 and will move on to washing Building 2 tomorrow.

Pressure washing is underway!

Getting the job done.

Friday, July 2nd: Good morning!

The carpenters are working on Building 3 currently. Enjoy your weekend!

Repairs on Building 3.

Thursday, July 1st: Greetings!

The crew is onsite and will be doing carpentry repairs on Building 2 today.

Wednesday, June 30th: Good afternoon & happy project start day!

The crew is off and running at Diamond Path and carpentry is underway! They will be doing carpentry on Buildings 1 and 2 later today once the materials arrive. 

We will return after the holiday weekend on Tuesday, 7/6 to power wash Buildings 1 and 2.

Tuesday, June 29th: Greetings Residents of Diamond Path!

Welcome to your project blog for the upcoming painting project at Diamond Path in Apple Valley!

For your project, we’ll be prepping and painting your siding, soffits, fascia/trim, chimney stacks, gas/electric meters, bollard posts, front entry railings & posts, rear deck railings, skirts, support posts, and latticework, wood windows/trim, front door frames, garage door frames, service doors/frames, and patio door frames, exterior screen frames, and pergolas… most of your paintable exterior surfaces. 

Our crew will soon begin pressure washing and performing carpentry repairs in your association. We will start performing carpentry to approved areas on Wednesday, 6/30. We will return after the holiday to begin pressure washing.

This is a large project that will likely take about 6-8 weeks to complete all buildings. However, each individual building will take less time.

The best way to obtain a project status update and any impact it may have on your daily routine will be posted here as we’ll share progress throughout, photos, and any weather delays.

Please reach out to the contacts below if you have any questions.

We’re looking forward to getting started this week!


Roell Painting

Project Manager
Ph: 763-559-5296
Email

Trent Stern

Project Manager
Ph: 612-803-5131
Email

2021
Houzz Best Of 2021 - Client Satisfaction

Houzz Best Of 2021 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2020
Best of Houzz 2020 - Client Satisfaction

Best of Houzz 2020 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2019
Best of Houzz 2019 - Client Satisfaction

Best of Houzz 2019 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2018
Best of Houzz 2018 - Client Satisfaction

Best of Houzz 2018 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2017
Best of Houzz 2017 - Client Satisfaction

Best of Houzz 2017 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2016
Best of Houzz 2016 - Client Satisfaction

Best of Houzz 2016 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2015
Best of Houzz 2015 - Client Satisfaction

Best of Houzz 2015 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.

Tags:


Leave a comment

Questions? Ask the Blue Tape Guy

roell logo

Office: 763-559-5296
Fax: 763-557-9597
7301 Penn Avenue South
Minneapolis, MN 55423