Parkvue Flats – Burnsville

Garage 1513: Painting Complete

Greetings and welcome to your project blog for the garage interior painting project at Parkvue Flats in Burnsville. We’re looking forward to completing another area of your property!


Wednesday, November 6th: Good Afternoon! 

The crew is finishing up the stenciling of the numbers as well as cleaning up. We’ll be out of here in no time and it seems just in time for the winter weather. Thank you again for your patience as we ‘took over’ your parking spaces for a bit. 

We hope you all have a great rest of the year!

Tuesday, November 5th: Greetings!

The crew is finishing up the remaining sections for spraying the top coat of the walls and ceiling. They’ll then move onto painting the numerals. We’ll be wrapped up in the next few days – thanks! 

Wrapping up the ceiling.

Spraying the final sections of the walls.

Monday, November 4th: Hello and happy Monday! 

It’s currently snowing, but our crew is cozied-up in the 1513 parking garage. They are continuing to prep and prime the final few sections of the garage ceiling and walls. They’ll be starting with the top coat shortly!

Heaters in action!

Product delivery this morning!

Prepping the last few sections of ceiling and walls.

Thursday, October 31st: Good afternoon! 

We’re Back!!! The crew has resumed their progress at the 1505 Garage. They’ve prepped the areas and covered, piping, floors, etc and are beginning to prime the walls and ceilings. Once primed, they’ll begin to paint the ceiling and then the walls. Thanks! 

The garage is prepped and covered and ready for primer.

Priming the ceilings.

Monday, September 16th: Good morning! 

The prep and painting of the 1505 Garage is on hold until the repairs and construction are complete. We are anticipating to be back onsite within the next 7-10 days to wrap up that garage and then move onto the 1503 garage. Thanks for your patience!

Wednesday, August 28th: Greetings!

The crew is rounding up the project and painting your garage stall numerals today. 

Spraying on your stall numbers- Before

After

Monday, August 26th: Good afternoon! 

The crew is wrapping up some touch ups and also cleaning up from the last month of prep and painting in your 1505 Garage. We hope you enjoy your newly painted parking spaces!

Wednesday, August 21st: Greetings! 

The crew is nearing the finish line in the 1505 garage. They are spraying the remaining sections of ceiling and walls with the top coat and will start to stencil the numbers tomorrow. Thanks!

Monday, August 19th: Hello and Happy Monday! 

It’s going to be a beautiful week!

The crew is continuing in the 1505 Garage – they are spraying the top coat on the ceiling and walls. 

Spraying down the 1505 Garage we go!

Spraying the top coat.

Friday, August 16th: Hello and TGIF! 

(Insert happy dance!)

The stenciling in 1501 is looking bright and fresh.

Spraying the last section with primer.

Tuesday, August 13th: Good afternoon!

The crew is priming their way down the 1505 garage — both the ceiling and walls. Thanks! 

Spraying the ceiling with primer.

Just us and the paint.

Spraying down the 1505 garage.

Monday, August 12th: Hello and Happy Monday! 

The week ahead in weather.

Back to the grind after the weekend! The crew is continuing to prime the ceiling and walls. They’ll also pressure wash the 2nd half o f the garage on Tuesday, 8/13. Thanks!

Friday, August 9th: Hello and TGIF! 

The crew is continuing to prep and prim the ceiling and walls of the 1505 garage. 

All set for applying the primer.

Making our way down the garage – applying the primer.

All covered and ready for spraying.

Thursday, August 8th: Good afternoon! 

The crew has completed their prep and has started to prime the garage walls and ceiling. This will take a few days for the crew to complete priming. They will then spray the top coat.

From dark and dare we say dingy… to light and bright!

Priming a section of the 1505 garage walls.

Wednesday, August 7th: Greetings!

We hope you all had a great evening with neighbor for National Night Out! 

The crew is continuing to prep the 1505 Garage. 

Rolling out the paper to cover piping and beams in the 1505 garage.

Prepping our way through the 1505 garage.

Monday, August 5th: Good afternoon! 

We hope you all had a great weekend! The crew is back in action at Parkvue after some repairs were made to the garages over the weekend. The pressure washing is complete and they are beginning their prep work— lots of paper and tape for the next few days before we spray the ceiling. 

And the prep begins…


Friday, August 2nd: Hello and TGIF!

Have a great weekend everyone!

The crew is not onsite today as there is some construction happening in the garage areas. We’ll resume as we’re able – thanks!


Thursday, August 1st: Greetings! 

We can hardly believe it’s already August! And we all know what the month of August brings… the Great Minnesota Get-Together!! We are into State Fair month and the gates open in a short 21 days!

The Countdown is on!

We are continuing to pressure wash in the 1505 Garage today – thanks!


Wednesday, July 31st: Good afternoon! 

Another beautiful day and the crew has moved onto Garage B and started their pressure washing. This will take 1-2 days, then they’ll let the areas dry before they begin prepping and covering areas. The ceilings will be painted first following by the numbering and striping- thanks!


Tuesday, July 30th: Greetings! 

We are less than a month away from the Great Minnesota Get- Together and a list of 53 new drink options has been released. We all know that that fair may be know for all of the foodie options, mostly fried and many on a stick of course! Yet, it seems we’re becoming creative with beers, spritzers, seltzers, meads, mimosas, etc etc many of which have clever names- case in point the ‘Berry Manilow’ which is a lightly hoppy beer brewed with homemade lemonade and pureed raspberries from Utepils Brewing. Check it out here!

The crew is stenciling your numbers today in Garage A. They’ll then move into Garage B to begin their prep and painting of that garage. Thanks!

Lucky Number 21!

It’s going to be a beautiful week!

We hope you all had a great weekend! The crew is cleaning up and taking down their tape and prep materials. They are also starting to paint the stall numerals. 

Taking down and removing tape.

Lots of paper and tape coming off the piping.


Friday, July 26th: Hello and TGIF! 

The crew is carrying on in Garage A and will be spraying sections of the ceiling today and into tomorrow. Once the stencils arrive, we’ll be painting the numbered stalls, posts, and areas for striping. 

Thanks! 

 It’s a white out… but not the snowy kind! Phew!

Spraying our way down the parking garage ceiling.


Wednesday, July 24th: Good afternoon! 

The crew is continuing to spray along sections of the ceiling in garage A and plans to wrap up later this week – thanks!


Monday, July 22nd: Hello and Happy Monday! 

Can you believe we’re only one month out from the ‘Great Minnesota Get-together?!’ That means one month to gear up for consuming ALL of the foods— pronto pups, Martha’s cookies, corn, cheese curds, fried pickles, and the list is endless… there are also some great groups playing at the Grandstand— check it out here

The crew is continuing to paint the Garage A ceiling today- thanks!

Prepped and primed and ready for the top coat.

Spraying the top coat on a section of the ceiling.


Friday, July 19th: Hello and TGIF! 

Inspired by this ‘Fire-y’ hot weather we’re having, we wanted to share Jimmy Fallon’s Tonight Show video of the Avengers: Endgame cast singing ‘We Didn’t Start the Fire’ — now stay cool out there! 

We are priming the final section of the ceiling today and will return tomorrow to begin with the top coat – thanks and have a great weekend!

 Patching and prepping an area of the ceiling.

 Kick the dust up. 


Thursday, July 18th: Greetings and Happy Hump Day!

As the 2019 Emmy Award nominees were recently announced, let’s throw it back to 2000 and a few of that’s year’s winners for #ThrowbackThursday:  Comedy Series- Will & Grace, Outstanding Drama Series – West Wing, Best Actor for Comedy Serious- Michael J Fox in Spin City, and Best Actress for Comedy Seriues- Patricia Heaton in Everybody Loves Raymond. Here’s the link for this year’s nominees. The Awards will be on September 22nd!

The crew is priming their way across Garage A and will begin spraying the top coat tomorrow- thanks!

Amidst the haze, we are spraying the ceilings.


Tuesday, July 16th: Greetings! 

The crew is continuing to work in Garage A and will be prepping and spraying the ceiling starting today. We want to reiterate our appreciation for you in allowing us full and unobstructed access to the garage while painting – thank you!


Monday, July 15th: Good afternoon!

It’s going to be a scorcher this week so take care of yourself and stay hydrated! And often with hot weather comes thunderstorms so check back here on the blog for weather updates and delays on your project!

The crew has prepped the garage and are now spraying the primer onto the ceilings and walls. Once the primer is applying, they’ll let it dry, and them begin to apply the top coat. The striping will be the final portion of this project.

Brush and rolling on the primer.

Spraying on the primer.


Thursday, July 11th: Good morning residents of Parkvue!

The crew has started their prep work in Garage A. They’ll be prepping the ceilings and wall for painting, which they’ll first apply the primer followed by the top coat over the next few days. We appreciate your cooperation as we’re working in your parking garage for the next several days- thanks!

Taping off and prepping the ceilings.

More beams and pipes to tape off and prep.

Prep, prep, and more prep.


Wednesday, July 10th: Good afternoon!

We are back onsite to complete the interior painting of your parking garages. The crew completed the pressure washing yesterday and will begin painting in Garage A of the 1501 Building. We’ll be prepping and painting the ceilings, walls, and also restriping the lanes. Thanks!


Roell Painting

Project Manager
Ph: 763-559-5296
Email

Tags:


Leave a comment

Questions? Ask the Blue Tape Guy

roell logo

Office: 763-559-5296
Fax: 763-557-9597
7301 Penn Avenue South