Greetings and welcome to your project blog for the upcoming painting project at Waycliffe l in Wayzata. We are thrilled to be back onsite this year to spruce up your exteriors.

Buildings Pressure Washing Start Date  Prep/Painting Start Date
Building 1 – 655 / 645 Thursday, 5/19 Monday, 5/23
Building 2 – 635 / 625 Friday, 5/20 Friday, 5/26
Building 3 – 595 / 585 Thursday, 5/26 Tuesday, 5/31
Building 4 – 350 / 360 Thursday, 5/26 Monday, 6/6

Tuesday, June 7th: Though there were a few sprinkles this morning, it wasn’t enough to deter the hardest working painters in the Twin Cities from continuing to make good progress at your association! Buildings #1-#3 have been completed, pending final inspection by your project supervisor Jesse Maki. 

Provided the weather cooperates, we project that all buildings will be completed by the end of the week.  As always, thanks a ton for having us and for the continued trust you place in our team year after year! 

Though he may not have a deerstalker hat and pipe, Jesse will be onsite with the same attention to detail as Sherlock Holmes as the project nears completion at Waycliffe 1.

Thursday, June 2nd: Good morning!

The crew is continuing to work diligently on your project. They are picking up where they left off on yesterday with their prep and painting work on Building 3.

Priming the surfaces before we apply the paint.

Prepping the door frame on Building 3.

Spraying on the paint at Building 3.

Wednesday, June 1st: Good afternoon!

Friday, May 27th: Happy Friday!

The crew has started prep work at Building 2 this morning. They are working on covering and priming surfaces to prepare for painting. The crew will return on Tuesday, 5/31. Have a great Memorial Day Weekend!

Priming is underway at Building 2.

Covering the windows.

Thursday, May 26th: Good morning!

The crew is back onsite after yesterday’s rain delay. They are continuing to work diligently on Building 1. They are also pressure washing at Building 4 currently. The crew will begin prepping and painting at Building 2 tomorrow.

Painting away on Building 1.

Painting away!

Pressure washing at Building 4.

Wednesday, May 25th: Greetings!

Tuesday, May 24th: Good afternoon!

The crew is continuing to work on prepping and painting Building 1 picking up where they left off at yesterday. 

Prepping the garage door.

Beautiful day for painting!

Photo of some prep work completed.

Monday, May 23rd: Greetings!

The crew has started prepping and painting at Building 1 this morning. Windows are being covered and taped off and painting is underway! They will return with the pressure washer on Thursday, 5/26 to pressure wash Building 3.

Ladders up and windows are covered.

The sun is out and we are ready to paint!

More windows to cover, getting the job done.

Thursday, May 19th: Good Morning!

Pressure washing is underway and your project has officially begun! The crew is working on Building 1 today and will move on to Building 2 tomorrow.

Pressure washing Building 1.

Making sure we wash every spot!

Wednesday, May 18th: Good Afternoon!

Please watch this project welcome video for more information on your project before we kick things off tomorrow!

Monday, May 16th: Greetings Residents of Waycliffe!

Welcome to your project blog for the upcoming painting project. We are looking forward to being back onsite!

Our crew will be kicking off on Thursday, May 19th with pressure washing Building 1.

We kindly request that you please remove all personal items from your deck for the pressure washing and small items from the outside of your home to allow for safe and unobstructed access for washing. Once the washing is complete, you may return the items to your deck. 

Once the substrates have had adequate time to dry, the crew will return to begin prepping and finishing of the included surfaces. We are projecting this prepping & painting to start on Monday, 5/23.

The project will take about 4-6 days to complete each home. In order to access the most current updates, check back here frequently to view any posted weather delays or other scheduling updates. Please reach out to the contacts below if you have any questions.

We’re looking forward to getting started this week!


Nick Roell

Project Manager
Ph: 763-559-5296
Email

2021
Houzz Best Of 2021 - Client Satisfaction

Houzz Best Of 2021 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2020
Best of Houzz 2020 - Client Satisfaction

Best of Houzz 2020 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2019
Best of Houzz 2019 - Client Satisfaction

Best of Houzz 2019 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2018
Best of Houzz 2018 - Client Satisfaction

Best of Houzz 2018 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2017
Best of Houzz 2017 - Client Satisfaction

Best of Houzz 2017 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2016
Best of Houzz 2016 - Client Satisfaction

Best of Houzz 2016 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2015
Best of Houzz 2015 - Client Satisfaction

Best of Houzz 2015 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.

Tags:


Leave a comment

Questions? Ask the Blue Tape Guy

roell logo

Office: 763-559-5296
Fax: 763-557-9597
7301 Penn Avenue South
Minneapolis, MN 55423