Greetings and welcome to the project blog for your painting project at Waycliffe II in Wayzata. We are thrilled to be back onsite this summer!
Building | Pressure Washing Start Date | Prep/Painting Start Date |
Building 1 – 218/228 | Monday, June 21st | Wednesday, June 23rd |
Building 2 – 293/303 | Monday, June 21st | Monday, June 28th |
Building 3 – 333/343 | Wednesday, June 23rd | Tuesday, June 29th |
Building 4 – 438/448 | Wednesday, June 23rd | Tuesday, July 6th |
Friday, July 16th: Good morning!
The crew has completed your project and has finished the touch-ups as well. It was our pleasure being onsite and working with and for you. We hope you are enjoying the newly refreshed exteriors and have a great rest of your summer!
Tuesday, July 13th: Good afternoon!
Yesterday and today the crew has been hard at work staining your deck floors. They have made great progress and will be wrapping up the staining by the end of the day today.
Friday, July 9th: Greetings and TGIF!
The crew is continuing to prep and paint at Building #4 today. After today, they’ll be completed with the painting at #1- #4. The deck floors remain to be stained.
Tuesday, July 6th: Good morning!
We hope you all had a great weekend! The crew will not be onsite today but we should be back tomorrow or Thursday, weather permitting.
Friday, July 2nd: Greetings!
Thursday, July 1st: Good morning!
Wednesday, June 30th: Greetings!
The crew is onsite today and they are prepping and painting Building 3.
Tuesday, June 29th: Good afternoon!
The crew is actively working on Buildings 1-3. We are anticipating the finishing of these three buildings by Saturday, weather permitting. We will then pick work up on Building 4 after the holiday.
Friday, June 25th: Good morning!
The crew is continuing to prep and paint Building 1 today. Have a great weekend!
Wednesday, June 23rd: Greetings!
The crew is back onsite after pressure washing Buildings 1 and 2 on Monday. They are starting the prep and painting at Building 1 today. They will also be pressure washing Buildings 3 and 4 today as well.
Monday, June 21st: Good morning & happy project start day!
The crew is off and running at Waycliffe II and the pressure washer is ready to roll! They have started washing at Building 1 and will also be washing Building 2 today. The crew will return on Wednesday, 6/23 to begin prepping and painting at Building 1.
Friday, June 18th: Greetings residents of Waycliffe II!
Welcome to your project blog for the upcoming painting project. We are looking forward to being back onsite and refreshing your exteriors.
Our crew will be kicking off on Monday, 6/21 with pressure washing Buildings 1 & 2.
We kindly request that you please remove any and all small personal belongings from the outside of your home for the pressure washing to allow for safe and unobstructed access for washing. Once the washing is complete, you may return your personal items to the outside of your home.
Once the substrates have had time to dry, the crew will be back to start prepping & painting – starting on Building 1. We are projecting this prepping & painting to start on Wednesday, 6/23.
We are projecting that each building will take between 4-6 days to complete. In order to access the most current updates, check back here frequently to view any posted weather delays or other scheduling updates. Please reach out to the contacts below if you have any questions.
We’re looking forward to getting started next week!
Roell Painting
Houzz Best Of 2021 - Client Satisfaction
Best of Houzz 2020 - Client Satisfaction
Best of Houzz 2019 - Client Satisfaction
Best of Houzz 2018 - Client Satisfaction
Best of Houzz 2017 - Client Satisfaction
Best of Houzz 2016 - Client Satisfaction
Best of Houzz 2015 - Client Satisfaction
Tags: Completed Projects