Weston Woods of Bunker Hills – Coon Rapids

Weston Woods of Bunker Hills – Coon Rapids

Project Complete

Greetings and welcome to your project blog for the upcoming stianing project at Weston Woods of Bunker Hills! We are looking forward to being onsite with you!


Route Map @ Weston Woods


Thursday, August 16th: Good afternoon!

The crew starting their staining at Building #19 this morning and will finish at Building #20 today as well. We’ll be completing a walk-through in the near future to make sure we’ve crossed our t’s and dotted our i’s. Thanks so much for having us as your association and we hope you enjoy your newly staining decks and have a great rest of the summer! 


Wednesday, August 15th: The crew has started their deck staining at Building #16 this morning. We anticipate them to complete the remaining decks by the end of tomorrow!

Applying the stain to the deck spindles.

It’s like that Jordin Sparks song, “One Step at a Time.”


Tuesday, August 14th: Hello residents of Weston Woods in Coon Rapids. 

The crew is starting today on Building #13. The crew supervisor is anticipating to be done with all of the decks on Thursday, weather permiting.

We must say the newly painted decks are looking very vibrant!

Team Roell Painting with a careful eye to stain all areas.


Monday, August 13th: Good afternoon! We hope you all had a great weekend and are staying cool today, it’s a scorcher out there!

The crew is keeping on schedule with the route and has started at Building #11 today. 

Staining one of the deck skirts. 

Boards, skirts, posts, and railings – all being stained.


Friday, August 10th: Hello and TGIF! 

The crew is starting on the 5th Building this morning and will continue to make their way along the route. We appreciate your patience and cooperation in moving items from your decks for our staining. Thanks!

The crew tackles another one of your deck floors.

Another day, another deck post being completed.


Thursday, August 9th: Hello and happy Thursday!

The crew is starting at Building #3 this morning and are staying on track to complete about 2 buildings/day – we’ll post pictures soon!

Taking care of the deck posts at Weston Woods.


Wednesday, August 8th: Good morning! 

The crew is continuing with pressure washing of your decks today and they plan to begin staining, starting at the first building, as well. We’ll post deck staining progress made by the crew later this afternoon, that way we’ll be able to better project how many buildings/decks they’ll complete in a day and you will know when to expect us at your deck. Thanks!

Update- the pressure washing is complete. The crew is staining your decks and they anticipate to move through 2 buildings/day.

 

Thorough prep is in progress @ Weston Woods.

Painting one of the deck posts. 

Board by board, the crew stains your decks.


Tuesday, August 7th: Hello!

Quick update today- the crew is resuming their pressure washing of the decks at Weston Woods. They started at Building #9 and they hope to finish all the buildings by the end of the day tomorrow. Thanks!


Monday, August 6th: Good afternoon residents of Weston Woods in Coon Rapids. We hope you all had a great weekend!

And they’re off! The crew has started their pressure washing of your decks. This will span the course of a few days. Once the washing is completed, we’ll return to the beginning of the route to start staining. Once the staining is underway, we’ll post progress updates – referring to the building numbers posted on the map above. This way we can tentatively project when we’ll be at your deck, thus needing the contents to be cleared. Thanks!

Washing and prepping your decks for staining.

One board at a time, the crew is pressure washing your decks.


Friday, August 3rd:

Welcome Video @ Weston Woods of Bunker Hills!

Good afternoon and welcome to your project blog! 

We’ll be starting your project on Monday, August 6th with pressure washing your decks. Please remove any belongings from your deck during the pressure washing. Once they’ve been washed, the crew will begin staining the decks in the same order that they were pressure washed – we’ve posted a route map above for your reference. We’re projecting to begin the staining on the first buildings on Wednesday, August 8th, weather permitting. 

Please stay tuned here on the blog for progress updates, schedule updates/changes, pictures of progress, and any weather delays should they come up. 

Thanks so much and we’re looking forward to being onsite next week!


Roell Painting

Project Manager
Ph: 763-559-5296
Email

Tags:


Questions? Ask the Blue Tape Guy

roell logo

Office: 763-559-5296
Fax: 763-557-9597
7301 Penn Avenue South
Minneapolis, MN 55423