Lilywood HOA – St. Paul
Lilywood HOA – St. Paul
Preoject Complete
Greetings and welcome to your project blog for the upcoming pressure washing and painting project. We’re looking forward to being onsite and refreshing the exteriors of your buildings!
Building | Pressure Washing Start Date | Prep/Painting Start Date |
1 | Thursday, 6/3 | Monday, 6/7 |
2 | Thursday, 6/3 | Wednesday, 6/9 |
3 | Thursday, 6/3 | Monday, 6/14 |
4 | Friday, 6/4 | Tuesday, 6/15 |
5 | Friday, 6/4 | Monday, 6/21 |
6 | Friday, 6/4 | Tuesday, 6/22 |
Tuesday, July 6th: Greetings!
The crew has completed the project and has finished the touch-ups as well. It was our pleasure being onsite. We hope you are enjoying the newly painted exteriors and have a great rest of your summer!
Friday, July 2nd: Good morning!
Wednesday, June 30th: Greetings!
The crew is back onsite today and they are working on prepping and painting the foundation.
Tuesday, June 29th: Good afternoon!
Monday, June 28th: Good morning!
The crew will not be onsite today due to the deck floors being too wet to work on from the rain last night. The crew will return tomorrow, weather permitting, to continue staining the decks.
Thursday, June 24th: Greetings!
The crew is onsite today and working hard. They are starting to stain the decks.
Tuesday, June 22nd: Good afternoon!
The crew has started the preparations on Building 6 and will be working on this Building for the remainder of the day.
Monday, June 21st: Good morning!
The crew is onsite this morning and working hard. They have finished up at Building 4 and are now starting to prep and paint at Building 5.
Friday, June 18th: Good afternoon!
Thursday, June 17th: Good morning!
The crew is continuing to work on Building 4 today. A good, durable paint application involves not only spraying, but backrolling. This ensures that the coating being applied gets “worked in” to the underlying substrate. Which you can see our crew doing in the photos below!
Wednesday, June 16th: Good afternoon!
The crew is onsite and continuing their diligent work on Building 4. They are picking up from where they left off yesterday prepping and painting.
Tuesday, June 15th: Good morning!
The crew is prepping and painting at Building 4 today. Enjoy your Tuesday!
Monday, June 14th: Greetings!
The crew is onsite today and has started to prep and paint Building 3.
Friday, June 11th: Good morning!
The crew is painting the trim on Building 2 today.
Thursday, June 10th: Good afternoon!
The crew is continuing their prepping and painting at Building 2.
Wednesday, June 9th: Greetings!
The crew is onsite today working on the prep and painting of Building 2.
Tuesday, June 8th: Good afternoon!
We wanted to share a quick update regarding the carpentry portion of the project. The materials to complete repairs, etc have been ordered and the carpentry will begin once materials arrive onsite.
As for the timeline, the painters will continue along the route above and if they need to do another pass through after carpentry repairs have been completed to paint the newly replaced/repaired areas they will! Thank you!
The crew is continuing their work on prepping and painting Building 1.
Monday, June 7th: Greetings!
Hope everyone stayed cool this weekend! The crew is onsite prepping and painting at Building 1.
Friday, June 4th: Good morning!
The crew is continuing to work their way around the route to pressure wash all of the Buildings. Have a great weekend!
Thursday, June 3rd: Good afternoon!
Happy project start day! The crew is onsite and the pressure washer is ready to roll. The crew has started to wash at Building 1 today. They will make their way around the route to pressure wash all of the buildings. Which will likely take several days to complete.
Wednesday, June 2nd: Good morning!
Welcome to your project blog for the upcoming painting project at Lilywood HOA in St. Paul!
We are thrilled to be onsite this summer. We’ll be kicking off your project with pressure washing tomorrow, June 3rd, which will take approximately 2-3 days.
We kindly request that you please remove all small personal items away from your deck for the pressure washing and small items from outside of your home to allow for safe and unobstructed access for washing. Once the washing is complete, you may return the items to their normal place.
After the surfaces have had time to dry (about 5-7 days) the crew will return to begin their prep and painting.
We are projecting 3-4 weeks to complete. The best way to obtain a project status update and any impact it may have on your daily routine will be posted here as we’ll share progress throughout, photos, and any weather delays.
Please reach out to the contacts below if you have any questions.
We’re looking forward to getting started!
Dana Clark
Houzz Best Of 2021 - Client Satisfaction
Best of Houzz 2020 - Client Satisfaction
Best of Houzz 2019 - Client Satisfaction
Best of Houzz 2018 - Client Satisfaction
Best of Houzz 2017 - Client Satisfaction
Best of Houzz 2016 - Client Satisfaction
Best of Houzz 2015 - Client Satisfaction
Tags: Completed Projects