Greetings and welcome to your project portal for the upcoming painting project at Lohmans Amhurst in St. Louis Park. We are thrilled to be working with and for you this summer!

Buildings  Pressure Washing Dates Prep/ Painting Start Date
1-3 Monday 9/13 – Wednesday 9/15 Thursday 9/16 – Wednesday, 9/22; Complete
4-5 Monday 9/13 – Wednesday 9/15 Friday 9/24 – Wednesday 9/29; Complete
6-10 Monday 9/13 – Wednesday 9/15 Wednesday, 9/29 – Tuesday, 10/5; Complete
11-13 Monday 9/13 – Wednesday 9/15 Monday, 10/4 – Wednesday 10/6; Complete
14-15 Monday 9/13 – Wednesday 9/15 Tuesday 9/21 – Monday, 9/27; Complete
16-19 Monday 9/13 – Wednesday 9/15 Wednesday 9/29 – Saturday 10/2; Complete
20-23 Monday 9/13 – Wednesday 9/15 Monday, 10/4 – Wednesday 10/6
24-26 Monday 9/13 – Thursday 9/16 Tuesday 9/21 – Monday 9/27; Complete
27-30 Monday 9/13 – Thursday 9/16  Wednesday 9/29 – Saturday 10/2; Complete
31-33 Monday 9/13 – Thursday 9/16 Monday, 10/4 – Wednesday 10/6; Complete
34-36 Monday 9/13 – Thursday 9/16 Wednesday, 10/6 – Friday 10/8

 


Thursday, October 14th: Good afternoon!

The crew has wrapped up with your project! We will be doing a walk-through to mark the areas that need touch-ups in the next few weeks. Thank you for having us!

Thursday, October 7th: Greetings!

The crew is nearing completion with your project. Area 1 should be complete along with area 2 today. Area 3 should be done by tomorrow. The crew is hoping to be completely wrapped and cleaned by Monday, October 11th. They will also be doing a walk through to mark areas with blue tape to complete touch-ups that are needed.

Wednesday, October 6th: Good afternoon!

The crew is back onsite today and are picking up where they left off yesterday. Today they are prepping and painting 11, 22, and 33.

Just getting started painting at Building 33!

Working together to get the job done at Building 22.

Tuesday, October 5th: Greetings!

The crews are continuing to work diligently on your project. Today they are prepping and painting at Buildings 10, 11, and 22.

Painting the Building 11 fence.

Working on Building 22 this afternoon!

Monday, October 4th: Good afternoon!

The crews are back onsite today. They are prepping and painting at Buildings 9, 21, and 31.

Prepping at Building 31.

Working hard on Building 9!

Painting away at Building 21.

Friday, October 1st: Good morning and happy October! 

The crews are prepping and painting at Buildings 8, 19, and 30 today. They’re on schedule to move to the next buildings on Monday. We hope you all have a great weekend!

Painting at Building 19.

Covering areas and prepping for paint.

Prep and covering around Building 8.

Thursday, September 30th: Good morning!

The crew is back onsite today and they are sticking to the schedule posted above! Today they are working on Buildings 7, 18, and 28.

Painting the fence at Building 7.

Lots of prep work happening at Building 18!

Great focus while painting the fence at Building 28.

Tuesday, September 28th: Good afternoon!

We have updated the schedule above. This is a projected schedule so it is subject to change depending on weather and other circumstances. Thank you!

Monday, September 27th: Greetings!

The crew is continuing their diligent work on your project. Today they are prepping Building 5, prepping and painting Building 16, and have completed Buildings 24-26.

Prepping Building 5.

Spraying and backrolling the fence at Building 16.

Friday, September 24th: Good afternoon and happy Friday!

The crew has pulled off a bit early today because of the rain. We are tentative to be back tomorrow and resume painting the fencing at Buildings 4, 14, and 25. Thank you!

Thursday, September 23rd: Good afternoon!

The crew is onsite today and they are picking up where they left off yesterday. Today they are prepping Building 4 and painting Building 13.

Prepping Building 4 to be ready to paint.

Spraying and back rolling the paint on Building 13.

Wednesday, September 22nd: Greetings! 

Another beautiful day to be painting your fencing at Lohmans. 

The crew are starting off at Buildings 3, 13, and 24 today and will continue to progress through the route. We are updated the table above as needed based on pace of crews and also any weather delays. Thank you!

Painting at Building 24.

Spraying at Building 13.

Hermes refreshes the fencing at Building 3.

Spraying and rolling at Building 3 fencing.

Tuesday, September 21st: Good afternoon! 

The crew has resumed hand cleaning, prep, and painting of the privacy fencing. Crews are working at Buildings 2, 13, and 24. 

Working in Area 2 on Building 13.

Prepping on Building 2.

Refreshing the fencing on Building 2.

Monday, September 20th: Greetings! 

The crew is not onsite today due to forecasted rain. They are tentative to return tomorrow. Thanks! 

Friday, September 17th: Good morning! 

We wanted to share a scheduling update. The crew is planning to be onsite Saturdays and Sundays through the duration of the project as advised by the board and also onsite manager Jim to combat upcoming rain days and assure our intent to complete the project this summer. As weather permits the crew will continue to work through the week and weekends. Thank you!

We’ve updated our map and table to reflect the push back from the rain this week and the longer time needed to finish the pressure washing. Thanks for your cooperation! 

Thursday, September 16th: Good afternoon!

The crew is picking up where they left off yesterday pressure washing. They have also begun to prep and prime.

Pressure washing the fence

Priming the fence

Wednesday, September 15th: Greetings!

The crew is continuing to pressure wash today and will begin painting tomorrow.

Working hard today!

Tuesday, September 14th: Good afternoon!

The crew is back onsite today and are picking up right where they left off yesterday pressure washing Buildings 1, 13, and 24 and along the route.

Pancho on and pressure washing away.

Monday, September 13th: Happy Project Start Day!

The crew is off and running at Lohman’s Amhurst and the pressure washer is ready to roll! The crew will be pressure washing Buildings 1, 13, and 24 today through Wednesday.

Pressure washing is underway!

Pressure washing away.

Tuesday, September 7th: Good morning! 

The crew will be onsite this week priming the newly replaced wood. We will officially begin pressure washing the fencing next week Monday, 9/13. We will be posting physical notices onsite tomorrow with further information and instruction to ready the fencing for washing and staining. We’ve posted a route map above — there are 3 phases we will complete the washing and staining in. There will be 3 crews onsite working in each area simultaneously. 

Thank you! 

Thursday, August 26th: Hello and welcome to your project blog!

For your project we’ll be pressure washing and painting the privacy fencing. 

The start date for the crew to kick off with pressure washing and painting is yet to be determined. For the washing and painting we kindly ask that you remove or tie back any greenery and/or decor from your fences to allow for safe an unobstructed access for washing and painting.

After surfaces have been washed the crew will return to begin prepping and painting the fences. The crew will follow the route above for washing, and painting. 

Overall, the project will have minimal impact on your daily routine.

The best way to obtain a project status update and any impact it may have on your daily routine will be posted here as we’ll share progress throughout, photos, and any weather delays.

Please reach out to the contacts below if you have any questions.

We’re looking forward to getting started and working with you!


Roell Painting

Project Manager
Ph: 763-559-5296
Email

2021
Houzz Best Of 2021 - Client Satisfaction

Houzz Best Of 2021 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2020
Best of Houzz 2020 - Client Satisfaction

Best of Houzz 2020 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2019
Best of Houzz 2019 - Client Satisfaction

Best of Houzz 2019 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2018
Best of Houzz 2018 - Client Satisfaction

Best of Houzz 2018 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2017
Best of Houzz 2017 - Client Satisfaction

Best of Houzz 2017 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2016
Best of Houzz 2016 - Client Satisfaction

Best of Houzz 2016 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.
2015
Best of Houzz 2015 - Client Satisfaction

Best of Houzz 2015 - Client Satisfaction

This professional was rated at the highest level for client satisfaction by the Houzz community.

 


Tags:


Comments (2)

  • Nancy Garrett

    |

    Portions of the top of my fence were not painted resulting in an unslightly view from my second floor window. I reported this earlier to Jim but this has not been corrected to date.
    Nancy Garrett
    #70 Blackwood
    P.S. paint cans and other trash left outside my fence

    Reply

    • Dana

      |

      Hi Nancy – thank you for the note. I will make sure we get back to your unit/fencing to take care of any missed areas. I can also note to remove garage, often the crew is storing cans/garbage/supplies in a few designated spots to be fully cleaned towards the end of the project. I will make sure they can tidy that area soon. Thank you!