Project Complete

Greetings and welcome to your project blog for this year’s painting project at Asbury Glen in Rosemount. We are thrilled to be onsite with you!


Thursday, August 13th: Good afternoon! 

Blue skies ahead!

The crew is back onsite and working on the remaining building – #12. We’ll soon mark touch ups and come back through to address areas needing more attention. Thanks! 

Taping off around the siding.

Taping and prepping at Building 12.

Tuesday, August 11th: Greetings! 

The crew is onsite this afternoon to prep and paint at Buildings 15 and 16.

Monday, August 10th: Good afternoon! 

The crew has returned onsite this afternoon to resume their prep and painting. They are currently working at Building 14 — Building 12 was skipped, but we’ll return that Building at the end per resident request. Thanks!

Thursday, August 6th: Greetings! 

The crew continuing onto Building 7 yesterday as well and they are working on Building 8 and 9 today too. 

Spraying the siding around the garage doors.

All hands on deck to prep.

Wednesday, August 5th: Good morning! 

The crew has moved right along to Buildings 5 and 6. They’re continuing to prep/paint about 2 Buildings each day. 

Tackling Buildings 5 and 6 today.

Prepping to paint the siding.

Tuesday, August 4th: Greetings! 

The completed Buildings 1 and 2 yesterday and they will be prepping and painting at 3 and 4 today. They’re projecting to complete about 2 building/day with continued dry weather. 

Starting prep on Buildings 3 and 4.

Off and running – prepping and covering at Asbury.

Monday, August 3rd: Good morning! 

We are off and running at Building 1 at Asbury Glen. 

The crew is working hard to prep and cover areas before we begin painting. 

Taping off edges at Building 1.

Teamwork to complete the prepwork.

Covering around garage doors.

Prep on Building 1 is underway.

Thursday, July 30th: Good morning! 

Happy Project Kick off Day! 

The crew is onsite and you can hear the hum of our pressure washers. They are tentatively planning to get through all 13 Buildings for pressure washing, but could roll into tomorrow for the last few buildings. We’ll keep you posted. 

The crew will return on Monday to begin their prep/painting at Building 1. We are anticipating to complete the project in about 3 weeks, this will project the crew to prep/paint 3-4 Buildings each week. Stay tuned for further scheduling details once they get started on Monday and know their pace. 

And they’re off!

Washing up your Buildings today at Asbury.

Tuesday, July 28th: Good afternoon! 

The crew is going to be getting started at Asbury on Thursday, 7/28. We will start off with pressure washing of all Buildings – this will take several days. 

Prep and painting will begin on Building 1 on Monday, August 3rd. 

You can continue to follow the project progress here on the blog as we’ll post frequent updates, share progress photos, and alert you of any weather delays should they come up. 

Thanks and we’ll see you onsite on Thursday!

Wednesday, July 22nd: Good morning! Welcome to your project blog for the upcoming painting project at Asbury Glen. 

For your project we’ll be prepping and finishing the 16 buildings at your association. We’ll begin with pressure washing the designated surfaces, the metal siding. Once the surfaces have had time to dry completely, we’ll return to begin our prep and painting. 

We’ll soon post a route map and tentative finishing schedule. This will allow you to know when we’ll be washing and painting at your building. 

Thank you so much for having us and we’re looking forward to getting started soon!

 


Dana Clark

Project Manager
Ph: 763-559-5296
Email

Hirsh Logo
Sherwin Williams Logo
Cabot Stain Logo
PPG Logo
Sikkens Logo
Benjamin Moore Logo

Tags:


Leave a comment

Questions? Ask the Blue Tape Guy

roell logo

Office: 763-559-5296
Fax: 763-557-9597
7301 Penn Avenue South
Minneapolis, MN 55423