Lodges at Settler’s Glen – Stillwater
Lodges at Settler’s Glen – Stillwater
Project Complete
Greetings and welcome to your project blog for the upcoming carpentry and and screen porch painting project. We’re looking forward to being onsite!
Monday, August 23rd: Good afternoon!
The crew continues to repair, prep, and paint the select screen porches. They’re working at unit 3830 to start with today. Thanks!

Working on the screen porches.

Carpentry in progress.
Friday, August 20th: Hello and TGIF!
The crew is working at Building 3840 and continues to prep, replace and paint select decking areas.
Have a great weekend!

Repairs on the screen porches.

Scraping and prepping the pillars.
Wednesday, August 18th: Good afternoon!
The crew is continuing to prep, repair and paint the select porches at Settlers Glen. They’ve made their way to 3660, 3670, and 3700 . They will continue to complete areas along the route.

Scraping the pillars.

Carpentry in progress.

Painting the frames.
Monday, August 16th: Good morning!
Welcome to your project blog for the screen porch project this summer!
We’ll be onsite completing carpentry and painting on the designated screen porches.
This is a large project that in entirety will take about 3-5 weeks to complete, however your individual porch will take less time.
Overall, this project will have minimal impact on your daily routine. The best way to obtain a project status update and any impact it may have on your daily routine will be posted here as we’ll share progress throughout, photos, and any weather delays.
Please reach out to the contact below if you have any questions.
We’re looking forward to getting started!
Trent Stern

Houzz Best Of 2021 - Client Satisfaction

Best of Houzz 2020 - Client Satisfaction

Best of Houzz 2019 - Client Satisfaction

Best of Houzz 2018 - Client Satisfaction

Best of Houzz 2017 - Client Satisfaction

Best of Houzz 2016 - Client Satisfaction

Best of Houzz 2015 - Client Satisfaction
Tags: Completed Projects